Training Module For House Defect Inspection For
Training Module For House Defect Inspection For
FEBRUARY 2022
PROGRAMME IN BUILDING SURVEYING
DEPARTMENT OF BUILT ENVIRONMENT STUDIES AND TECNOLOGY
FACULTY OF ARCHITECTURE, PLANNING AND SURVEYING
UNIVERSITI TEKNOLOGI MARA
PERAK BRANCH SERI ISKANDAR CAMPUS
FEBRUARY 2021
PREPARED BY
NAME : NUR HIDAYAH BINTI MALIKI
SIGNATURE :
SUPERVISING LECTURER
NAME : SR DR ALIA ABDULLAH SALEH
SIGNATURE:
DATE:
2
List of Content
List of Content ........................................................................................................ 3
List of Figures ......................................................................................................... 5
List of Table ............................................................................................................ 5
CHAPTER 1: INTRODUCTION ........................................................................... 6
1.1 COMPANY PROFILE .................................................................... 7
1.2 COMPANY BACKGROUND ........................................................ 8
1.3 COMPANY VISION AND MISSION ........................................... 9
1.4 LOCATION PLAN........................................................................ 10
CHAPTER 2: LITERATURE REVIEW .............................................................. 11
2.1 RESIDENTIAL BUILDING ......................................................... 12
2.2 BUILDING DEFECT .................................................................... 12
2.2.1 Definition of Building Defect ....................................................... 12
2.3 BUILDING DEFECT INSPECTION ............................................ 13
2.3.1 Definition of Building Defect Inspection ...................................... 13
2.3.2 Types of Building Defect Inspection ............................................ 14
2.4 METHOD OF ASSESSMENT ...................................................... 15
2.5 TOOLS & EQUIPMENT USED FOR HDI .................................. 17
2.6 DEFECT CLASSIFICATION ....................................................... 20
2.6.1 Architectural Work ........................................................................ 20
2.6.2 M&E Work.................................................................................... 20
2.7 THE CONSTRUCTION INDUSTRY STANDARD FOR HOUSE
DEFECT ASSESSMENT ......................................................................... 21
2.7.1 Architectural Work .......................................................................... 21
2.7.2 Basic M & E Fittings ....................................................................... 37
2.8 HOUSE DEFECT INSPECTION REPORTING .......................... 41
2.9 THE IMPORTANT OF BUILDING DEFECT INSPECTION .... 42
2.10 CHAPTER SUMMARY................................................................ 44
CHAPTER 3: CASE STUDY ............................................................................... 45
3
3.1 INTRODUCTION TO CASE STUDY ......................................... 46
3.2 THE ASSESSMENT FOR HOUSE DEFECT INSPECTION ........... 48
3.3 HOUSE DEFECT IINSPECTION REPORT FOR KOTA
SERIBONG............................................................................................... 50
CHAPTER 4: RECOMMENDATION ................................................................. 65
4.1 PROBLEM AND RECOMMENDATION ................................... 66
CHAPTER 5: CONCLUSION ............................................................................. 67
5.1 CONCLUSION .............................................................................. 68
5.2 REFERENCE................................................................................. 69
4
List of Figures
Figure 1. 1: AVE Building ...................................................................................... 7
Figure 1. 2: AVE Logo ........................................................................................... 8
Figure 1. 3: Location Plan of AVE Building ........................................................ 10
List of Table
Table 3. 1: V The defect list for HDI .................................................................... 16
Table 3. 2: The list of Tools and Equipment for HDI........................................... 17
Table 3. 3: The Element of Architectural Work ................................................... 20
Table 3. 4: Defect Group for Architectural Work................................................. 20
Table 3. 5: List OF M&E Work ............................................................................ 20
Table 3. 6: list of Architectural Work ................................................................... 21
Table 3. 7: The Information of Clients ................................................................. 47
5
CHAPTER 1:
INTRODUCTION
6
1.1 COMPANY PROFILE
Company Adress : PT1530, Tingkat 1, Taman Iman Jaya,Wakaf Che Yeh, 15150
Kota Bharu, Kelantan.
Contact Number : 012 325 3478 (Wan Amir), 016 220 6494 (Syukran Na'im)
Email : [email protected]
7
1.2 COMPANY BACKGROUND
8
1.3 COMPANY VISION AND MISSION
VISION
Akira Ventures aims to be a company that provides professional services with integrity in
the field of construction (civil) & mechanical on the east coast, especially in Kelantan.
MISSION
Akira Ventures is committed in helping our customers to achieve our service professional
satisfaction totally in line with the company motto "professionalism within build-
inintegrity".
9
1.4 LOCATION PLAN
1.5 SUMMARY
This chapter introduce the selected company which is Akira Venture Enterprise
from company profile, its background, vision mission and its location plan.
10
CHAPTER 2:
LITERATURE REVIEW
11
2.1 RESIDENTIAL BUILDING
Residential building is made up of one or more rooms used for housing, with the
necessary facilities and utilities that satisfy the living requirements of a person or family.
Residential building for the purpose of house inspection, a structure consisting of one to
four dwelling unit used or occupied for residential purpose.
A defect is a building flaw or design mistake that reduces the value of the building,
and causes a dangerous condition. A construction defect can arise due to many factors,
such as poor workmanship or the use of inferior materials. Building defects do not appear
to have been minimized despite recent advancements in building technology. Some
common defects caused by agents such as atmospheric pollution, poor workmanship or the
use of inferior materials and climatic conditions are more frequent.
Defective building construction not only contributes to the final cost of the product
but also to the cost of maintenance, which can be substantial. Defective construction
includes activities such as compaction not done to specifications leading to ground
subsidence and eventual early deterioration of foundations. This may lead to the complete
failure of a structure. Conditions under which building construction takes place are often
far from ideal with the focus mainly being on speedy delivery. Defects resulting of
inaccurate construction can be avoided by ensuring that proper inspection mechanisms are
in place. The understanding of building defects and their causes is essential for better
performance of any building. Building defects can affect the performance of structure and
appearance of structure.
12
2.3 BUILDING DEFECT INSPECTION
13
2.3.2 Types of Building Defect Inspection
i. British Standard defined non-destructive testing (NDT) as a test that does not
impair the intended performance of the element or member under investigation.
Visual inspection is the method applied during the first survey of the structures.
The purpose is to observe for any surface discontinuities. Visual features may be
related to workmanship, structural serviceability and material deterioration.
Typical equipment used during the visual inspection includes special tapping
hammer, crack gauge, magnifying glass, binocular and camera. For buildings,
survey may be started from the outside of the building and followed by the inside
survey with particular attention given to areas at the corner or any tension area of
the building.
14
2.4 METHOD OF ASSESSMENT
a) Site Inspection
• Visual assessment
• Physical Assessment
15
Defect List Assessment
DEFECT LIST
16
2.5 TOOLS & EQUIPMENT USED FOR HDI
Tools Function
17
Tools Function
18
Tools Function
19
2.6 DEFECT CLASSIFICATION
Material & Functional Test Skim Coat or Pre-packed Plaster, Wet Area Water
Tightness Test/ Wet Area Ponding Test
Finishing
Alignment and Evenness
Crack and Damages
Hollowness and Delamination
Jointing
Table 3. 4: Defect Group for Architectural Work
Plumbing Pipes
Gully trap & floor trap
Fittings ( shower/ shower tap/ water tap & others)
M&E fittings Power points/ switches/ lights, telephone point, air- con diffuser,
fan coil unit, lighting, smoke alarm, sprinkler heads,
CATV/CCTV camera
Table 3. 5: List OF M&E Work
20
2.7 THE CONSTRUCTION INDUSTRY STANDARD FOR HOUSE DEFECT
ASSESSMENT
Floor Element
Defect Group Standard Assessment Tool
21
Defect Group Standard Assessment
Tool
Cracks and No visible damages /defects (chipping, broken tiles, Visual
Damages crack tiles,scratches, broken timber
No warpage Visual
No loose floor panels or rocking Visual
22
Internal Wall
Defect Group Standard Assessment Tool
23
Defect Standard Type of Finishes Assessment
Group Tool
Cracks and No visible damages/defects/visual Visual
Damages crack/ dent/scratches/corrosion
24
Coating
Defect Group
Type of Assessment
Standard
Finishes Tool
Finishing No stain marks Plaster / Skim Coat Visual
Ceiling/ False
ceiling/Grid System
Consistent color tone Plaster / Skim Coat Visual
Ceiling/ False
ceiling/Grid System
Paintwork with good Plaster / Skim Coat Visual
opacity and with no brush
Ceiling/ False
marks
ceiling/Grid System
25
Ceiling
Type of Assessment
Defect Group Standard Finishes Tool
Alignment Surface should be smooth, Plaster / Skim Coat Visual
and Evenness even, not wavy and notsagging Ceiling/ False
ceiling/ Grid System
Straight and aligned ceiling Plaster / Skim Coat Visual
edges Ceiling/ False
ceiling/ Grid System
Alignment of rails should False ceiling/ Grid Visual
be visually straight System
26
Defect Group Standard Type of Finishes Assessment
Tool
No rough or patchy Plaster / Skim Coat Visual
Roughness/ Ceiling/ False
Patchiness surfaces ceiling/ Grid System
No trowels marks Plaster / Skim Coat Visual
Ceiling
27
Door
Defect Group
Standard Tolerance AssessmentTool
Assessment Tool
Defect Group Standard Tolerance
28
Assessment
Defect Group Standard Tolerance
Tool
29
Defect Group Standard Tolerance Assessment
Tool
Ease of opening, closing and locking Physical
Functionality
No squeaky sound during opening Test minimum Physical
and closingof the door 1 time and
continuously auditory
(hearing)
30
Window
Assessment
Defect Group Standard Tolerance Tool
Alignment Alignment/level with wall openings Visual
andEvenness
Assessment
Defect Group Standard Tolerance Tool
Materials and No stain marks and visible damages/ Visual
Damages
defects
Louvered window with glass Visual
panels of correctlength
Assessment
Defect Standard Tolerance Tool
Group
Ease opening, closing and locking Physical
Functionality
No squeaky sound during opening Tested Physical
and closingof the window minimum 1 and auditory
time (hearing)
continuously
31
Assessment
Defect Group Standard
Tool
Internal Fixtures
32
Roof - Flat roof including exposed waterproofing, gutters and rain water down
pipes (RWDP)
abutment details
33
Visual
Gutter and RWDP inlet to be covered
toprevent chockage, where practical
Pitched Roof Including Gutters and Rain Water Down Pipes (RWDP)
34
External Finishes: Apron & Perimeter Drain
35
External Finishes: Car Porch
Assessment
Defect Group Standard
Tool
36
2.7.2 Basic M & E Fittings
Plumbing Fittings
37
Item Defect Group Standard Assessment
Tool
Joints and Gaps No visible gap Visual
Pipes
Consistent joints width and neat Visual
38
Item Defect Group Standard Assessment
Tool
Joints and Gaps No visible gap Visual
Fittings
Consistent joints width and neat Visual
Joints properly sealed and marked Visual
39
Item Defect Group Standard Tolorence Assessment
Tool
No visible gaps Visual
Installation ( Joints and Gaps
include power Consistent joints width and Visual
point, neat
telephone Neat patch-up for Visual
point, air-cond marking/penetration
diffuser, fan No visible gap between Visual
coil unit,
switches and walls
lighting,
smoke alarm, Alignment and Aligned, levelled and Visual &
sprinkler Evenness straight Spirit level
heads, Heights of switch and Visual
CATV/CCTV
marks should be consistent
camera,
speakers, Visual
Materials and No visible damages/defects
alarm system,
Damages No stain marks Visual
etc )
Visual
Consistent color tone
No operational defects Physical and
Functionality
Visual
and Safety
Physical
Securely fixed, functional
and safe
Switch can properly Tested Physical
function minim
um 1
time
Accessories Visual
No missing accessories
Defects
(Moveable No visible damages/defects Visual
parts;screw,
capping, Accessories with good fit Visual
switches and no stains
button)
40
2.8 HOUSE DEFECT INSPECTION REPORTING
House Defect Reporting were done after the building inspection. The report is for the
specific purposed of assessing the general condition of the property. It contained the
general information and defect detail. The inspection report is a valid instrument to
submitted to the client.
41
2.9 THE IMPORTANT OF BUILDING DEFECT INSPECTION
The importance of building defect inspection is to protect interest of new home buyers. It
is:
In general, new house buyers are eager to move in their new house once issuance
of vacant possession is given by the Property Developers. Building defects could
be identified through visual inspection. However ,any legal incompliance due to
the materials used and workmanship are difficult to determine by the house buyers.
Most of the vendor‟s representatives try their best to avoid from receiving many
complaints pertaining to the defects of the buildings. The situation is even worse,
when the owner lacks technical background to confirm on specification and
building condition of the property.
42
ii. The right of new house buyers are protected under provision.
In Malaysia, any new completed houses are protected under the provision of Defect
Liability Period (DLP) as stated in Clause 29 in Schedule H of Housing
Development. Any defect, or other faults in the said parcel or in the building or in
the common property which shall become apparent within a period of twenty four
month (24 months) after the date of vacant possession of the said parcel. Most of
the new home buyers are not aware of their rights, that any defect of the property
could be claimed to the vendors.
43
2.10 CHAPTER SUMMARY
This chapter were about the standard of building construction, the isnpection will
use this as their reference when inspect the defect. The methods, tools, the standard and
the important of hiring defect inspector were describe in this chapter.
44
CHAPTER 3: CASE
STUDY
45
3.1 INTRODUCTION TO CASE STUDY
The selection of the case study was meant for the study of training module for
house defect inspection for residential building.
The case study known as Kota Seribong Residency is a two-storey terrace house
located at Kota Seribong in Kota Bharu, Kelantan. Kota Seribong Residency placed at
strategic location which it close to schools, markets, supermarket, Kota Bharu city center,
government departments and many more.
46
This housing is the choice of the people because it is built with a modern and
attractive design. Residential areas are equipped with 24 -hour surveillance. The housing
area are quiet, green & peaceful area. The construction plans of various infrastructure
facilities nearby.
Client Information
47
3.2 THE ASSESSMENT FOR HOUSE DEFECT INSPECTION
The defect assessment at Kota Seribong take two days to complete. It depends on
the area of the building. All the element and component in this building was inspected by
using tools and equipment. The building element such as floor, wall, ceiling, door, window
and other components include M&E fittings and permanent fixtures such as bath tubs,
basins and kitchen cabinet. The defects were assessed by area or room for example master
bedroom, guest room, bathroom 1, bathroom 2, kitchen and family area.
48
The defect inspection performed by assess the wall in the living room, we look at
the finishing. Make sure the walls are free from paint drips or stain marks and are evenly
painted. Next, we checked the alignment and evenness. Then, see whether there are cracks
or damage on the walls. We also check the wall for hollowness and make sure there is
consistent skirting thickness and no visible gap between the wall and skirting. Finally,
ensure that all electrical outlets and switches are properly installed. Make sure the positions
of the electrical outlets and switches follow what is stated in the layout plan.
For doors, windows, components and M&E fittings, we check for alignment and
evenness, the joints and gaps, materials and damage, functionality and accessories defects.
For instance, check the windows, make sure the lead and frame corners are at the right
angles. Make sure the window can open and close smoothly.
Next, check that the windows are sealed when closed. Also, we see whether there
are scratches on the glass and check that the windows can be locked properly. Finally,
make sure there are no missing accessories and that all the accessories, such as the window
stays, handles and screws, are in good condition.
For bathroom, make sure all the taps are functioning. Pour a pail of water down
the sink to see whether the water in the basin discharges quickly. Check that the bath tub,
basin and toilet bowl are properly installed. Inspect under the bath tub and basin to ensure
there are no leaks. Also check whether the tiles have been properly installed. Make sure
there isn’t a hollow sound when we tap on the floor tiles. Also, pour a pail of water on the
floor to see whether there is a water ponding problem and whether the floor is properly
sloped.
For roof, we will use the ladder to assess the defect. We check for water tank to
make there are no dirt. We also check for wiring and piping by making sure they are
installed properly. Finally, we check for roof tile, making sure there are no sun light or
hole.
49
3.3 HOUSE DEFECT IINSPECTION REPORT FOR KOTA SERIBONG
50
1: INSPECTION DETAILS
Information
General Disclaimer
Disclaimer
The House Defect Inspection Report is prepared by Pantai Timur House Defect Inspection
for the specific purposed of assessing the general condition of the property and identifying
defects that are readily apparent at the time of inspection based on the limited visual, non-
invasive inspection. Contained in this report are general information items and defect
details.
This report is our professional opinion but not a guarantee or a warranty. The inspection is
intended to add to your knowledge of the building and help you understand the defects and
risk in it.
The report is complete and thorough, but it is a general overview, not technically
exhaustive. Specialists in each field could provide a more detailed analysis of the building
systems, but at considerably more cost and time. Our visual and limited operational
inspection provides the broadest overview of the property with less costs and time.
This inspection report is limited to deficiencies present at the time of the inspection. Roof,
mechanical equipment, plumbing and electrical systems often fail without warning. New
deficiencies can develop in buildings at any time, especially in buildings which may lie
vacant.
No responsibility is accepted in the event that the Report is used for any other purpose.
51
2: REPORT SUMMARY & ANALYSIS
52
DEFECTS ANALYSIS BY AREA CHART
Bedroom No. 3 Roof
Living
Exterior- 9% 1%
16%
Backyard
7%
Exterior – Car Kitchen
Porch 9%
10%
Bath No.1
Bath No.2 5%
6% Staircase
Foyer4%
Bedroom No.2
2%
8% Master
Bedroom No.1 Bedroom
Master Bath
6% 9%
8%
NO ITEM NO. OF
DEFECTS
1 Floor 8
2 Wall 59
3 Ceiling 8
4 Door 35
5 Window 7
6 Internal Fixtures 3
7 M&E Fittings 11
8 Others 8
TOTAL 139
53
Report Summary:
The pie charts compare the analysis of the defect area and item. It can be clearly seen that
most of the defects are at the Living and the most defect items are for Wall.
In defect analysis by area, the Exterior contributes the most at 16% and for most defect
by items will be for Wall with 43% of overall contribution. Clearly we can see the
Walling issue will be the most concern defect in the house.
In conclusion, we can see the Living and Wall in the house must be taken extra attention
for verification & rectification.
Wall
43%
Door
25%
Ceiling
6%
54
3: INTERIOR (LIVING)
Observations
3.1.1 Floors
FINISHING
3.2.1 Wall
FINISHING
55
4: INTERIOR (KITCHEN)
Observations
4.1.1 Wall
FINISHING
4.1.2 Wall
56
5: INTERIOR (BATHROOM #1)
Observations
5.1.1 Wall
FINISHING
57
6: INTERIOR (STAIRCASE)
Observations
6.1.1 Wall
FINISHING
6.2.1 Ceiling
58
7: INTERIOR (FOYER)
Observations
7.1.1 Floor
FINISHING
7.2.1 Ceiling
FINISHING
59
8: INTERIOR (MASTER BEDROOM)
Observations
8.1.1 Floor
FINISHING
8.2.1 Door
60
9: INTERIOR (MASTER BATH)
Observations
9.1.1 Wall
FINISHING
9.1.2 Wall
HOLLOWNESS
61
10: INTERIOR (BEDROOM #1)
Observations
10.1.1 Door
FUNCTIONALITY
10.3.1 Window
62
11: EXTERNAL (CAR PORCH)
Observations
11.1.1 Ceiling
11.2.1 Fence
63
3.4 SUMMARY
This chapter discuss about how the inspection was perform and the preparation for
the report to be submitted to clients.
64
CHAPTER 4:
RECOMMENDATION
65
4.1 PROBLEM AND RECOMMENDATION
Some of the problems in this study is the vital information such as building plan is
not provided for the defect inspector. It purpose is to ensure the building constructed as in
plan. For example, the position of electrical outlet and switches follow what is stated in the
layout plan. The inspector should ask the home owner for the building plan as a reference
for inspection. The plan will ease the inspector to do an inspection.
Other problem is that the inspector did not provide rating system for the building.
With defect rating, the home buyers will know the condition of their house. So that, the
clients will aware of defect condition. If the building element or building component is
defected severely, the home owner will ask the developer to fix the problem before the
expiry of defect liability period. The inspector may use QLASSIC rating system to be
included in the report before submitted to clients.
66
CHAPTER 5:
CONCLUSION
67
5.1 CONCLUSION
With this training module, the inspector will be detecting the defect
according to the QLASSIC. The home owner might able to check the defect by
themselves but it is may not accurate and not realize there may defect in the building
because they are not professionally trained to detect the defect. With the service
provided by professional inspector will help home owner to give them justice for
their home.
68
5.2 REFERENCE
https://www.theedgemarkets.com/article/how-perform-inspection-new-house
https://www.google.com/amp/s/vincivilworld.com/2021/06/11/destructive-tests-
on-hardened-concrete/amp/
doi:10.1051/matecconf/201814901015
69