Flexible Manufacturing Systems Overview
Flexible Manufacturing Systems Overview
FLEXIBLE MANUFACTURING
SYSTEMS
BITS Pilani Girish Kant Garg
Department of Mechanical Engineering
Pilani Campus
1
Contents
Course Handout
– Importance of Manufacturing (Chapter 1 and 2)
– Evaluation
– Guidelines
2
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-1, 3/8/24 BITS Pilani, Pilani Campus
What is Manufacturing?
Manufacturing (Latin word): Manus + Factus : Made by hands
A value addition process by which raw materials are
converted into finished product.
4
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-1, 3/8/24 BITS Pilani, Pilani Campus
Importance of Manufacturing
Manufacturing
37% Machine tools
75%
Mining, construction
and others
63%
5
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-1, 3/8/24 BITS Pilani, Pilani Campus
Importance of Manufacturing
Provides the hand on experience about different processes
required for production of different products.
A value addition process by which raw materials are converted
into finished product.
GDP of a country is a function of manufacturing. Higher the level
of manufacturing higher the standard of living. (In U.S,
manufacturing contributes more than 12% to GDP, employ 18% of
workforce and 40% of export).
Manufacturing accounts for 37% of global energy demand.
Manufacturing cost represent about 40% of a product’s selling
price. 6
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-1, 3/8/24 BITS Pilani, Pilani Campus
Importance of Manufacturing
7
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-1, 3/8/24 BITS Pilani, Pilani Campus
Importance of Manufacturing
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-1, 3/8/24 BITS Pilani, Pilani Campus
Importance of Manufacturing
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-1, 3/8/24 BITS Pilani, Pilani Campus
Importance of Manufacturing
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-1, 3/8/24 BITS Pilani, Pilani Campus
What is Flexible Manufacturing
System
Flexible + Manufacturing + System
Manufacturing System
It is a collection of people, equipment and procedures
organized to perform the manufacturing operations of a
company.
11
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-1, 3/8/24 BITS Pilani, Pilani Campus
What is Flexible Manufacturing
System
Manual Work
System
12
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-1, 3/8/24 BITS Pilani, Pilani Campus
What is Flexible Manufacturing
System
Worker Machine
System
13
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-1, 3/8/24 BITS Pilani, Pilani Campus
What is Flexible Manufacturing
System
Automated
System
14
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-1, 3/8/24 BITS Pilani, Pilani Campus
What is Flexible Manufacturing
System
Manufacturing Support System
15
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-1, 3/8/24 BITS Pilani, Pilani Campus
What is Flexible Manufacturing
System
System capable of processing a variety of different parts
simultaneously and quantity of production can be adjusted in
response to changing demand patterns.
A flexible manufacturing system (FMS) consists of a group of
processing workstations, interconnected by an automated
material handling and storage system, and controlled by a
distributed computer system.
16
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-1, 3/8/24 BITS Pilani, Pilani Campus
Course Handout
Textbook
References Book
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-1, 3/8/24 BITS Pilani, Pilani Campus
Course Plan - Theory
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-1, 3/8/24 BITS Pilani, Pilani Campus
Course Plan - Theory
Lecture Learning Chapter
No. Objectives Topics to be covered
No.
4 Manufacturing Production Performance Metrics
Metrics and Manufacturing Costs
3
Economics
5 Automation and Introduction to automation 4,5
Control Systems Overview of industrial control systems
6-7 Numerical Control Applications of NC, Advantages and
Disadvantages of NC
Engineering analysis of NC Positioning 7
Systems – Open loop & Closed loop
positioning systems.
NC Part Programming – Manual Part
programming, Words, format of coding
Computer Assisted Programming –
various commands, formats
Examples of programming
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-1, 3/8/24 BITS Pilani, Pilani Campus
Course Plan - Theory
Lecture Learning Chapter
No. Objectives Topics to be covered
No.
8 Review Session Review of 1-7 -
Mid Semester Examination (Closed Book)
9 Material Handling Introduction to MH systems, design
and Transport considerations.
Systems Types of Material handling equipment, 10
applications
Analysis of MH Systems – Vehicle
based & Conveyors
10 Storage Systems Conventional storage methods and
and Automatic equipment
Identification and Automated storage systems 11,12
Data Capture Automatic identification methods
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-1, 3/8/24 BITS Pilani, Pilani Campus
Course Plan - Theory
Lecture Learning Objectives Chapter
No. Topics to be covered
No.
11 Introduction to Components of a manufacturing
Manufacturing system
Systems & Single- Types of manufacturing systems 13,14
Station Single station manned cells
Manufacturing Cells Single station automated cells.
Analysis of single station cells
12 Manual Assembly Fundamentals of Manual Assembly 15
Lines lines
Analysis of Single Model Assembly
lines
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-1, 3/8/24 BITS Pilani, Pilani Campus
Course Plan - Theory
Lecture Learning Objectives Chapter
No. Topics to be covered
No.
13 Automated Fundamentals of Automated
Production Lines and Production Lines
Assembly Systems Applications of Automated Production 16,17
Lines
Analysis of Transfer Lines
Fundamentals of Automated
Assembly Systems
Analysis of Automated Assembly
Systems
14 Flexible Concept of FMS, Types of FMS 19
Manufacturing Components of FMS – Workstations,
Systems Application & benefits of FMS
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-1, 3/8/24 BITS Pilani, Pilani Campus
Course Plan - Theory
Lecture Learning Objectives Chapter
Topics to be covered
No. No.
15 Flexible FMS planning and implementation
Manufacturing issues – planning and design issues,
Systems operational issues 19
Quantitative analysis of FMS –
Bottleneck model, Extended
Bottleneck model, Sizing of FMS
16 Review Session Review of 9-15 -
Comprehensive Examination (Open Book)
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-1, 3/8/24 BITS Pilani, Pilani Campus
Course Handout
Evaluation scheme
Evaluation Name Type Duration Weight Day, Date, Session, Time
Component
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-1, 3/8/24 BITS Pilani, Pilani Campus
Guidelines
Syllabus for Mid-Semester Test (Closed Book): Topics in
Contact Hours: 1 to 16
Syllabus for Comprehensive Exam (Open Book): All topics
Elearn portal: [Link]
Refer the Elearn portal for the latest announcements and
deadlines.
25
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-1, 3/8/24 BITS Pilani, Pilani Campus
Thanks
26
BITS Pilani, Pilani Campus
EA ZC412 / MM ZC412 / DM ZC412
FLEXIBLE MANUFACTURING
SYSTEMS
BITS Pilani Girish Kant Garg
Department of Mechanical Engineering
Pilani Campus
1
Review Lecture-1
Course Handout
– Importance of Manufacturing
– Evaluation
– Guidelines
2
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-2, 10/8/24 BITS Pilani, Pilani Campus
Learning Objectives
Introduction to Production or Manufacturing Systems (Ch-1)
– Manufacturing Systems
3
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-2, 10/8/24 BITS Pilani, Pilani Campus
Manufacturing Systems
Manufacturing System
4
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-2, 10/8/24 BITS Pilani, Pilani Campus
Manufacturing System Facility
The facilities include the factory, production machines and toolings,
material handling equipments, inspection equipments, and computer
systems that control the manufacturing operations.
It also includes plant layout.
Plant layout : The way the equipment is physically arranged in the
factory.
Manufacturing systems: Logical groupings of equipment and workers
in the factory.
Production line
Stand-alone workstation and worker
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-2, 10/8/24 BITS Pilani, Pilani Campus
Manufacturing Systems
Three categories in terms of the human participation in
the processes performed by the manufacturing system:
1. Manual work systems - a worker performing one or more
tasks without the aid of powered tools.
2. Worker-machine systems - a worker operating powered
equipment.
3. Automated systems - a process performed by a machine
without direct participation of a human.
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-2, 10/8/24 BITS Pilani, Pilani Campus
Manufacturing Systems
Manual Work System
Manual Work
System
7
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-2, 10/8/24 BITS Pilani, Pilani Campus
Manufacturing Systems
Worker Machine System
8
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-2, 10/8/24 BITS Pilani, Pilani Campus
Manufacturing Systems
Automated System
9
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-2, 10/8/24 BITS Pilani, Pilani Campus
Manufacturing Support
Systems
It involves a cycle of information-processing activities that
consists of four functions:
1. Business functions - sales and marketing, order entry, cost
accounting, customer billing.
2. Product design - research and development, design
engineering, prototype.
3. Manufacturing planning - process planning, master
scheduling, MRP, capacity planning.
4. Manufacturing control - shop floor control, inventory control,
quality control.
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-2, 10/8/24 BITS Pilani, Pilani Campus
Manufacturing Support
Systems
11
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-2, 10/8/24 BITS Pilani, Pilani Campus
Automation in Production
Systems
Two categories of automation in the production system:
Automation of manufacturing systems in the factory
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-2, 10/8/24 BITS Pilani, Pilani Campus
Automated Manufacturing
Systems
Automated Manufacturing Systems operate in the factory on the
physical product.
Examples:
Automated machine tools that process parts.
Transfer lines that performs a series of machining
operations.
Automated assembly systems.
Industrial robots that perform processing or assembly
operations.
Automated material handling and storage systems to
integrate manufacturing operations.
Automatic inspection systems for quality control.
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-2, 10/8/24 BITS Pilani, Pilani Campus
Automated Manufacturing
Systems
Three basic types:
1. Fixed automation
2. Programmable automation
3. Flexible automation
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-2, 10/8/24 BITS Pilani, Pilani Campus
Fixed Automation
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-2, 10/8/24 BITS Pilani, Pilani Campus
Programmable Automation
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-2, 10/8/24 BITS Pilani, Pilani Campus
Flexible Automation
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-2, 10/8/24 BITS Pilani, Pilani Campus
Computerized Manufacturing
Support Systems
To reduce the amount of manual and clerical effort in
product design, manufacturing planning and control, and
the business functions.
Integrates computer-aided design (CAD) and computer-
aided manufacturing (CAM) in CAD/CAM.
CIM includes CAD/CAM and the business functions of
the firm.
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-2, 10/8/24 BITS Pilani, Pilani Campus
Reasons for Automating
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-2, 10/8/24 BITS Pilani, Pilani Campus
Manual Labor in Production
Systems
Is there a place for manual labor in the modern
production system?
– Answer: YES
Two aspects:
1. Manual labor in factory operations
2. Labor in manufacturing support systems
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-2, 10/8/24 BITS Pilani, Pilani Campus
Manual Labor in Factory
Operations
The long term trend is toward greater use of automated
systems to substitute for manual labor.
When is manual labor justified?
– Some countries have very low labor rates and automation
cannot be justified.
– Task is too technologically difficult to automate.
– Short product life cycle.
– Customized product requires human flexibility.
– To cope with ups and downs in demand.
– To reduce risk of product failure.
– Lack of capital
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-2, 10/8/24 BITS Pilani, Pilani Campus
Labor in Manufacturing
Support Systems
Product designers who bring creativity to the
design task.
Manufacturing engineers who
– Design the production equipment and tooling
– And plan the production methods and routings
Equipment maintenance.
Programming and computer operation.
Engineering project work.
Plant management.
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-2, 10/8/24 BITS Pilani, Pilani Campus
Automation Principles and
Strategies
1. The USA Principle
2. Ten Strategies for Automation and Process
Improvement
3. Automation Migration Strategy
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-2, 10/8/24 BITS Pilani, Pilani Campus
U.S.A Principle
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-2, 10/8/24 BITS Pilani, Pilani Campus
Ten Strategies for Automation
and Process Improvement
1. Specialization of operations
2. Combined operations
3. Simultaneous operations
4. Integration of operations
5. Increased flexibility
6. Improved material handling and storage
7. On-line inspection
8. Process control and optimization
9. Plant operations control
10. Computer-integrated manufacturing
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-2, 10/8/24 BITS Pilani, Pilani Campus
Automation Migration Strategy
for Introduction of New Products
Phase 1 – Manual production
– Single-station manned cells working independently
– Advantages: quick to set up, low-cost tooling
Phase 2 – Automated production
– Single-station automated cells operating independently
– As demand grows and automation can be justified
Phase 3 – Automated integrated production
– Multi-station system with serial operations and automated
transfer of work units between stations
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-2, 10/8/24 BITS Pilani, Pilani Campus
Automation Migration Strategy
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-2, 10/8/24 BITS Pilani, Pilani Campus
Thanks
28
BITS Pilani, Pilani Campus
EA ZC412 / MM ZC412 / DM ZC412
FLEXIBLE MANUFACTURING
SYSTEMS
BITS Pilani Girish Kant Garg
Department of Mechanical Engineering
Pilani Campus
1
Review Lecture-2
Introduction to Production or Manufacturing Systems (Ch-1)
– Manufacturing Systems
2
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
Learning Objectives
Case Study
– Optimization of tool geometry parameters for turning operations based
on the response surface methodology
3
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
Automation Principles and
Strategies
1. The USA Principle
2. Ten Strategies for Automation and Process
Improvement
3. Automation Migration Strategy
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
U.S.A Principle
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
Ten Strategies for Automation
and Process Improvement
1. Specialization of operations
2. Combined operations
3. Simultaneous operations
4. Integration of operations
5. Increased flexibility
6. Improved material handling and storage
7. On-line inspection
8. Process control and optimization
9. Plant operations control
10. Computer-integrated manufacturing
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
Automation Migration Strategy
for Introduction of New Products
Phase 1 – Manual production
– Single-station manned cells working independently
– Advantages: quick to set up, low-cost tooling
Phase 2 – Automated production
– Single-station automated cells operating independently
– As demand grows and automation can be justified
Phase 3 – Automated integrated production
– Multi-station system with serial operations and automated
transfer of work units between stations
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
Automation Migration Strategy
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
Manufacturing Process
(Modelling and Optimization)
9
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
Manufacturing Process
(Modelling and Optimization)
• Predictive Modelling
– Analytical
– Numerical
– Empirical
• Optimization
– Conventional (Taguchi, RSM)
10
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
Mechanism of chip formation
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
Mechanism of chip formation
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
Mechanism of chip formation
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
Mechanism of chip formation
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
Mechanism of chip formation
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
Mechanism of chip formation
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
Mechanism of chip formation
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
Mechanism of chip formation
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
Mechanism of chip formation
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
Mechanism of chip formation
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
Mechanism of chip formation
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
Mechanism of chip formation
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
Mechanism of chip formation
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
Mechanism of chip formation
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
Mechanism of chip formation
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
Mechanism of chip formation
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
Mechanism of chip formation
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
Mechanism of chip formation
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
Mechanism of chip formation
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
Mechanism of chip formation
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
Mechanism of chip formation
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
Mechanism of chip formation
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
Mechanism of chip formation
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
Mechanism of chip formation
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
Mechanism of chip formation
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
Mechanism of chip formation
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
Mechanism of chip formation
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
Mechanism of chip formation
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
Mechanism of chip formation
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
Mechanism of chip formation
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
Mechanism of chip formation
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
Mechanism of chip formation
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
Numerical Modelling
(Machining) - Results
43
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
Numerical Modelling (Machining)
2d-fem simulation of the orthogonal high speed cutting process
Wear modelling in mild steel orthogonal cutting when using uncoated carbide
tools
Estimation of tool wear in orthogonal cutting using the finite element analysis
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
Empirical Modelling
Response
Artificial
Surface
Neural
Methodology
Network
Empirical
Models
Support Fuzzy
Vector Set
Machines Theory
45
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
Empirical Modelling (Machining)
Integrated ANN-GA for estimating the minimum value for machining
performance
Surface roughness (Ra) prediction model for turning of AISI 1019 steel using
response surface methodology and Box-Cox transformation
Power consumption and tool life models for the production process
Surface roughness predictive modeling neural networks versus regression
Support vector machines models for surface roughness prediction in CNC
turning of AISI 304 austenitic stainless steel
Application of fuzzy logic and regression analysis for modeling surface
roughness in face milling
A rule-based system for trade-off among energy consumption, tool life, and
productivity in machining process
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
Optimization (Machining)
A method integrating Taguchi, RSM and MOPSO to CNC machining parameters
optimization for energy saving
Optimization of machining parameters and cutting fluids during nano-fluid based
minimum quantity lubrication turning of titanium alloy by using evolutionary
techniques
Optimization of machining parameters considering minimum cutting fluid
consumption
Selection of optimum parameters in multi-pass face milling for maximum energy
efficiency and minimum production cost
Empirical models for specific energy consumption and optimization of cutting
parameters for minimizing energy consumption during turning
An energy consumption optimization strategy for CNC milling
Multi-objective optimization of milling parameters: the trade offs between energy,
production rate and cutting quality.
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-3, 17/8/24 BITS Pilani, Pilani Campus
BITS Pilani
Pilani Campus
49
BITS Pilani, Pilani Campus
EA ZC412 / MM ZC412 / DM ZC412
FLEXIBLE MANUFACTURING
SYSTEMS
BITS Pilani Girish Kant Garg
Department of Mechanical Engineering
Pilani Campus
1
Review Lecture - 3
Case Study
Optimization of tool geometry parameters for turning operations
based on the response surface methodology
2
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
BITS Pilani
Pilani Campus
Facility Layout
Process Layout
Part Families and Machine Groups
Cellular Manufacturing
Analysis of Cellular Manufacturing
4
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Production Facilities
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Basic Layouts
Process layout
group similar activities together according to process or
function they perform
Product layout
arrange activities in line according to sequence of operations
for a particular product or service
Fixed-position layout
are used for projects in which product cannot be moved
6
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Production Quantity
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Product Variety
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Low Production Quantity
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Fixed-Position Layout
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Fixed-Position Layout
• Typical of projects
• Bulky, heavy items
• Equipment, workers & materials brought to site
• Highly skilled labor
• Typically low fixed cost
• Often high variable costs
11
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Medium Production Quantities
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Process Layout
13
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
High Production
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Product Layout
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Comparison of Product and
Process Layout
Product Process
Description Sequential Functional
arrangement of grouping of
activities activities
Continuous, mass Intermittent, job
Type of process
production, mainly shop, batch
assembly production, mainly
fabrication
Product Standardized, Varied, made to
made to stock order
Demand Stable Fluctuating
Volume High Low
Equipment Special purpose General purpose
16
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Comparison of Product and
Process Layout
Product Process
Workers Limited skills Varied skills
Inventory Low in-process, high High in-process, low
finished goods finished goods
Storage space Small Large
Material handling Fixed path (conveyor) Variable path (forklift)
Aisles Narrow Wide
Scheduling Part of balancing Dynamic
Layout decision Line balancing Machine location
Goal Equalize work at each Minimize material
station handling cost
Advantage Efficiency Flexibility
17
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Designing Process Layout
18
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Block Diagramming
Unit load Steps
• quantity in which • Create From/To chart or load
material is normally summary chart
moved • Calculate composite (two way)
movements
Nonadjacent load • Develop trial layouts minimizing
• distance farther number of nonadjacent loads
than the next block
19
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Example
Barko, Inc. makes bark scalpers, processing equipment that strips the bark off trees and turns
it into nuggets or mulch for gardens. The facility that makes bark scalpers is a small-job shop
that employs 50 workers and is arranged into five departments:
1) bar stock cutting 2)Sheet metal 3)Machining 4) Painting 5) Assembly
The average number of loads transported between the five departments per month is
given in the accompanying load summary chart. The current layout of the facility is
shown schematically on the 2 × 3 grid. There is quite a bit of flexibility in the facility,
as indicated by six possible locations available for five departments.
20
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Example
Forklift used in the facility is flexible allowing horizontal, vertical and diagonal
movement of material.
Management anticipates that a new plant will soon be necessary and would
like to know if a similar layout is to be used or if a better layout can be designed.
Propose a new layout on a 2 X 3 grid that will minimize the number of nonadjacent
loads.
21
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Example
Nonadjacent Loads
110+40=150
110
100 200
1 2 3
150 50 50
60
4 5
40
Grid 1
22
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Example
Nonadjacent Loads: 0
2 3 200 loads
2 4 150 loads
1 3 110 loads
1 2 100 loads
4 5 60 loads
3 5 50 loads
2 5 50 loads
3 4 40 loads
1 4 0 loads
1 5 0 loads
23
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Example
• Block Diagram
• type of schematic layout diagram; includes space requirements
(a) Initial block diagram (b) Final block diagram
1 4
1 2 4 2
3 5 3 5
24
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Problem - 1
Avalanche, Inc. is a manufacturer of premium snow skis. The work is a combination
of precision machining and skilled craftsmanship. Before completion, skis are
processed back and forth between six different departments: (1) molding, (2) cutting,
(3) fiberglass weaving, (4) gluing, (5) finishing, and (6) waxing. Avalanche is opening
a new production facility and wants to lay it out as efficiently as possible. The number
of loads of material moved from department to department at existing operations in
other plants is shown below. Arrange the department for Avalanche’s new plant in a 2
3 grid so that nonadjacent loads are minimized.
25
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Problem - 2
ABC company has recently changed management, and the new owners want to revise
the current layout. The store performs six main services: (1), (2), (3), (4), (5), and (6).
Each is located in a separate department, as shown here. The load summary chart
gives the current level of interaction between the departments. Calculate the number of
nonadjacent loads for the current layout. Design an alternative layout to minimize the
number of nonadjacent loads.
26
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Relationship Diagramming
• Muther’s grid
format for displaying manager
preferences for department
locations
• Schematic diagram that uses
weighted lines to denote
location preference
27
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Relationship Diagramming
(a) Relationship diagram of original layout
Key: A
E
I
Stockroom Toolroom Production
O
U
X
28
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Relationship Diagramming
(b) Relationship diagram of revised layout
Stockroom
Offices Shipping
and
receiving
29
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Thanks
30
BITS Pilani, Pilani Campus
EA ZC412 / MM ZC412 / DM ZC412
FLEXIBLE MANUFACTURING
SYSTEMS
BITS Pilani Girish Kant Garg
Department of Mechanical Engineering
Pilani Campus
1
Learning Objectives
Facility Layout
Process Layout
Part Families and Machine Groups
Cellular Manufacturing
Analysis of Cellular Manufacturing
2
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Production Facilities
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Basic Layouts
Process layout
group similar activities together according to process or
function they perform
Product layout
arrange activities in line according to sequence of operations
for a particular product or service
Fixed-position layout
are used for projects in which product cannot be moved
4
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Production Quantity
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Product Variety
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Low Production Quantity
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Fixed-Position Layout
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Fixed-Position Layout
• Typical of projects
• Bulky, heavy items
• Equipment, workers & materials brought to site
• Highly skilled labor
• Typically low fixed cost
• Often high variable costs
9
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Medium Production Quantities
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Process Layout
11
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
High Production
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Product Layout
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Comparison of Product and
Process Layout
Product Process
Description Sequential Functional
arrangement of grouping of
activities activities
Continuous, mass Intermittent, job
Type of process
production, mainly shop, batch
assembly production, mainly
fabrication
Product Standardized, Varied, made to
made to stock order
Demand Stable Fluctuating
Volume High Low
Equipment Special purpose General purpose
14
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Comparison of Product and
Process Layout
Product Process
Workers Limited skills Varied skills
Inventory Low in-process, high High in-process, low
finished goods finished goods
Storage space Small Large
Material handling Fixed path (conveyor) Variable path (forklift)
Aisles Narrow Wide
Scheduling Part of balancing Dynamic
Layout decision Line balancing Machine location
Goal Equalize work at each Minimize material
station handling cost
Advantage Efficiency Flexibility
15
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Designing Process Layout
16
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Block Diagramming
Unit load Steps
• quantity in which • Create From/To chart or load
material is normally summary chart
moved • Calculate composite (two way)
movements
Nonadjacent load • Develop trial layouts minimizing
• distance farther number of nonadjacent loads
than the next block
17
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Example
Barko, Inc. makes bark scalpers, processing equipment that strips the bark off trees and turns
it into nuggets or mulch for gardens. The facility that makes bark scalpers is a small-job shop
that employs 50 workers and is arranged into five departments:
1) bar stock cutting 2)Sheet metal 3)Machining 4) Painting 5) Assembly
The average number of loads transported between the five departments per month is
given in the accompanying load summary chart. The current layout of the facility is
shown schematically on the 2 × 3 grid. There is quite a bit of flexibility in the facility,
as indicated by six possible locations available for five departments.
18
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Example
Forklift used in the facility is flexible allowing horizontal, vertical and diagonal
movement of material.
Management anticipates that a new plant will soon be necessary and would
like to know if a similar layout is to be used or if a better layout can be designed.
Propose a new layout on a 2 X 3 grid that will minimize the number of nonadjacent
loads.
19
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Example
Nonadjacent Loads
110+40=150
110
100 200
1 2 3
150 50 50
60
4 5
40
Grid 1
20
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Example
Nonadjacent Loads: 0
2 3 200 loads
2 4 150 loads
1 3 110 loads
1 2 100 loads
4 5 60 loads
3 5 50 loads
2 5 50 loads
3 4 40 loads
1 4 0 loads
1 5 0 loads
21
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Example
• Block Diagram
• type of schematic layout diagram; includes space requirements
(a) Initial block diagram (b) Final block diagram
1 4
1 2 4 2
3 5 3 5
22
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Problem - 1
Avalanche, Inc. is a manufacturer of premium snow skis. The work is a combination
of precision machining and skilled craftsmanship. Before completion, skis are
processed back and forth between six different departments: (1) molding, (2) cutting,
(3) fiberglass weaving, (4) gluing, (5) finishing, and (6) waxing. Avalanche is opening
a new production facility and wants to lay it out as efficiently as possible. The number
of loads of material moved from department to department at existing operations in
other plants is shown below. Arrange the department for Avalanche’s new plant in a 2
3 grid so that nonadjacent loads are minimized.
23
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Problem - 2
ABC company has recently changed management, and the new owners want to revise
the current layout. The store performs six main services: (1), (2), (3), (4), (5), and (6).
Each is located in a separate department, as shown here. The load summary chart
gives the current level of interaction between the departments. Calculate the number of
nonadjacent loads for the current layout. Design an alternative layout to minimize the
number of nonadjacent loads.
24
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-4, 24/8/24 BITS Pilani, Pilani Campus
Relationship Diagramming
• Muther’s grid
format for displaying manager
preferences for department
locations
• Schematic diagram that uses
weighted lines to denote
location preference
25
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Relationship Diagramming
(a) Relationship diagram of original layout
Key: A
E
I
Stockroom Toolroom Production
O
U
X
26
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Relationship Diagramming
(b) Relationship diagram of revised layout
Stockroom
Offices Shipping
and
receiving
27
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Process Layout
Assembly
4 6 7 9
5 8
2 10 12
1 3 11
A B C Raw materials
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Route Matrix
Machines
Parts 1 2 3 4 5 6 7 8 9 10 11 12
A x x x x x
B x x x x
C x x x
D x x x x x
E x x x
F x x x
G x x x x
H x x x
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Reordered route Matrix
Machines
Parts 1 2 4 8 10 3 6 9 5 7 11 12
A x x x x x
D x x x x x
F x x x
C x x x
G x x x x
B x x x x
H x x x
E x x x
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Revised Cellular Layout
Assembly
8 10 9 12
11
4 Cell 1 Cell 2 6 Cell 3
7
2 1 3 5
A C B
Raw materials
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Overview of Group Technology
32
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Group Technology (GT) Defined
33
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
When to Use GT and
Cellular Manufacturing
34
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Problems in Implementing GT
35
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Part Families and
Cellular Manufacturing
36
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Part Family
37
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Part Families
Two parts that are identical in shape and size but quite
different in manufacturing: (a) 1,000,000 units/yr, tolerance
= 0.010 inch, 1015 CR steel, nickel plate; (b) 100/yr,
tolerance = 0.001 inch, 18-8 stainless steel
38
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Part Families
39
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Ways to Identify Part Families
40
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Intuitive Grouping
41
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Parts Classification and Coding
42
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Parts Classification and Coding
43
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Parts Classification and Coding
44
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Production Flow Analysis (PFA)
45
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Steps in Production Flow
Analysis
46
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Process Layout
Assembly
4 6 7 9
5 8
2 10 12
1 3 11
A B C Raw materials
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Route Matrix
Machines
Parts 1 2 3 4 5 6 7 8 9 10 11 12
A x x x x x
B x x x x
C x x x
D x x x x x
E x x x
F x x x
G x x x x
H x x x
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Reordered route Matrix
Machines
Parts 1 2 4 8 10 3 6 9 5 7 11 12
A x x x x x
D x x x x x
F x x x
C x x x
G x x x x
B x x x x
H x x x
E x x x
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Revised Cellular Layout
Assembly
8 10 9 12
11
4 Cell 1 Cell 2 6 Cell 3
7
2 1 3 5
A C B
Raw materials
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Rank Order Clustering
51
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Rank Order Clustering
Apply the rank order clustering technique to the part machine incidence matrix in
the following table to identify logical part families and machine groups. Parts are
identified by letters and machines are identified numerically.
53
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Problem-2
Apply the rank order clustering technique to the part machine incidence matrix in
the following table to identify logical part families and machine groups. Parts are
identified by letters and machines are identified numerically.
54
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Problem-3
Jetaway, a small manufacturer of replacement parts for the aircraft industry, had always
maintained a simple layout—all like machines were located together. That way the firm could
be as flexible as possible in producing small amounts of the variety of parts its customers
required. No one questioned the production arrangement until Chris Munnelly started to work
for the company. Chris was actually hired to upgrade Jetaway’s computer system. In the process
of creating a database of part routings, Chris began to see similarities in the parts produced. A
part routing matrix for nine of the most popular parts is shown below, along with a schematic of
the factory layout.
Chris, who was already tired of being a programmer, decided to reorder the matrix
and see what he could find. If he could identify distinct part families, he could reorganize the
placement of machines into the cells he had been reading about in his business magazines.
Maybe then someone would notice his management potential. Help Chris gain status in
Jetaway by creating a cellular layout for the company. Show your results in a schematic
diagram. Be sure to include the reordered routing matrix.
55
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Problem-3
56
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Thanks
57
BITS Pilani, Pilani Campus
EA ZC412 / MM ZC412 / DM ZC412
FLEXIBLE MANUFACTURING
SYSTEMS
BITS Pilani Girish Kant Garg
Department of Mechanical Engineering
Pilani Campus
1
Learning Objectives
Facility Layout
Process Layout
Part Families and Machine Groups
Cellular Manufacturing
Analysis of Cellular Manufacturing
2
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Overview of Group Technology
3
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Group Technology (GT) Defined
4
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
When to Use GT and
Cellular Manufacturing
5
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Problems in Implementing GT
6
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Part Families and
Cellular Manufacturing
7
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Part Family
8
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Part Families
Two parts that are identical in shape and size but quite
different in manufacturing: (a) 1,000,000 units/yr, tolerance
= 0.010 inch, 1015 CR steel, nickel plate; (b) 100/yr,
tolerance = 0.001 inch, 18-8 stainless steel
9
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Part Families
10
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Ways to Identify Part Families
11
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Intuitive Grouping
12
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Parts Classification and Coding
13
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Parts Classification and Coding
14
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Parts Classification and Coding
15
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Production Flow Analysis (PFA)
16
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Steps in Production Flow
Analysis
17
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Process Layout
Assembly
4 6 7 9
5 8
2 10 12
1 3 11
A B C Raw materials
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Route Matrix
Machines
Parts 1 2 3 4 5 6 7 8 9 10 11 12
A x x x x x
B x x x x
C x x x
D x x x x x
E x x x
F x x x
G x x x x
H x x x
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Reordered route Matrix
Machines
Parts 1 2 4 8 10 3 6 9 5 7 11 12
A x x x x x
D x x x x x
F x x x
C x x x
G x x x x
B x x x x
H x x x
E x x x
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Revised Cellular Layout
Assembly
8 10 9 12
11
4 Cell 1 Cell 2 6 Cell 3
7
2 1 3 5
A C B
Raw materials
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Rank Order Clustering
22
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Rank Order Clustering
Apply the rank order clustering technique to the part machine incidence matrix in
the following table to identify logical part families and machine groups. Parts are
identified by letters and machines are identified numerically.
24
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Problem-2
Apply the rank order clustering technique to the part machine incidence matrix in
the following table to identify logical part families and machine groups. Parts are
identified by letters and machines are identified numerically.
25
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Problem-3
Jetaway, a small manufacturer of replacement parts for the aircraft industry, had always
maintained a simple layout—all like machines were located together. That way the firm could
be as flexible as possible in producing small amounts of the variety of parts its customers
required. No one questioned the production arrangement until Chris Munnelly started to work
for the company. Chris was actually hired to upgrade Jetaway’s computer system. In the process
of creating a database of part routings, Chris began to see similarities in the parts produced. A
part routing matrix for nine of the most popular parts is shown below, along with a schematic of
the factory layout.
Chris, who was already tired of being a programmer, decided to reorder the matrix
and see what he could find. If he could identify distinct part families, he could reorganize the
placement of machines into the cells he had been reading about in his business magazines.
Maybe then someone would notice his management potential. Help Chris gain status in
Jetaway by creating a cellular layout for the company. Show your results in a schematic
diagram. Be sure to include the reordered routing matrix.
26
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Problem-3
27
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-5, 31/8/24 BITS Pilani, Pilani Campus
Cellular Manufacturing
28
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-6, 7/9/24 BITS Pilani, Pilani Campus
Composite Part Concept
29
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-6, 7/9/24 BITS Pilani, Pilani Campus
Composite Part Concept
30
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-6, 7/9/24 BITS Pilani, Pilani Campus
Part Features and Corresponding
Manufacturing Operations
31
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-6, 7/9/24 BITS Pilani, Pilani Campus
Machine Cell Designs
1. Single machine
2. Multiple machines with manual handling
Often organized into U-shaped layout
3. Automated cell – automated processing and integrated
handling
Flexible manufacturing cell
Flexible manufacturing system
32
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-6, 7/9/24 BITS Pilani, Pilani Campus
Machine Cell with Manual
Handling
33
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-6, 7/9/24 BITS Pilani, Pilani Campus
Machine Cell Layouts
34
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-6, 7/9/24 BITS Pilani, Pilani Campus
Cell with Semi-Integrated
Handling
35
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-6, 7/9/24 BITS Pilani, Pilani Campus
Four Types of Part Moves in
Cellular Manufacturing
36
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-6, 7/9/24 BITS Pilani, Pilani Campus
Arranging Machines in a GT cell
37
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-6, 7/9/24 BITS Pilani, Pilani Campus
Hollier Method
38
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-6, 7/9/24 BITS Pilani, Pilani Campus
Example
39
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-6, 7/9/24 BITS Pilani, Pilani Campus
Problem-3
40
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-6, 7/9/24 BITS Pilani, Pilani Campus
Problem-4
• In problem-2, two logical machine groups are identified. For each group
determine the (a) the most logical sequence of machines for this data (b)
Construct the network diagram for the data (c) Compute the percentage of in-
sequence moves, by-passing moves and backtracking moves.
41
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-6, 7/9/24 BITS Pilani, Pilani Campus
Thanks
42
BITS Pilani, Pilani Campus
EA ZC412 / MM ZC412 / DM ZC412
FLEXIBLE MANUFACTURING
SYSTEMS
BITS Pilani Girish Kant Garg
Department of Mechanical Engineering
Pilani Campus
1
BITS Pilani
Pilani Campus
3
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-7, 14/9/24 BITS Pilani, Pilani Campus
Operation Cycle Time
Cycle time:
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-7, 14/9/24 BITS Pilani, Pilani Campus
Production rate (Rp)
• Batch production
• Job shop production
• Mass production
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-7, 14/9/24 BITS Pilani, Pilani Campus
Types of discrete production
(a) Job shop, Q = 1, (b) batch production, sequential, (c) batch production,
simultaneous, (d) quantity mass production, (e) flow line mass production
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-7, 14/9/24 BITS Pilani, Pilani Campus
Production Rate
Batch production:
Batch time in min,
Tb = Tsu + QTc
Tb = Batch processing time (min/batch)
Tsu = Setup time to prepare for the batch (min/batch).
Q = Batch quantity (pc/batch).
Tc = Cycle time per work unit (min/cycle).
Average production time per work unit
Tp = Tb/Q
Production rate
Rp = 1/Tp
Rp = 60/Tp
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-7, 14/9/24 BITS Pilani, Pilani Campus
Production Rate
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-7, 14/9/24 BITS Pilani, Pilani Campus
Ex:1
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-7, 14/9/24 BITS Pilani, Pilani Campus
Ex:2
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-7, 14/9/24 BITS Pilani, Pilani Campus
Ex:3
A batch production operation has a machine setup time of 3.0
hours and a processing time of 1.60 min per cycle. Two parts are
produced each cycle. No tool handling time is included in the
cycle. Part handling time each cycle is 45 sec. It consists of the
worker obtaining two starting work units from a parts tray,
loading them into the machine, and then after processing,
unloading the completed units and placing them into the same
tray. Each tray holds 24 work units. When all of the starting work
units have been replaced with completed units, the tray of
completed parts is moved aside and a new tray of starting parts
is moved into position at the machine. This irregular work
element takes 3.0 min. Batch quantity is 2400 units. Determine
(a) average cycle time, (b) time to complete the batch, and (c)
average production rate.
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-7, 14/9/24 BITS Pilani, Pilani Campus
Ex:4
A flow line mass production operation consists of eight manual
workstations. Work units are moved synchronously and
automatically between stations, with a transfer time of 15 sec.
The manual processing operations performed at the eight
stations take 40 sec, 52 sec, 43 sec, 48 sec, 30 sec, 57 sec,
53 sec, and 49 sec, respectively. Determine (a) cycle time for
the line, (b) time to process one work unit through the eight
workstations, (c) average production rate, and (d) time to
produce 10,000 units.
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-7, 14/9/24 BITS Pilani, Pilani Campus
Production Capacity
Production capacity is the maximum rate of output that a production
facility is able to produce under a given set of operating conditions.
Plant capacity for facility in which parts are made in one operation
PC = n Hpc Rp
where
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-7, 14/9/24 BITS Pilani, Pilani Campus
Ex:1
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-7, 14/9/24 BITS Pilani, Pilani Campus
Utilization
Utilization:
It refers to the amount of output of a production facility
relative to its capacity.
where
Q = quantity actually produced,
PC = production capacity
Utilization can be defined as the proportionate of time that
the facility is operating relative to the time available under
the definition of capacity.
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-7, 14/9/24 BITS Pilani, Pilani Campus
Ex:2
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-7, 14/9/24 BITS Pilani, Pilani Campus
Availability
Availability:
It is a common measure of reliability for equipment.
It can be defined using two reliability terms mean time
between failures (MTBF) and mean time to repair (MTTR).
MTBF: Average length of time the piece of equipment
runs between breakdowns.
MTTR: Average time required to service the equipment
and put it back into operation when a breakdown occurs.
Calculation of availability:
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-7, 14/9/24 BITS Pilani, Pilani Campus
Availability-MTBF and MTTR
Defined
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-7, 14/9/24 BITS Pilani, Pilani Campus
Ex:3
The turret lathe section has six machines, all devoted to the
production of the same part. The section operates 10
shifts/week. The number of hours per shift averages 8.0.
Average production rate of each machine is 17 unit/hour.
Determine the weekly production capacity of the turret lathe
section. If the availability of the machines (A) = 90% and the
utilization of machines U=80%. Determine the expected plant
output.
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-7, 14/9/24 BITS Pilani, Pilani Campus
Manufacturing Costs
20
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-7, 14/9/24 BITS Pilani, Pilani Campus
Fixed and Variable Costs
21
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-7, 14/9/24 BITS Pilani, Pilani Campus
Manufacturing Costs
22
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-7, 14/9/24 BITS Pilani, Pilani Campus
Manufacturing Costs
23
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-7, 14/9/24 BITS Pilani, Pilani Campus
Typical Manufacturing Costs
(J Black)
24
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-7, 14/9/24 BITS Pilani, Pilani Campus
Overhead Rates
FOHR = FOHC
DLC
Corporate overhead rate:
COHR = COHC
DLC
where DLC = direct labor costs
25
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-7, 14/9/24 BITS Pilani, Pilani Campus
Example1
26
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-7, 14/9/24 BITS Pilani, Pilani Campus
Example2
27
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-7, 14/9/24 BITS Pilani, Pilani Campus
Thanks
28
BITS Pilani, Pilani Campus
EA ZC412 / MM ZC412 / DM ZC412
FLEXIBLE MANUFACTURING
SYSTEMS
BITS Pilani Girish Kant Garg
Department of Mechanical Engineering
Pilani Campus
1
BITS Pilani
Pilani Campus
3
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-7, 14/9/24 BITS Pilani, Pilani Campus
Operation Cycle Time
Cycle time:
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-7, 14/9/24 BITS Pilani, Pilani Campus
Production rate (Rp)
• Batch production
• Job shop production
• Mass production
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-7, 14/9/24 BITS Pilani, Pilani Campus
Types of discrete production
(a) Job shop, Q = 1, (b) batch production, sequential, (c) batch production,
simultaneous, (d) quantity mass production, (e) flow line mass production
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-7, 14/9/24 BITS Pilani, Pilani Campus
Production Rate
Batch production:
Batch time in min,
Tb = Tsu + QTc
Tb = Batch processing time (min/batch)
Tsu = Setup time to prepare for the batch (min/batch).
Q = Batch quantity (pc/batch).
Tc = Cycle time per work unit (min/cycle).
Average production time per work unit
Tp = Tb/Q
Production rate
Rp = 1/Tp
Rp = 60/Tp
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-7, 14/9/24 BITS Pilani, Pilani Campus
Production Rate
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-7, 14/9/24 BITS Pilani, Pilani Campus
Ex:1
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-7, 14/9/24 BITS Pilani, Pilani Campus
Ex:2
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-7, 14/9/24 BITS Pilani, Pilani Campus
Ex:3
A batch production operation has a machine setup time of 3.0
hours and a processing time of 1.60 min per cycle. Two parts are
produced each cycle. No tool handling time is included in the
cycle. Part handling time each cycle is 45 sec. It consists of the
worker obtaining two starting work units from a parts tray,
loading them into the machine, and then after processing,
unloading the completed units and placing them into the same
tray. Each tray holds 24 work units. When all of the starting work
units have been replaced with completed units, the tray of
completed parts is moved aside and a new tray of starting parts
is moved into position at the machine. This irregular work
element takes 3.0 min. Batch quantity is 2400 units. Determine
(a) average cycle time, (b) time to complete the batch, and (c)
average production rate.
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-7, 14/9/24 BITS Pilani, Pilani Campus
Ex:4
A flow line mass production operation consists of eight manual
workstations. Work units are moved synchronously and
automatically between stations, with a transfer time of 15 sec.
The manual processing operations performed at the eight
stations take 40 sec, 52 sec, 43 sec, 48 sec, 30 sec, 57 sec,
53 sec, and 49 sec, respectively. Determine (a) cycle time for
the line, (b) time to process one work unit through the eight
workstations, (c) average production rate, and (d) time to
produce 10,000 units.
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-7, 14/9/24 BITS Pilani, Pilani Campus
Production Capacity
Production capacity is the maximum rate of output that a production
facility is able to produce under a given set of operating conditions.
Plant capacity for facility in which parts are made in one operation
PC = n Hpc Rp
where
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-7, 14/9/24 BITS Pilani, Pilani Campus
Ex:1
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-7, 14/9/24 BITS Pilani, Pilani Campus
Utilization
Utilization:
It refers to the amount of output of a production facility
relative to its capacity.
where
Q = quantity actually produced,
PC = production capacity
Utilization can be defined as the proportionate of time that
the facility is operating relative to the time available under
the definition of capacity.
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-7, 14/9/24 BITS Pilani, Pilani Campus
Ex:2
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-7, 14/9/24 BITS Pilani, Pilani Campus
Availability
Availability:
It is a common measure of reliability for equipment.
It can be defined using two reliability terms mean time
between failures (MTBF) and mean time to repair (MTTR).
MTBF: Average length of time the piece of equipment
runs between breakdowns.
MTTR: Average time required to service the equipment
and put it back into operation when a breakdown occurs.
Calculation of availability:
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-7, 14/9/24 BITS Pilani, Pilani Campus
Availability-MTBF and MTTR
Defined
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-7, 14/9/24 BITS Pilani, Pilani Campus
Ex:3
The turret lathe section has six machines, all devoted to the
production of the same part. The section operates 10
shifts/week. The number of hours per shift averages 8.0.
Average production rate of each machine is 17 unit/hour.
Determine the weekly production capacity of the turret lathe
section. If the availability of the machines (A) = 90% and the
utilization of machines U=80%. Determine the expected plant
output.
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-7, 14/9/24 BITS Pilani, Pilani Campus
Manufacturing Costs
20
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-8, 15/9/24 BITS Pilani, Pilani Campus
Fixed and Variable Costs
21
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-8, 15/9/24 BITS Pilani, Pilani Campus
Manufacturing Costs
22
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-8, 15/9/24 BITS Pilani, Pilani Campus
Manufacturing Costs
23
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-8, 15/9/24 BITS Pilani, Pilani Campus
Typical Manufacturing Costs
(J Black)
24
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-8, 15/9/24 BITS Pilani, Pilani Campus
Overhead Rates
FOHR = FOHC
DLC
Corporate overhead rate:
COHR = COHC
DLC
where DLC = direct labor costs
25
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-8, 15/9/24 BITS Pilani, Pilani Campus
Example1
26
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-8, 15/9/24 BITS Pilani, Pilani Campus
Example2
27
EA ZC412 / MM ZC412/DM ZC412, FMS, Lecture-8, 15/9/24 BITS Pilani, Pilani Campus
Thanks
28
BITS Pilani, Pilani Campus