Construction Work Progress Report

The document outlines the construction activities for a new 4-lane bridge parallel to the existing MG Setu across the Ganga River in Patna, Bihar. It includes detailed descriptions of various construction tasks scheduled for July 16, 2025, such as checking of materials, reinforcement, and concreting for different bridge components. Each task is associated with specific locations, materials, and responsible engineers.

Uploaded by

Gandhi Setu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
49 views2 pages

Construction Work Progress Report

The document outlines the construction activities for a new 4-lane bridge parallel to the existing MG Setu across the Ganga River in Patna, Bihar. It includes detailed descriptions of various construction tasks scheduled for July 16, 2025, such as checking of materials, reinforcement, and concreting for different bridge components. Each task is associated with specific locations, materials, and responsible engineers.

Uploaded by

Gandhi Setu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

Construction of New 4-lane Bridge (Parallel to the Existing MG Setu) with the approaches from km 0/000 to km 14/500 across

river Ganga on NH-19 at Patna in the state of Bihar on EPC mode

RFI-16-07-2025

Chainage Chainage
[Link] Description of work Layer Width Side Material Nature of Work RFI No. Date Time SPS Engineer Side
From To

1 Checking of survey, reinforcement, shutter, formwork and concreting of pier cap of P-19A(viaduct) Pier Cap SPS/NMGS/RFI 34767 16-07-2025 11:00 AM Devendar Singh Patna

BHS FDD Retained


2 Fdd checking for Retained zone (P.A) 26th layer 13+200-13+400 BHS MCW 14mtr 13+200 13+400 26 14m Pond Ash SPS/NMGS/RFI 34768 16-07-2025 3:00 PM Neetesh Hajipur
MCW Earthfill

LHS
3 Fdd checking for R.E fill (P.A) 32nd layer 13+160-13+250 LHS MCW 9mtr 13+160 13+250 32 9m Pond Ash FDD RE Fill SPS/NMGS/RFI 34769 16-07-2025 3:20 PM Neetesh Hajipur
MCW

RHS
4 Fdd checking for R.E fill (P.A) 40th layer 13+270-13+402 RHS MCW 9mtr 13+270 13+402 40 9m Pond Ash FDD RE Fill SPS/NMGS/RFI 34770 16-07-2025 3:40 PM Neetesh Hajipur
MCW

RHS
5 Fdd checking for R.E fill (P.A) 31st layer 13+160-13+200 RHS MCW 9mtr 13+160 13+200 31 9m Pond Ash FDD RE Fill SPS/NMGS/RFI 34771 16-07-2025 4:00 PM Neetesh Hajipur
MCW

LHS
6 Fdd checking for R.E fill (Sand dust) 27th layer 12+150-12+200 LHS MCW 9mtr 12+150 12+200 27 9m Sand dust FDD RE Fill SPS/NMGS/RFI 34772 16-07-2025 4:20 PM Neetesh Hajipur
MCW

RHS
7 Fdd and level checking for Sub Grade Top (Sand dust) 12+150-12+220 RHS MCW 13.5mtr 12+150 12+220 13.5m Sand dust FDD Subgrade SPS/NMGS/RFI 34773 16-07-2025 4:40 PM Neetesh Hajipur
MCW

LHS
8 Fdd checking for R.E fill (Sand dust) 11th layer 12+800-12+850 LHS MCW 9mtr 12+800 12+850 11 9m Sand dust FDD RE Fill SPS/NMGS/RFI 34774 16-07-2025 5:00 PM Neetesh Hajipur
MCW

LHS
9 Fdd checking for R.E fill (P.A) 8th layer 12+850-12+900 LHS MCW 9mtr 12+850 12+900 8 9m Pond Ash FDD RE Fill SPS/NMGS/RFI 34775 16-07-2025 10:00 AM Neetesh Hajipur
MCW

RHS
10 Fdd checking for R.E fill (Sand dust) 42nd layer 13+505-13+518 RHS MCW 16mtr 13+505 13+518 42 16m Sand dust FDD RE Fill SPS/NMGS/RFI 34776 16-07-2025 10:20 AM Neetesh Hajipur
MCW

LHS
11 Fdd checking for R.E fill (Sand dust) 44th layer 13+518-13+527 LHS MCW 16mtr 13+518 13+527 44 16m Sand dust FDD RE Fill SPS/NMGS/RFI 34777 16-07-2025 10:40 AM Neetesh Hajipur
MCW

RHS
12 Erection and alignment checking for friction slab crash barrier 13+590-13+620 RHS MCW 13+590 13+620 Friction slab SPS/NMGS/RFI 34778 16-07-2025 11:00 AM Neetesh Hajipur
MCW

LHS
13 Level checking shuttering and concreting for friction slab crash barrier PCC 13+550-13+600 LHS MCW 13+550 13+600 Friction slab SPS/NMGS/RFI 34779 16-07-2025 11:20 AM Neetesh Hajipur
MCW

14 Reinforcement checking shuttering and concreting of Friction slab crash barrier 6nos at Old P-1 Friction slab SPS/NMGS/RFI 34780 16-07-2025 11:40 AM Chunchun Hajipur

Reinforcementchecking shuttering and concreting of Friction slab crash barrier 8nos at 9+570 RHS RHS
15 9+570 Friction slab SPS/NMGS/RFI 34781 16-07-2025 12:00 PM Chunchun Hajipur
MCW MCW

16 checking of reinforcement, shutter, formwork and concreting ofcontinuity slab of P1L(flyover) Continuity Slab SPS/NMGS/RFI 34782 16-07-2025 12:20 PM Devendar Singh Patna

17 checking of reinforcement, shutter, formwork and concreting ofcontinuity slab of P2L(flyover) Continuity Slab SPS/NMGS/RFI 34783 16-07-2025 12:40 PM Devendar Singh Patna
Chainage Chainage
[Link] Description of work Layer Width Side Material Nature of Work RFI No. Date Time SPS Engineer Side
From To

18 Checking of reinforcement, shutter, formwork and concreting of dirt wall 02nd lift of A1R(flyover) 2 Dirt Wall SPS/NMGS/RFI 34784 16-07-2025 1:00 PM Devendar Singh Hajipur

19 P-14- upper Pylon 10th lift LHS survey and concrete checking 10 Upper Pylon SPS/NMGS/RFI 34785 16-07-2025 2:20 PM S.D. Manjhi Hajipur

Rhs
20 FDD & level checking of emba top layer sand+sd 0++350 to o+450 Rhs mcw w-16m 16m Sand dust FDD Embankment SPS/NMGS/RFI 34786 16-07-2025 2:40 PM Ashok Singh Patna
mcw

Rhs
21 FDD checking of R.E fill 12th layer pond ash 1+530 to 1+550 Rhs mcw w-8m3. 1+530 1+550 12 Pond Ash FDD RE Fill SPS/NMGS/RFI 34787 16-07-2025 3:00 PM Ashok Singh Patna
mcw

RHS
22 Checking of RE panel erection 3rd layer 0+966 to 1+111 RHS MCW 0+966 1+111 3 RE Panel Erection SPS/NMGS/RFI 34788 16-07-2025 3:20 PM Ashok Singh Patna
MCW

LHS
23 Laying and Fdd checking of wmm 1st layer layer ch 14+200 to 14+280 LHS mcw w-15.5mtr 14+200 14+280 1 15.5m WMM FDD WMM SPS/NMGS/RFI 34789 16-07-2025 3:40 PM Neetesh Hajipur
mcw

24 FDD Checking of Embankment 6th layer(Pond Ash) RHS,[Link](9+080) to (9+170) (Width -24 mtr) 9+080 9+170 6 24m Pond Ash FDD Embankment SPS/NMGS/RFI 34790 16-07-2025 4:00 PM Shane Ahmad Hajipur

RHS
25 Reinforcement & shuttering checking and concreting of Box culvert raft 0+754 RHS MCW 0+754 Box Culvert SPS/NMGS/RFI 34791 16-07-2025 4:20 PM Ashok Singh Patna
MCW

26 Stay Pipe SPS/NMGS/RFI 34792 16-07-2025 8:00 AM Vijay Sindher Hajipur


P23-C08B & C08A (LHS,RHS) Stay Pipe welding & lifting

Longitudinal
27 SPS/NMGS/RFI 34793 16-07-2025 9:00 AM Vijay Sindher Hajipur
Stressing
Longitudnal T31 stressing at pier 27

Segment
28 SPS/NMGS/RFI 34794 16-07-2025 10:00 AM KP Gupta Hajipur
Stressing
P22-B19-F Stressing of segment at finishing yard in Bay-2

Longitudinal
29 SPS/NMGS/RFI 34795 16-07-2025 11:00 AM KP Gupta Hajipur
Grouting
T22-T22',T23-T23',T24-T24' (LHS & RHS) Longitudnal Tendon grouting at pier 30

Segment
30 SPS/NMGS/RFI 34796 16-07-2025 3:00 PM KP Gupta Hajipur
Stressing
P14-B14-F Stressing of segment at finishing yard in Bay-2

Longitudinal
31 SPS/NMGS/RFI 34797 16-07-2025 6:00 PM Vijay Sindher Hajipur
Stressing
Longitudnal T32 stressing at pier 30