Load Shedding
in Industrial Power Grids
Unrestricted | © Siemens 2023 | SI EA
Section 1
Five Reasons to Implement
a SICAM Load Shedding Solution
Page 2 Unrestricted | © Siemens 2023 | SI EA
Reason Nr. 1 to implement a SICAM load shedding system:
Sudden, unexpected loss of a power source
Without Load Shedding System With Load Shedding System
Loss of power source Loss of power source
Frequency drop Frequency drop
Fast shedding of unimportant loads
Blackout !!! Blackout will be avoided !!!
Page 3 Unrestricted | © Siemens 2023 | SI EA
Reason Nr. 2 to implement a SICAM load shedding system:
Mismatch between provided and consumed power (without the loss of a power source)
Without Load Shedding System With Load Shedding System
Frequency
Too high power consumption Too high power consumption
Frequency drop Frequency drop
Generation
Load Generation
Load
Shedding of unimportant loads
Blackout !!! Blackout will be avoided !!!
Page 4 Unrestricted | © Siemens 2023 | SI EA
Reason Nr. 3 to implement a SICAM load shedding system:
Automatic monitoring of contractual limits
The load shedding function
can predict possible
contractual violations
based on forecasts.
To avoid such violations
the load shedding function
can automatically trip
an appropriate number
of low priority loads.
Page 5 Unrestricted | © Siemens 2023 | SI EA
Reason Nr. 4 to implement a SICAM load shedding system:
Automatic monitoring of technical limits
Protection relays disconnect entire Load shedding can trip only
transformers/cables/overhead lines the required number of loads
Significant impact on production Much smaller impact on production
Page 6 Unrestricted | © Siemens 2023 | SI EA
Reason Nr. 5 to implement a SICAM load shedding system:
Support of public grids with low inertia
Generator (with inertia)
Decreasing number
Public Grids
Public grids will be forced to ask their
Photovoltaic
connected industrial customers for help
Increasing number
in stabilizing the grid frequency.
Wind
Increasing number
Page 7 Unrestricted | © Siemens 2023 | SI EA
Section 2
What you should know about
Frequency Based Load Shedding
Page 8 Unrestricted | © Siemens 2023 | SI EA
Frequency Based Load Shedding
1. Principle of operation
Main target for industry power grid: Stability of frequency
Insufficient generation decline of frequency
• Monitoring of predefined frequency stages
• When reaching a stage shedding of predefined loads
• Restore nominal frequency
Page 9 Unrestricted | © Siemens 2023 | SI EA
Frequency Based Load Shedding
2. Architecture
4 GOOSE messages
to indicate f violations
f relay Prot. Prot. Prot.
(81u) relay relay relay
To trip coil feeder 1
To trip coil feeder 2
To trip coil feeder x
Page 10 Unrestricted | © Siemens 2023 | SI EA
Frequency Based Load Shedding
3. Challenges with Frequency Based Load Shedding
Frequency decline:
All consumer will recognize it
Overcompensation:
Shedding too much
Frequency stages:
Low number of priorities
Not to react too fast:
At least 5 complete sine waves selectivity with fast power-based
load shedding frequency drop during start of big loads
Page 11 Unrestricted | © Siemens 2023 | SI EA
Frequency Based Load Shedding
5. Use cases
A Simple load shedding function to protect the local power grid against a sudden loss of power
B Simple load shedding against lack of power in the local power grid
(e.g. too many consumers at the same time)
C Backup load shedding for Fast Power Based Load Shedding
D Support of the connected public grid in case of lack of power
Page 12 Unrestricted | © Siemens 2023 | SI EA
Section 3
What you should know about Fast
Power Based Load Shedding
Page 13 Unrestricted | © Siemens 2023 | SI EA
Fast Power Based Load Shedding
1. Principle of operation
Public Grid
Triggered by digital events:
• Trip of circuit breaker (contingency feeder)
• Release of protection relay (contingency feeder)
Industrial Grid
The reaction is pre-calculated based on:
• Grid configuration
• Actual provided power per source
• Actual consumed power per considered load
• Predefined priority of load
• Validity of information
• Ramp-up power and spinning reserve of generators
Page 14 Unrestricted | © Siemens 2023 | SI EA
Fast Power Based Load Shedding
2. System architecture and function
Page 15 Unrestricted | © Siemens 2023 | SI EA
Fast Power Based Load Shedding
3. Integrated load shedding system
Combined use for Substation Advantages:
Automation and Load Shedding of: • Much lower cost (material, engineering,
• HMI space, heat, tests etc.)
• Controller • Better MTBF
• Network • Same look & feel at the combined HMI
• Protection relays and meters • Even 3rd party IEDs can be integrated
Page 16 Unrestricted | © Siemens 2023 | SI EA
Fast Power Based Load Shedding
4. Later extensions
Challenge:
How to assure in an energized plant the correct function of an extended load shedding system?
Two Solutions:
• Simulation of the entire system
(existing + new) in the test lab
• Optional implementation of test
function (“I would have tripped”)
Existing Loads New Loads
Page 17 Unrestricted | © Siemens 2023 | SI EA
Fast Power Based Load Shedding
5. Use cases
a) Sophisticated load shedding function to protect the local power grid against a sudden loss of power
b) By converting other events into a digital event, this load shedding function can be used flexibly
Example:
Prediction
Fast shedding of x MW
of contractual violation
Page 18 Unrestricted | © Siemens 2023 | SI EA
Section 4
Discussion Points when it comes
to Fast Power Based Load Shedding
Page 19 Unrestricted | © Siemens 2023 | SI EA
Fast Power Based Load Shedding
a) Typical discussion point: Thousands of individual loads
Example from a project:
4000 loads to be considered
Example: Conveyer belt
Trip of only 1 motor
Trip of all 3 motors
Page 20 Unrestricted | © Siemens 2023 | SI EA
Fast Power Based Load Shedding
b) Typical discussion point: Load shedding for EDGs
EDG (Emergency Diesel Generators) supply power to critical loads
Extreme example: EDG to supply power to the motors of cooling pumps in a nuclear power plant
EDG
Load shedding for M1 to M3
EDG designed to power M1, M2 and M3
M1 M2 M3
Page 21 Unrestricted | © Siemens 2023 | SI EA
Fast Power Based Load Shedding
c) Typical discussion point: GTGs and STG in combined cycle
Air Gas
Combined Cycle
Exhaust
GTG1
Hot steam
STG1
Compressor Turbine
G
Air Gas
Turbine
G
Hot combustion gas
Challenge:
Water
GTG2 Trip of GTG influences STG
Compressor Turbine
G Condenser
Page 22 Unrestricted | © Siemens 2023 | SI EA
Fast Power Based Load Shedding
d) Typical discussion point: Load shedding execution time
Load Shedding Execution Time =
time from contingency event to
closing trip contact at the load
Example requirement: „Load shedding execution time 1ms“
Page 23 Unrestricted | © Siemens 2023 | SI EA
Fast Power Based Load Shedding
e) Typical discussion point: Extension of existing 3rd party load shedding system
3rd party New
LS controller LS controller
3rd party New
communication communication
network network
3rd party 3rd party New New
IED 1 IED x IED 1 IED y
Page 24 Unrestricted | © Siemens 2023 | SI EA
Fast Power Based Load Shedding
e) Typical discussion point: Reactive load shedding
G G
Example requirement:
The load shedding system has to:
1. Observe the priorities of loads
2. Compensate the lost amount of active power
3. Compensate the lost amount of reactive power
Page 25 Unrestricted | © Siemens 2023 | SI EA
Fast Power Based Load Shedding
f) Typical discussion point: Generation Shedding
200MW
210MW 50MW
Trip
G G
Load
Shedding ≠ Generation
Shedding
Page 26 Unrestricted | © Siemens 2023 | SI EA
Section 5
What you should know about Dynamic
Power Based Load Shedding
Page 27 Unrestricted | © Siemens 2023 | SI EA
Dynamic Power Based Load Shedding
1. Principle of operation
Basic tasks:
• At the HMI the operator can define a power reserve (SR)
Industrial Grid
• The controller permanently monitors the available SR
SR3
• Too low SR unimportant loads are shed
SR1 SR2 Goal of Dynamic Power Based load Shedding:
Stability in the local grid
SR3 Power reserve, (technical and contractual limits)
Page 28 Unrestricted | © Siemens 2023 | SI EA
Dynamic Power Based Load Shedding
2. System architecture and function
Since this function
is not very time-critical,
the type of transmission
between the governor
devices and the load
shedding controller
does not matter much.
Page 29 Unrestricted | © Siemens 2023 | SI EA
Dynamic Power Based Load Shedding
3. Gradual overload
Short Spinning Reserve deficits do not lead to load shedding actions
Page 30 Unrestricted | © Siemens 2023 | SI EA
Dynamic Power Based Load Shedding
5. Smart monitoring of primary equipment
Protection Relay Dynamic Load Shedding
Loss of entire transformer/line Only reduced number of loads is shed
Page 31 Unrestricted | © Siemens 2023 | SI EA
Load Shedding
6. Load Inhibition
Solution 1 Solution 2 Solution 3 Solution 4
Load Shedding System Load Shedding System Load Shedding System Load Shedding System
Individual signals: Individual signals: Individual signals:
„Do not start load 5“ „Do not start load 5“ „Do not start load 5“
Common signal:
and and and
„Do not start additional
„Do not start load 8“ „Do not start load 8“ „Do not start load 8“
loads“
and and and
„Do not start load 19“ „Do not start load 19“ „Do not start load 19“
Individual Feeder +
Process Control Center Process Control Center Individual Feeder
Process Control Center
Page 32 Unrestricted | © Siemens 2023 | SI EA
Key Take Aways From This Training
In worst case our provided load shedding
execution time is less than 70ms
Even in working plants the SICAM Load Shedding
solution can be extended and tested
SICAM Load Shedding can be integrated
within our standard substation automation system
Page 33 Unrestricted | © Siemens 2023 | SI EA
Thank you for attending the webinar
If you are interested in our upcoming or past webinars register for
free here: Visit our
[Link] website
Stay up to date with subscriptions?
[Link]/ea-subscriptions Visit our
website
Looking for trainings?
• [Link] Visit our
website
Page 34 Unrestricted | © Siemens 2023 | SI EA
Contact
Published by Siemens 2023
Smart Infrastructure
Electrification & Automation
Mozartstraße 31 C
91052 Erlangen
Germany
For the U.S. published by
Siemens Industry Inc.
100 Technology Drive
Alpharetta, GA 30005
United States
© Siemens 2023
Subject to changes and errors. The information given in this
document/video only contains general descriptions and/or
performance features which may not always specifically reflect those
described, or which may undergo modification in the course of further
development of the products. The requested performance features
are binding only when they are expressly agreed upon
in the concluded contract.
All product designations may be trademarks or other rights
of Siemens, its affiliated companies or other companies whose use
by third parties for their own purposes could violate the rights
of the respective owner.
Page 35 Unrestricted | © Siemens 2023 | SI EA