Controlling Configuration Guide
Controlling Configuration Guide
CONTROLLING Page 1
CONTROLLING CONFIGURATION AND STUDY MATERIAL
1. INTRODUCTION TO CONTROLLING 3
2. MAINTAIN CONTROLLING AREA 5
3. MAINTAIN NUMBER RANGES FOR CONTROLLING DOCUMENTS 11
4. AINTAIN VERSION 15
5. PROFIT CENTER ACCOUNTING 18
6. MAINTAIN CONTROLLING SETTING 19
7. CREATION OF DUMMY PROFIT CENTER 19
8. DEFINE PROFIT CENTER 20
9. COST ELEMENT ACCOUNTING 23
10. AUTOMATIC CREATION OF PRIMARY & SECONDARY COST ELEMENTS 24
11. CHANGE SECONDARY COST ELEMENT 28
12. DISPLAY COST ELEMENT INFORMATION 45
13. CREATION OF COST ELEMENT GROUP 46
14. COST CENTER ACCOUNTING 50
15. COST CENTER CATEGORY 51
16. CREATION OF COST CENTER GROUP 52
17. CREATION OF COST CENTER 54
18. COST CENTER INFORMATION REPORT 56
19. CREATION OF STATISTICAL KEY FIGURE 57
20. CREATION OF ACTIVITY TYPE 59
21. ACTIVITY CATEGORY 61
22. PRICE INDICATORS 62
23. COST CENTER PLANNING 63
24. PLANNING VALUE FOR STATISTICAL KEY FIGURE 68
25. REPORT ON COST CENTER 75
26. ACTIVITY INPUT OR PRICE PLANNING 76
27. ACTIVITY-INDEPENDENT AND ACTIVITY-DEPENDENT COST PLANNING 79
28. ACTIVITY DEPENDENT ACTIVITY INPUT PLANNING 80
29. ACTIVITY INPUT ACTIVITY INDEPENDENT PLANNING 82
30. PLAN RECONCILICATION OF ACTIVITES 87
31. ACTIVITY DEPENDENT COST PLANNING 88
32. ACTIVITY INDEPENDENT COST PLANNING 91
33. DISTRIBUTION METHOD OF ALLOCATION OF THE PRIMARY COST 97
34. PRICE PLAN CALCULATION 108
35. DEFINE CYCLE FOR INDIRECT ACTIVITY ALLOCATION 111
36. SPLITTING 116
37. SPLITTING STRUCTURE 117
38. EXECUTE SPLITTING FUNCTION 121
39. BUDGETING COST CENTER 123
40. CREATE BUDGET PROFILE 124
41. POSTING BUDGET TO COST CENTER 125
42. POSTING G/L 126
43. REPOST LINE ITEMS 127
44. DIRECT ACTIVITY ALLOCATION 130
45. POST SENDER ACTIVITY 130
46. POSTING ACTUAL PRICE 131
47. ENTERING ACTUAL STATISTICAL KEY FIGURES 132
48. DEFINE ASSESSMENT CYCLE FOR ASSESSMENT METHOD 133
49. ACTUAL PRICE CALCULATION 139
50. INDIRECT ACTIVITY ALLOCATION 141
51. SPLITTING OF COST 145
52. COMMITMENT MANAGEMENT 147
53. ASSIGN FISCAL YEAR VARIANT TO FINANCIAL MANAGEMENT AREA 147
54. ASSGH FIELD STATUS VARIENT TO COMPANY CODE 147
55. CREATE COMMITMENT 148
56. ASSIGH COMMITMENT ITEM TO G/L ACCOUNT 149
57. ENTER VALUE TO COMMITMENT ITEM 150
58. INTERNAL ORDERS 156
59. DEFINE ORDER TYPE 157
60. MAINTAIN SETTLEMENT 160
61. DEFINE TOLERANCE LIMITS FOR AVAILABILITY CONTROL 161
62. DEFINE INTERNAL ORDER 162
63. PLANNING INTERNAL ORDER 167
64. BUDGETTING INTERNAL ORDER 169
65. PRODUCT COST CONTROLING 182
66. DEFINE BILL OF MATERIAL 184
67. DEFINE WORK CENTER 186
68. DEFINE ROUTINGS 192
69. DEFINE COSTNG SHEET ROWS 196
70. MATERIAL COST ESTIMATE WITH QUANTITY STRUCTURE 203
71. CALCULATION OF COST OF GOODS MANUFACTURED
CONTROLLING Page 2
CONTROLLING CONFIGURATION AND STUDY MATERIAL
1. Intraduction..............................................................................................................................- 5 -
2. Maintain Controlling Area...................................................................................................- 6 -
CONTROLLING Page 3
CONTROLLING CONFIGURATION AND STUDY MATERIAL
1. Introduction
Controlling Module in SAP provides supporting information to Management for the purpose of planning, reporting, as well
as monitoring the operations of their business. Management decision-making can be achieved with the level of
information provided by this module.
Cost Element Accounting: component provides information which includes the costs and revenue for an organization.
These postings are automatically updated from FI (Financial Accounting) to CO (Controlling). The cost elements are the
basis for cost accounting and enable the User the ability to display costs for each of the accounts that have been
assigned to the cost element. Examples of accounts that can be assigned are Cost Centers, Internal Orders, WBS (work
breakdown structures).
Cost Center Accounting: provides information on the costs incurred by your business. Within SAP, you have the ability
to assign Cost Centers to departments and /or Managers responsible for certain areas of the business as well as
functional areas within your organization. Cost Centers can be created for such functional areas as Marketing,
Purchasing, Human Resources, Finance, Facilities, Information Systems, Administrative Support, Legal,
Shipping/Receiving, or even Quality.
Some of the benefits of Cost Center Accounting: (1) Managers can set Budget /Cost Center targets; (2) Cost Center
visibility of functional departments/areas of your business; (3) Planning; (4) Availability of Cost allocation methods; and
(5) Assessments/Distribution of costs to other cost objects.
Internal Orders: provide a means of tracking costs of a specific job, service, or task. Internal Orders are used as a
method to collect those costs and business transactions related to the task. This level of monitoring can be very detailed
but allows management the ability to review Internal Order activity for better-decision making purposes.
Activity-Based Costing: allows a better definition of the source of costs to the process driving the cost. Activity-Based
Costing enhances Cost Center Accounting in that it allows for a process-oriented and cross-functional view of your cost
centers. It can also be used with Product Costing and Profitability Analysis.
Product Cost Controlling: allows management the ability to analyze their product costs and to make decisions on the
optimal price(s) to market their products. It is within this module of CO (Controlling) that planned, actual and target
values are analyzed. Sub-components of the module are:
· Product Cost Planning which includes Material Costing( Cost estimates with Quantity structure, Cost
estimates without quantity structure, Master data for Mixed Cost Estimates, Production lot Cost
Estimates) , Price Updates, and Reference and Simulation Costing.
· Cost Object Controlling includes Product Cost by Period, Product Cost by Order, Product Costs by Sales
Orders, Intangible Goods and Services, and CRM Service Processes.
· Actual Costing/Material Ledger includes Periodic Material valuation, Actual Costing, and Price Changes.
Profitability Analysis: allows Management the ability to review information with respect to the company’s profit or
contribution margin by business segment. Profitability Analysis can be obtained by the following methods:
· Account-Based Analysis which uses an account-based valuation approach. In this analysis, cost and
revenue element accounts are used. These accounts can be reconciled with FI(Financial Accounting).
· Cost-Based Analysis uses a costing based valuation approach as defined by the User.
CONTROLLING Page 4
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Profit Center Accounting: provides visibility of an organization’s profit and losses by profit center. The methods which
can be utilized for EC-PCA (Profit Center Accounting) are period accounting or by the cost-of-sales approach. Profit
Centers can be set-up to identify product lines, divisions, geographical regions, offices, production sites or by functions.
Profit Centers are used for Internal Control purposes enabling management the ability to review areas of responsibility
within their organization. The difference between a Cost Center and a Profit Center is that the Cost Center represents
individual costs incurred during a given period and Profit Centers contain the balances of costs and revenues.
Controlling (CO) and Financial Accounting (FI) are independent components in the SAP system. The data flow between
the two components takes place on a regular basis.
The data relevant to cost, flows automatically to Controlling from Financial Accounting. At the same time, the system
assigns the costs and revenues to different CO account assignment objects, such as cost centers, business processes,
projects or orders. The relevant accounts in Financial Accounting are managed in Controlling as cost elements or
revenue elements. This enables you to compare and reconcile the values from Controlling and Financial Accounting.
An organizational unit within a company, used to represent a closed system for cost accounting purposes.
A controlling area may include single or multiple company codes that may use different currencies. These company
codes must use the same operative chart of accounts.
All internal allocations refer exclusively to objects in the same controlling area.
The company code assignment to the controlling area must be made according to the processes your company has in
logistics and accounting. The organizational environment is also very important. It is difficult or at best, time-consuming
to change the 1:1 or 1:N relationship between the controlling area and company code after the decision and the
assignment have already been made.
The company code and controlling area organizational units can be combined in a number of ways. Using these
combinations you can represent organizations with different structures.
In this example, the financial accounting and cost accounting views of the organization are identical.
This example is Cross-Company Code Cost Accounting. Cost accounting is carried out in multiple company codes in
one controlling area. All cost-accounting relevant data is collected in one controlling area and can be used for allocations
and evaluations. In this case, the external and internal accounting perspectives differ from each other.
CONTROLLING Page 5
CONTROLLING CONFIGURATION AND STUDY MATERIAL
For example, this method can be used if the organization contains a number of independent subsidiaries using global
managerial accounting. Cross-company code cost accounting gives you the advantage of using internal allocations
across company code boundaries.
If you assign more than one company code to one controlling area, then you need to note the following:
You need to use same operational chart of accounts for all company codes
You need to treat each cost element (in all company codes) in the same way (for example, as a primary cost element, or
as an accrual cost element).
The operative fiscal year variants in the company codes must match the fiscal year variants in the controlling
area.
You should execute period-end closing in Controlling for all company codes at the same time. Separate period-
end closing for each company code would be too time-consuming.
You can only execute period-end closing for a shared controlling area once closing is complete in Financial Accounting.
If you wish to calculate plan prices automatically, you need to wait until planning is complete.
The system only posts reconciliation postings across company codes without tax, which means that it cannot
automatically create invoices.
For tax reasons, cost flows (that are cross-company code) in Controlling can only be passed onto Financial Accounting if
the company codes form an integrated company with sales tax.
If you wish to prevent cross-company code postings in Controlling, then you need to create a detailed
authorization concept.
Retrospectively excluding a company code in another SAP system or client, requires more time and effort
than in cost accounting by company code.
If you only use one controlling area, you can only use one operating concern.
CONTROLLING Page 6
CONTROLLING CONFIGURATION AND STUDY MATERIAL
You need to take the following into consideration when deciding on the controlling area – company code assignment:
However, if you then create a controlling area with more than one assigned company code so that you can use all the
functions in Controlling, you may be causing a significant amount of extra work. Therefore, check to see if you really
need a 1:n relationship and whether the extra work it would create is acceptable.
SAP recommends a 1: N relationship between controlling area and company code for the following situations:
Cross-company code transactions that MUST be processed in a controlling area, for example, production in an
associate plant, special cases of intercom any processing.
Cross-company code CO postings that can be displayed in the reconciliation ledger, such as assessments,
capitalization of internal activity in Asset Accounting, activity allocation.
Representation of group costing
Use of Profit Center Accounting and transfer prices
Multilevel Product Cost Management across company codes
SAP recommends a 1:1 relationship between controlling area and company code for the following situations:
Consolidated analysis of settled transactions across company codes in Profitability Analysis (CO-PA) In this
situation, you assign more than one controlling area to an operating concern
Representation of intercom any processes, whereby producing and delivering plant are the same.
Click on (IM Activity), select “Maintain Controlling Area” click on button or pres enter key
CONTROLLING Page 7
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Enter your company code and pres enter button or click on continue key.
So it will copy few parameters to this screen form company code parameters as follow.
CONTROLLING Page 8
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Now pres on save button and pres on save button so it will display following dialogue box:
Just pres enter key or pres on yes button it will save automatically.
Standard Hierarchy is a tree structure containing all the cost centers in a controlling area from the Controlling
standpoint.
Now double click on “Assignment of company code” at left side as in follow window:
Now double click on “Activate Components/Control Indicators” at left side as I shown in following window:
CONTROLLING Page 9
CONTROLLING CONFIGURATION AND STUDY MATERIAL
It will take to another screen here pres on . In this screen non of the components will be in active. So we
have active all of them as follow:
Click on save button to save the activity, it display the following information window:
Areas in which numbers are assigned that refer to business objects of the same type. Examples of objects:
· Business partners
· G/L accounts
· Orders
· Posting documents
· Materials
CONTROLLING Page 10
CONTROLLING CONFIGURATION AND STUDY MATERIAL
One or more number range intervals are specified for each number range, as well as the type of number assignment.
The system generates a document number for each business transaction. Business transactions are classified according
to CO transactions.
The business transaction Direct Internal Activity Allocation belongs to the Controlling transaction Actual Activity
Allocation.
This means that you must assign each transaction to a number range interval. It is also possible to define multiple
business transactions in one number range interval.
The Controlling component provides a large number of transactions for each controlling area.
Path: SPRO Controlling General Controlling Organization Maintain Number Ranges for Controlling Documents.
CONTROLLING Page 11
CONTROLLING CONFIGURATION AND STUDY MATERIAL
In above window enter your Controlling Area and pres on Maintain Groups button
So it will take to following screen:
In above window go to mane bar “Group + Insert” it will display following window:
In the above window enter text and number range and pres enter key or click on insert button so it will appear on
the top of main window as follow:
CONTROLLING Page 12
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Select the check box and double click number range objects as follow (when you double click on each number range
objects the color of each object will change to blue from black)
So your all number range objects will assign to your number range as follow:
Click on save button to save the activity and go back to SPRO screen.
CONTROLLING Page 13
CONTROLLING CONFIGURATION AND STUDY MATERIAL
3. Maintain Versions
Select Version 0 and double click on “Settings for Each Fiscal Year”. It will display following screen:
In this window enter your controlling area and pres enter or click on continue key.
CONTROLLING Page 14
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Enter above parameters and Click on save button to save the activity so it will display the following window:
CONTROLLING Page 15
CONTROLLING CONFIGURATION AND STUDY MATERIAL
In the above window type “LP01” as Output Device and pres enter button or click on continue button:
CONTROLLING Page 16
CONTROLLING CONFIGURATION AND STUDY MATERIAL
EC-PCA lets you calculate internal operating results for SBU. A profit center represents an organizational subunit that
operates independently on the market and bears responsibility for its own costs and revenues. You organize your
organization into profit centers by assigning the master data of each profit-relevant objects (materials, cost centers,
orders, projects, sales orders, assets, cost objects, and profitability segments) to a profit center.
All the business transactions in the SAP system which are relevant for costs and profits are updated in the profit centers
at the same time they are processed in the original module, and organized according to cost and revenue elements. This
transforms all the flows of goods and services within the company into exchanges of goods and services between profit
centers. This profit center structure applies for both actual postings and profit center plan data.
A profit center is an organizational unit in accounting that reflects a management-oriented structure of the organization
for the purpose of internal control.
You can analyze operating results for profit centers using either the cost-of-sales or the period accounting approach.
By calculating the fixed capital as well, you can use your profit centers as investment centers.
Profit center Accounting at the profit center level is based on costs and revenues. These are assigned statistically by
multiple parallel updating to all logistical activities and other allocations of relevance for a profit center.
The exchange of goods and services between profit centers can be valuated using the same valuation approach as in
financial accounting or another approach
The master data of a profit center includes the name of the profit center, the controlling area it is assigned to, and the
profit center’s period of validity, as well as information about the person responsible for the profit center, the profit
center’s assignment to a node of the standard hierarchy, and data required for communication (address, telephone
number and so on).
Every profit center is assigned to the organizational unit controlling area. This assignment is necessary because Profit
Center Accounting displays values in G/L accounts.
The system transfers all the data to Profit Center Accounting together with the G/L account to which the data was
originally posted. You can only aggregate data of this structure by using the same
chart of accounts
currency
When we are implementing profit center accounting, system activates the Ledger 8A for PCA.
Path: SPRO Controlling Profit Center Accounting Basic Settings Controlling Area Settings Maintain Controlling
Area Settings.
CONTROLLING Page 17
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Click on save button to save the activity and go back to SPRO screen.
The dummy profit center is the default profit center to which data is posted when the corresponding object has not been
assigned to a profit center.
You can find out which objects are not assigned to profit centers by analyzing the postings assigned to the profit center.
You can also assess or distribute data from the dummy profit center to the desired profit centers.
It may happen that some objects in your system are inadvertently left without an assignment to a profit center. In this
case, postings to accounts which are defined as revenue or cost elements are assigned to the dummy profit center of
the controlling area to which the object posted to belongs. This ensures that your internal and financial accounting data
are reconciled.
You should not assign data intentionally to your dummy profit center for the purpose of allocating it later. If desired,
define a separate "allocation profit center" for this purpose.
Path: SPRO Controlling Profit Center Accounting Master Data Profit Center Create Dummy Profit Center
CONTROLLING Page 18
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Double click on “EC-PCA: Create Dummy Profit Center” or select that and click on button.
Type IN05_DUMMY as Dummy Profit center and click on Basic Data or pres enter key.
Click on save button to save the activity, and back to SPRO screen.
CONTROLLING Page 19
CONTROLLING CONFIGURATION AND STUDY MATERIAL
The essential difference between a profit center and a business area is that profit centers are used for internal control,
while business areas are more geared toward an external viewpoint.
The profit center differs from a cost center in that cost centers merely represent the units in which capacity costs arise,
whereas the person in charge of the profit center is responsible for its balance of costs and revenues.
Path: SPRO Controlling Profit Center Accounting Master Data Profit Center Define Profit Center
Double click on “EC-PCA: Create Profit Center” or select that and click on button.
In Profit center field any number and click on Master Data button, it will take to following screen:
Update the Name, Description, Person responsible, Profit center Group and Segment fields.
CONTROLLING Page 20
CONTROLLING CONFIGURATION AND STUDY MATERIAL
After maintaining above all parameters click on Active Button. So it will save automatically.
Note: like above process you can create any number of profit centers as per client or project requirement.
The scenario combines Customizing settings from different business views. In these Customizing settings, you specify
which posting data is transferred from different application components in General Ledger accounting, such as cost
center update or profit center update.
For each scenario, the system transfers the posting data relevant for General Ledger Accounting from the actual and
plan documents.
Overview of the Scenarios Delivered by SAP
Scenario Fields Filled Technical Field Name
Cost center update Cost center RCNTR
Sender cost center SCNTR
Preparation for consolidation Trading partner RASSC
Transaction type RMVCT
Business area Business area RBUSA
Trading partner business area SBUSA
Profit center update Profit center PPRCTR
Partner profit center PRCTR
Segment reporting Profit center PRCTR
Segment PSEGMENT
Partner segment SEGMENT
Cost of sales accounting Functional area RFAREA
Partner functional area SFAREA
You have to set up cost of sales accounting. The Functional Area field is not filled automatically by the assignment of the
scenario to your ledger.
Cost Element Accounting is the area of cost accounting where you track and structure the costs incurred during a
settlement period. It is thus not an accounting system as such, but rather a detailed recording of data that forms the
basis for cost accounting.
In an integrated accounting system such as the SAP system, you do not need to enter cost data separately. This is
because each business transaction that involves costs updates the CO component with detailed information on the cost
element and on the account assignment object itself. Each consumption transaction in Material Management (MM), each
billing in Sales and Distribution (SD) (= revenue), and each external transaction for invoice verification flows directly
through the G/L Account (= cost element) to the corresponding account assignment object.
Cost elements classify an organization’s valuated consumption of production factors within a controlling area. A cost
element corresponds to a cost-relevant item in the chart of accounts.
We distinguish between primary cost and revenue elements and secondary cost elements.
Primary Cost/Revenue Elements: A primary cost or revenue element is a cost or revenue-relevant item in the chart
of accounts, for which a corresponding general ledger (G/L) account exists in Financial Accounting (FI). You can only
create the cost or revenue element if you have first defined it as a G/L account in the chart of accounts and created it as
an account in Financial Accounting. The SAP System checks whether a corresponding account exists in Financial
Accounting.
Material costs
Personnel costs
Energy costs
Salary Costs
Sales
CONTROLLING Page 21
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Secondary Cost Elements: Secondary cost elements can only be created and administrated in cost accounting (CO).
They portray internal value flows, such as those found in internal activity allocation, overhead calculations and
settlement transactions.
When you create a secondary cost element, the SAP System checks whether a corresponding account already exists in
Financial Accounting. If one exists, you can not create the secondary cost element in cost accounting.
Cost elements in Controlling (CO) are closely related to the general ledger accounts used in Financial Accounting (FI).
This is because the SAP System is structured as an Integrated Accounting System:
The cost element category has a technical control function. It determines whether you can post to a cost element
directly or indirectly.
Direct posting means: You post a fixed amount to an account by specifying the account number. You can post directly to
all primary cost elements.
Indirect posting means: The system determines the account automatically at the time of posting You can not enter the
account number with the posting transaction. You can only post indirectly to secondary cost elements.
The following cost element categories can be used for primary cost elements
The following cost element categories can be used for secondary cost elements
CONTROLLING Page 22
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Enter your chart of account and press enter key or click on continue button.
Click on save button and click on back button to go back to SPRO screen.
CONTROLLING Page 23
CONTROLLING CONFIGURATION AND STUDY MATERIAL
It will display the above screen now click back button to go back to SPRO screen.
CONTROLLING Page 24
CONTROLLING CONFIGURATION AND STUDY MATERIAL
In the above window select “Display errors only” radio button and click on Process button.
The session has been executed and above window will display here just click on “Exit Batch Input” button
CONTROLLING Page 25
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Path: Accounting Controlling Cost Element Accounting Master Data Cost Element Individual Processing KA02
– Change.
Enter the secondary cost element and pres enter button or click on Master Data button:
It will come to following screen;
In this screen the name and description field contain “Internal activity allocation”. Change this as follow:
Now click on save button so it save the activity and com back to previous screen.
Path: Accounting Controlling Cost Element Accounting Information System Reports for Cost and Revenue
Element Accounting (New) Master Data Indexes KA23 - Cost Elements: Master Data Report
CONTROLLING Page 26
CONTROLLING CONFIGURATION AND STUDY MATERIAL
You can collect cost elements with similar characteristics in cost element groups.
CONTROLLING Page 27
CONTROLLING CONFIGURATION AND STUDY MATERIAL
We can use cost element groups in the information system, for example. You can use the cost element group structure
to define the row structure of your reports. Totals are calculated in the report for each node.
we can also use cost element groups whenever you want to process several cost elements in one transaction. For
example, in cost center planning, distribution or assessment.
Path: Accounting Controlling Cost Element Accounting Master Data Cost Element Group KAH1 – Create.
In the above screen enter Cost Element Group and press enter or click on Hierarchy button ,
Now place the curser on above yellow line pres “Lower Level” button so it will display another level under this structure
as follow:
CONTROLLING Page 28
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Now in the above lower level enter those parameters and place the curser on the same lower level and pres “Same
Level” button 5 times.
Like above screen type Cost Element Group and Description in each line one by one.
To assign Cost Elements to each group place the curser on “IN05_1000” and click on “Cost Element” Button
CONTROLLING Page 29
CONTROLLING CONFIGURATION AND STUDY MATERIAL
In the above window double click on required and relevant cost element so that it will automatically assign to cost
element group.
Do the same activity for right side box also (Click on down arrow button. It will display elements window) and double
click on “410020” cost element and pres enter button so it will assign all cost elements automatically as follow:
Do the same steps for all other cost Elements Groups and assign cost elements and click on save button to save the
activity and click on back button to go back.
You use Cost Center Accounting for controlling purposes within your organization. The costs incurred by your
organization should be transparent. This enables you to check the profitability of individual functional areas and provide
decision-making data for management. This requires that all costs be assigned according to their source. However,
CONTROLLING Page 30
CONTROLLING CONFIGURATION AND STUDY MATERIAL
source-related assignment is especially difficult for overhead costs. Cost Center Accounting lets you analyze the
overhead costs according to where they were incurred within the organization.
Depending on the level of decision-making powers assigned to the manager of an organizational unit, you can
distinguish between various types of responsibility areas within an organization:
Dividing an organization into cost centers allows you to follow several goals, depending on the cost accounting method.
· Assigning costs to cost centers lets you determine where costs are incurred within the organization.
· If you plan costs at cost center level, you can check cost efficiency at the point where costs are incurred.
· If you want to assign overhead costs accurately to individual products, services, or market segments, you need
to further allocate the costs to those cost centers directly involved in the creation of the products or services.
From these cost centers you can then use different methods to assign the activities and costs to the relevant
products, services, and market segments.
This enables you to valuate semi-finished and finished products in Product Cost Controlling (CO-PC), and to calculate
contribution margins in Profitability Analysis (CO-PA).
The “activities” of cost centers represent “internal resources” for business processes in Activity-Based Costing.
Cost Center Accounting (CO-OM-CCA) is often used in the first phase of implementation, together with the main areas of
Financial Accounting (General Ledger (FI-GL), Assets Payable (FI-AP), Assets Receivable (FI-AR)) and Overhead Orders
(CO-OM-OPA).
You can also implement Cost Center Accounting without Financial Accounting. Some settings, however, such as chart of
accounts, company code, must be made in Financial Accounting.
The costs of each cost-accounting-relevant business transaction portrayed in the system through can be assigned
through Cost and Revenue Element Accounting (CO-OM-CEL) to an account assignment object in the Controlling
component (CO). For overhead costs this can be cost centers, internal orders, business processes, or overhead projects.
Recording and assigning overhead costs allows you to control costs and prepare information for the subsequent areas of
Cost Accounting.
You can use the methods of activity allocation, assessment or distribution to further allocate costs, for example, to
internal orders (CO-OM-OPA), projects (PS), cost objects (CO-PC) or market segments (CO-PA).
Features:
Entering actual costs: Primary costs can be transferred to Cost Accounting from other components, for example,
Materials Management (MM), Asset Accounting (AA), Payroll Accounting (PY).Additional costs and outlay costs are
recorded using the accrual method.
Allocating actual costs: You can use various methods to further allocate the actual costs you have recorded,
according to their source. The system distinguishes between transaction-based allocations, which occur within one
period, and period-based allocations, which occur at period end.
Planning activities and costs: You can use planning to define organizational targets and carry out regular cost-
effectiveness checks. Variances can be calculated by comparing the actual costs and activities with the plan values.
These variances serve as a control signal, which helps you to correct business processes, when [Link] can plan
costs and activities to determine allocation (activity) prices.
Allocating plan costs: All actual allocations that occur for cost centers can also be planned (for example, distribution,
assessment, indirect activity allocation).
Entering plan and actual statistical key figures: Statistical key figures are used as the basis for the indirect
allocation methods, as well as for evaluations in the information system (for example, employees, telephones).
CONTROLLING Page 31
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Activity Accounting: Activity Accounting uses the activity produced by a cost center as the tracing factor for the costs.
You can use activities to measure the operating rate or the rate of capacity utilization for a cost center. The target costs
of the cost center refer to the activity output.
Depending on the source of the costs, the activities of a cost center are divided into various activity types (for example,
for the Work center cost center: Repair hours or Assembly hours.
Information system: The information system provides tools with which you can analyze the cost flows that have
occurred in your organization. You can carry out standard recurring evaluations; and create special reports for unique
tasks or situations.
To classify and specify the types of cost center and to control the data flow to the cost centers by cost center
category you can maintain the following types of data to cost centers:
Path: SPRO Controlling Cost Center Accounting Master Data Cost Centers Define Cost Center Categories
If you want to create any new click on and specify Cost Center Category (CCTC), name and all other
parameters. Now save and back to SPRO screen.
CONTROLLING Page 32
CONTROLLING CONFIGURATION AND STUDY MATERIAL
You can collect cost centers according to various criteria into groups. This enables you to use cost centers to depict the
structure of the organization in the SAP System.
You can use the groups to build cost center hierarchies, which summarize the decision-making, responsibility, and
control areas according to the particular requirements of the organization. The individual cost centers form the lowest
hierarchical level.
There must be at least one group that contains all cost centers and represents the entire business organization. This
cost center group is described as the standard hierarchy. You can assign more cost center groups to the standard
hierarchy.
You can also create any number of alternative groups. You can structure these, for example, according to organizational
and/or functional viewpoints. Cost center groups enable you to perform evaluations for each decision-making,
responsibility, or control area. They also support the processes during planning and internal allocations.
You can assign each cost center to only one group in the standard hierarchy, but to as many alternative groups as you
require.
Path: Accounting Controlling Cost Center Accounting Master Data Cost Center Group KSH1 – Create
Click on Hierarchy
button
In above screen Cost Center Group name will display automatically and just click on Hierarchy button ,
CONTROLLING Page 33
CONTROLLING CONFIGURATION AND STUDY MATERIAL
The above small window will display just click on YES button.
In the above screen type the description and place the curser on the same window and click on Lower Level button
Now keep the curser on the same Lower level Group and pres the Button Same Level to add
hierarchy.
In the above screen enter other Cost Center Groups and pres save button to save the activity and click on back button
to go back to access screen.
Path: Accounting Controlling Cost Center Accounting Master Data Cost Center Individual Processing KS01 –
Create
CONTROLLING Page 34
CONTROLLING CONFIGURATION AND STUDY MATERIAL
And pres enter key or click on . So it will take you to following screen
Enter above parameters and click on save button to save the activity.
Immediately after you click on save button it will save and take you to previous screen. So you can change the Cost
Center number and create another one.
CONTROLLING Page 35
CONTROLLING CONFIGURATION AND STUDY MATERIAL
11 99 T 0
01.04.20 31.12.99 HOFF_100
IN05100001 ADMIN OFFICE ADMIN W INR IN05_00000
11 99 0
01.04.20 31.12.99 HOFF_100
IN05100002 LEGAL ADMIN W INR IN05_00000
11 99 0
01.04.20 31.12.99 HOFF_200
IN05200001 PAYROLL HR W INR IN05_00000
11 99 0
01.04.20 31.12.99 HOFF_200
IN05200002 TRAINING HR W INR IN05_00000
11 99 0
01.04.20 31.12.99 PLAT1_100
PLT1100001 ADMIN OFFICE ADMIN W INR IN05_PLAT1
11 99 0
01.04.20 31.12.99 NORMAL PRODUCTIO PLAT1_300
PLT1300001 F INR IN05_PLAT1
11 99 DESKTOP N 0
01.04.20 31.12.99 PRODUCTIO PLAT1_300
PLT1300002 HYBRID DESKTOP F INR IN05_PLAT1
11 99 N 0
01.04.20 31.12.99 DEGITAL PRODUCTIO PLAT1_300
PLT1300003 F INR IN05_PLAT1
11 99 DESKTOP N 0
01.04.20 31.12.99 PLAT1_400 IN05_PLAT1
PLT1400001 STORES MATERIAL M INR
11 99 0
01.04.20 31.12.99 PLAT1_500 IN05_PLAT1
PLT1500001 SALES SALES V INR
11 99 0
01.04.20 31.12.99 PLAT1_600 IN05_PLAT1
PLT1600001 R&D R&D E INR
11 99 0
01.04.20 31.12.99 PLAT1_700 IN05_PLAT1
PLT1700001 CANTEEN WELFARE H INR
11 99 0
01.04.20 31.12.99 PLAT1_700 IN05_PLAT1
PLT1700002 REPAIRS SERVICE H INR
11 99 0
01.04.20 31.12.99 PLAT1_800 IN05_PLAT1
PLT1800001 TRANSPORT LOGISSTICS H INR
11 99 0
01.04.20 31.12.99 PLAT2_100
PLT2100001 ADMIN OFFICE ADMIN W INR IN05_PLAT2
11 99 0
01.04.20 31.12.99 NORMAL PRODUCTIO PLAT2_300 IN05_PLAT2
PLT2300001 F INR
11 99 DESKTOP N 0
01.04.20 31.12.99 PRODUCTIO PLAT2_300 IN05_PLAT2
PLT2300002 HYBRID DESKTOP F INR
11 99 N 0
01.04.20 31.12.99 DEGITAL PRODUCTIO PLAT2_300 IN05_PLAT2
PLT2300003 F INR
11 99 DESKTOP N 0
01.04.20 31.12.99 PLAT2_400 IN05_PLAT2
PLT2400001 STORES MATERIAL M INR
11 99 0
01.04.20 31.12.99 PLAT2_500 IN05_PLAT2
PLT2500001 SALES SALES V INR
11 99 0
01.04.20 31.12.99 PLAT2_600 IN05_PLAT2
PLT2600001 R&D R&D E INR
11 99 0
01.04.20 31.12.99 PLAT2_700 IN05_PLAT2
PLT2700001 CANTEEN WELFARE H INR
11 99 0
01.04.20 31.12.99 PLAT2_700 IN05_PLAT2
PLT2700002 REPAIRS SERVICE H INR
11 99 0
01.04.20 31.12.99 PLAT2_800 IN05_PLAT2
PLT2800001 TRANSPORT LOGISSTICS H INR
11 99 0
Path: Accounting Controlling Cost Center Accounting Information System Reports for Cost Center Accounting
Master Data Indexes KS13 - Cost Centers: Master Data Report
CONTROLLING Page 36
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Select “All Cost Centers” and click on button to view the cost centers
These figures representing a cost center are business produce orders and profit centers, statistical key figures are used
as an allocation base and to used as an allocation base and to determine the operation rate of a cost center.
Figure representing
Cost Centers
Activity Types
CONTROLLING Page 37
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Orders
Business Processes
Profit Centers
Real Estate Objects
You can use them as the basis for internal allocations, such as Distribution and Assessment.
You assess the costs for the cafeteria to the individual cost centers, based on the number of employees in each cost
center. To do this, you need to enter the number of employees in each cost center as a statistical key figure.
Structure
Fixed values
Totals values
Key figures defined as fixed values are valid as of the posting period, and in all subsequent posting periods of the
fiscal year.
Example: The statistical key figure Employees is defined as a fixed value. In period 1 of the fiscal year, you post 10
Employees on cost center 4100. The system then automatically posts 10 employees in periods 2 through 12.
In period 6, the number of employees is increased to 15. This means that in period 6, you post 15 Employees on the cost
center. The system automatically posts 15 employees in periods 6 through 12.
Key figures defined as Totals values are valid only in the posting period in which they are entered.
Example: You define the statistical key figure Telephone units as a totals value. In period 1 of the fiscal year, you post
1000 Telephone units on cost center 4100. The system posts 1000 telephone units in period 01 only.
Double click on the Transaction Code so it will display the following screen:
In the above screen enter the Stat. Key Figure number and pres enter or click on Button.
CONTROLLING Page 38
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Stat. Key Name [Link]. UnM. Key fig. cat: Fxd Val Key fig. cat: Tot. Value
Figure
1000 No. Of employees EA X
2000 Telephone Calls EA X
3000 Area Occupied FT2 X
4000 No. Of Kilometers KM X
5000 Repairing Hours H X
6000 Power Units KWH X
7000 No of Tests EA X
8000 Purchase orders EA X
9000 Production Units EA X
After creating all above Statistical key Figure save the screen and back to mane.
ACTIVITY TYPE
Activity type describes and classifies the activities performed or produced by cost center. These activities are recorded
in the form of activity, quantity, which is measured in activity units.
Activity types classify the activities produced in the cost centers within a controlling area.
To plan and allocate the activities, the system records quantities that are measured in activity units. Activity quantities
are valuated using a price (allocation price).
In Overhead Cost Controlling, costs based on the activity quantity of an activity type are posted separately in fixed and
variable portions. When you divide the activities of a cost center into activity types, you should consider whether the
costs can be allocated effectively to the activity types.
The prices of the activity types of a cost center can be either entered manually, or calculated by the system based on
the costs allocated to the activities. Prices can be calculated either using plan costs or actual costs.
You can plan, allocate, and control costs either at the activity type level of a cost center, or at the cost center level. You
can enter actual costs at the cost center level. Costs entered at the cost center level are assigned using splitting.
You can also assign the activity type of a cost center directly. This use was designed for certain application areas (such
as personnel costs and depreciation postings).
When the activities produced by a cost center are used by other cost centers, orders, processes, and so on, this means
that the resources of the sending cost center are being used by the other objects.
CONTROLLING Page 39
CONTROLLING CONFIGURATION AND STUDY MATERIAL
You can assign one activity type, multiple activity types, or no activity types to a cost center.
Examples: Activity types for cost centers are machine hours, Labour hours, Maintanance hours or units produced.
These activity types are categorized based on the information availability for the purpose of allocation.
Price Indicators:
The default price indicator considered by the system in plan price 001,
To calculate actual price you need to specify the actual price indicator 005 and for actual price indicator 006,
For every activity type we need to specify an allocated cost element to store the valuated internal activity quantities.
Double click on the Transaction Code so it will display the following screen:
In the above screen enter Activity Type number and pres enter or button.
So it will take to next screen as follow:
CONTROLLING Page 40
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Activity Valid from Name / Activity CCtr ATyp Allocation Act. Price
Type Description Unit Categories Category Cost elem indicator
Machine
500000 01.01.2008 H * 1 500000 ---------------
Hour
501000 01.01.2008 Labour Hour H * 1 501000 ---------------
502000 01.01.2008 Set up Hour H * 1 502000 ---------------
Assembling
503000 01.01.2008 H * 1 503000 ---------------
Hour
Repairing
504000 01.01.2008 H * 3 504000 5
Hour
505000 01.01.2008 Testing Hour H * 3 505000 5
Production
506000 01.01.2008 UN * 3 506000 5
Units
Power in
507000 01.01.2008 Kilowatts KW * 1 507000 ---------------
energy
After you create all above Activity Types save the screen and back to easy access.
Activity Category
Activity type category 1: (Manual entry, manual allocation) you plan activity quantities manually for activity
types in this category. You enter actual activity quantities in internal activity allocation, based on business transactions.
Plan activities are allocated using activity input planning on the receivers. It may be necessary to reconcile the plan
sender quantities and the plan scheduled activities.
Activity type category 2: (Indirect calculation, indirect allocation) For activity types of this category, you plan
activity types on the sender cost center. You can calculate the plan and actual activity quantities for activity types of
this category as follows:
Automatically, using receiver tracing factors, which you can value with weighting factors and are defined for
each sender, or
Using a fixed quantity, which you define in the segment definition of the indirect activity allocation
The system automatically reconciles the plan and scheduled activity quantities.
CONTROLLING Page 41
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Activity type category 3: (Manual entry, indirect allocation) you plan activity quantities manually for activity
types in this category. To enter the actual activity quantities by business transaction, access the Cost Center Accounting
menu, and choose Actual postings Sender activities. You cannot enter receiver objects here.
Plan and actual activity quantities are allocated automatically using defined sender/receiver relationships. The system
calculates the activity quantity to be allocated to each receiver, based on the relationship of the tracing factors to all
receivers. Manually planned or posted activity quantities are further allocated in full to the receivers. This means that
the activity types in the plan are always reconciled following the activity allocation.
Activity type category 4: (Manual entry, no allocation) you plan activity quantities manually for activity types in
this category. To enter the actual activity quantities by business transaction, access the Cost Center Accounting menu,
and choose Actual postings Sender activities. You cannot enter receiver objects here.
You cannot allocate to other objects.
Activity type category 5: (Calculation and allocation through target=actual activity allocation)
You require activities of this activity type category when you carry out target=actual activity allocation. Target=actual
activity allocation is a special from of indirect activity allocation, where the planned input of an activity is transferred as
an actual value, in accordance with the operating rate Target=actual activity allocation is used only to allocate actual
values. Therefore, activities participating in target=actual allocation must be assigned different activity type categories
for planning and actual allocation.
Actual allocation requires activity type category 5. Planning requires activity type categories 1, 2, or 3. Category 1 is
most commonly used.
In activity type maintenance, you have the option of entering separate plan and actual activity type categories. An
actual activity type category is required only if actual allocation varies from plan allocation. Otherwise, the SAP System
automatically adopts the plan activity type category in the actual.
Price Indicators
The Price indicator determines how the price of a business process or an activity type is calculated for a cost center.
There are two fields: The Price indicator determines the way the system calculates prices for actual values. For actual
allocations, you can enter a price indicator different from that in the plan.
You can enter the following values for the (plan) price indicator:
· 001: The system calculates the price of the activity type automatically, based on the plan activity and the plan
costs required by the cost center.
· 002: The system calculates the variable portion of the price, based on the plan activity. The fixed portion,
however, is based on capacity. This method usually results in an under absorption for the cost center. This is
because the cost center is not credited in full for the costs of providing the capacity.
If you have set values 001 or 002, the system calculates new prices when you execute Plan Price Calculation.
You cannot enter price indicator 004 (the plan price of the activity is calculated purely iteratively). If you activate Purely
iterative price in the version, the SAP System calculates a purely iterative price, in addition to the price resulting from
planning.
You can enter the following values for the (actual) price indicator:
· 005: The SAP System calculates the actual price based on the actual activity if you execute Actual Price
Calculation.
CONTROLLING Page 42
CONTROLLING CONFIGURATION AND STUDY MATERIAL
(Actual Price Calculation: The method used to calculate the prices of planned activities iteratively for combinations of
cost center and activity type or for business processes, taking all activities performed for other cost centers or business
processes into account. This can be done for both planned and actual data.)
· 006: The system calculates the variable portion of the price, based on actual activity.
The fixed portion, however, is based on the capacity.
If you have set values 005 or 006, the system calculates new prices when you execute actual price calculation.
Recalculation of actual activity at actual prices can only be executed if you have selected recalculation during version
maintenance.
· 007: Manual actual price: You set the price of the activity type or business process manually. Using this price
indicator, you can set a price manually that is independent of and varies from the plan.
· 008: Actual price, activation from version maintenance: The system calculates the actual price of the activity
type or business process iteratively only. If you activate the indicator Iter., the system calculates a purely
iterative price in addition to the price resulting from planning.
You cannot enter price indicator 008 (the actual price is calculated purely iteratively). If you activate purely
iterative price in the version, the SAP System calculates a purely iterative price, in addition to the price resulting
from planning.
Cost center planning involves entering plan figures for costs, activities, prices or statistical key figures for a particular
cost center and a particular planning period. You can then determine the variances from these figures when you come to
compare these plan values with the costs actually incurred. These variances serve as a signal to make the necessary
changes to your business processes.
Cost center planning forms part of the overall business planning process, and is a prerequisite for standard costing. The
main characteristic of standard costing is that values and quantities are planned for specified timeframes, independently
of the actual values from previous periods.
You can take plan costs and plan activity quantities to determine the (activity) prices. These prices can be used to
valuate internal activities during the ongoing period, that is, before the actual costs are known.
To plan the structure of the organization’s future operations for a clearly defined time period.
You should define performance targets and target achievement grades. You must consider the internal and
external (market) factors affecting your organization.
This ensures that you keep as closely as possible to the plan. Iterative planning lets you adapt the target
performance to reflect any changes in the organizational environment.
To monitor efficiency after completion of the settlement period using plan/actual or target/actual
comparisons.
To provide a basis for the valuation of organizational activities, independent of random fluctuations.
o Primary costs
CONTROLLING Page 43
CONTROLLING CONFIGURATION AND STUDY MATERIAL
o Secondary costs
o Revenues
Statistical key figures can be planned for different purposes, for example, as a basis for distribution, assessment, or
creating key figures in the information system. You can plan statistical key figures on cost centers or on the activity
types of the cost centers. In addition to manually planning statistical figures you can also transfer statistical key figures
from the Logistics Information System (LIS) For more information.
In activity type planning, you plan the activity produced by a cost center. This represents the quantity-based output of a
cost center. During planning you can manually set the price with which the SAP system valuates the activity during
allocations. You can choose to retain this price or have the system overwrite it during plan price calculation. You can
also plan the capacity required for providing the activity type.
The input side of the cost center is affected when the primary and secondary cost values are planned. The primary and
secondary plan costs refer to the costs incurred in producing the plan output on the cost center.
Value-based cost planning can be executed manually or automatically. For the automatic planning of primary costs you
can use plan distribution
CONTROLLING Page 44
CONTROLLING CONFIGURATION AND STUDY MATERIAL
For automatic planning of secondary costs, you can use assessment. The SAP system determines the planning values on
the basis of user-defined rules. For planning purposes, you can transfer primary costs to cost center planning from
Human Resources and Asset Accounting
The quantity-based planning of secondary costs is based on the consumption of activity, which the SAP system valuates
using the corresponding activity type price. The planning of secondary costs by quantity (that is, activity input planning)
can be done manually or automatically using indirect activity allocation The SAP system determines the activity
quantities according to the receiver tracing factors.
Activity input enables extra planning detail: You can plan primary and secondary costs both independently and
dependently of activity.
For manual cost planning the SAP system provides a variety of special planner profiles for the various planning areas.
These profiles are tailored to specific planning projects and contain suitable planning layouts (input screens for
planning).
In one planner profile you can collect planning layouts grouped according to various criteria.
Planner profile SAP101 contains a planning layout that can be used both for activity-independent and activity-dependent
primary cost planning.
The periodic formulas are not calculated among the cumulated values of the overview screen, but always by period.
Features
Here is a selection of the periodic formulas offered by the system for the planning of CO objects:
Depending on the values you entered during planning, the system calculates the missing values by solving the formulas
according to the given variables.
Fixed + Variable = Overall (Primary Costs and Quantities)
CONTROLLING Page 45
CONTROLLING CONFIGURATION AND STUDY MATERIAL
This formula is valid for cost element planning and price planning. During the calculations, the system keeps to the
following priorities:
1. Fixed + variable = overall
If you have entered a fixed value, as well as a variable and overall value, the system overwrites your overall value.
The system calculates an overall value of $60 and overwrites the value of $80 in line with the first priority.
The system uses this formula when you plan activity-dependent secondary costs. If you have entered manual prices in
activity type planning, or have carried out price calculation, the system uses these values in the activity input planning
for valuation of the plan consumption
If you have not planned any prices, you cannot carry out a valuation during secondary planning. Only after price
calculation or manual price planning does the system execute a recalculation of the received activity quantities using
the prices.
CONTROLLING Page 46
CONTROLLING CONFIGURATION AND STUDY MATERIAL
With the value 200 hrs for the fixed consumption, the formula is once again correct.
Currency Translations
During manual planning, the system executes any necessary currency translations if these have been activated in the
controlling area. Generally, the system carries out manual planning in the controlling area currency. Additionally,
however, you can also use plan values in transaction, object or a freely-definable currency. To do this, you need to add
another column to the corresponding planning layout for each additional leading amount in a different currency. The
following translations are possible:
Controlling area currency to transaction currency
Controlling area currency to object currency
Controlling area currency to user-definable currency
CONTROLLING Page 47
CONTROLLING CONFIGURATION AND STUDY MATERIAL
In the overview screens for the planning of statistical key figures, the system displays the average values (not totals) for
statistical key figures of category Fixed values.
You can plan statistical key figures as activity-independent or activity-dependent. Use planning layout 1 - 301 for
activity-independent planning, and planning layout 1 - 302 for activity-dependent planning
Double click on the Transaction Code so it will display the following screen:
CONTROLLING Page 48
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Now click on “Next Combination” button to go to next Cost Center with Combination of Statistical Key Figures till
you reach the Cost Center “1130 – Production overheads” as follow:
Enter the above values and click on next combination for the Cost Center “1200 – Machine A”
It will display as follow:
Enter the above values and click on next combination for the Cost Center “1300 – Machine B”
It will display as follow:
CONTROLLING Page 49
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Enter the above values and click on next combination for the Cost Center “2100 – Administration Cost Center”
It will display as follow:
Enter the above values and click on next combination for the Cost Center “3100 – Material Management Cost
Center”
It will display as follow:
CONTROLLING Page 50
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Enter the above values and click on next combination for the Cost Center “4100 – Sales & Distribution Cost Center”
It will display as follow:
Enter the above values and click on next combination for the Cost Center “4200 – Marketing Cost Center”
It will display as follow:
CONTROLLING Page 51
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Enter the above values and click on next combination for the Cost Center “6100 – Personal Department Cost
Center”
It will display as follow:
Enter the above values and click on next combination for the Cost Center “6200 – Canteen & Welfare Cost Center”
It will display as follow:
CONTROLLING Page 52
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Enter the above values and click on next combination for the Cost Center “6300 – dispensary Cost Center”
It will display as follow:
Enter the above values and click on next combination for the Cost Center “6400 – Stores Department Cost Center”
It will display as follow:
CONTROLLING Page 53
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Enter the above values and click on next combination for the Cost Center “6600 – Repairs & Maintaince Cost
Center”
It will display as follow:
Enter the above values and click on next combination for the Cost Center “6700 – Quality Control Cost Center”
It will display as follow:
CONTROLLING Page 54
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Enter the above values and click on Save Button so your planning activity will save and back to Manu screen.
Path: Accounting Controlling Cost Center Accounting Information System Reports for Cost Center Accounting
Plan/Actual Comparisons S_ALR_87013611 - Cost Centers: Actual/Plan/Variance
CONTROLLING Page 55
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Double click on the Transaction Code so it will display the following screen:
In the above screen maintain above parameters and click on “Overview Screen” button.
In the above screen first click on “Next combination” Button till it comes to “1200 – Machine A Cost Center”.
CONTROLLING Page 56
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Click on “Next combination” Button till u comes to “1300 – Machine B Cost Center”.
It will display the following screen:
Click on “Next combination” Button till u comes to “1400 – Assembling Cost Center”.
It will display the following screen:
Click on “Next combination” Button till u comes to “6600 – Repairing & Maintains Cost Center”.
It will display the following screen:
Click on “Next combination” Button till u comes to “6700 – Quality & Control Cost Center”.
It will display the following screen:
CONTROLLING Page 57
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Click on “Next combination” Button till u comes to “6800 – Power Cost Center”.
It will display the following screen:
After entering above parameters click on save the button to save planning activity and back to Manu screen.
Path: Accounting Controlling Cost Center Accounting Information System Reports for Cost Center Accounting
Plan/Actual Comparisons S_ALR_87013611 - Cost Centers: Actual/Plan/Variance
CONTROLLING Page 58
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Activity-independent cost planning covers both primary and secondary costs, but does not refer to a specific activity
type. The opposite to this is activity-dependent planning.
Activity-dependent planning of primary and secondary costs enables you to plan both fixed and variable costs. You may
require this functionality if your costing system uses flexible standard costing based on marginal costs. It is also possible
to carry out flexible standard costing based on full costs or marginal costs.
Standard costing based on full costs means that the fixed costs are distributed in proportion to the operating level. This
could mean that portions of fixed costs are included in the prices. You can assign plan activity-independent costs to
activity types using various rules, for example, using equivalence numbers or your own splitting rules
Standard costing based on marginal costs means that the fixed costs included in the prices are not proportional to the
operating level If you want to use prices based on full costs for your marginal costing, as well as purely proportional
prices, you must assign to the cost objects the fixed costs of the sender cost centers in addition to allocating the
variable costs of internal activity allocation. Because the fixed preparation costs are not proportional to the operating
level, you should not allocate them in a marginal costing system based on the activity output of the sender cost centers.
Pre-distribution of Fixed Costs enables you to distribute the fixed costs in full to the cost centers that have planned
activity input. The following prerequisites apply:
Within an agreed activity plan, the sender cost centers provide activity quantities because other cost centers
have planned to consume them.
The sender cost center has not caused the fixed costs for the provision of these activities.
CONTROLLING Page 59
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Path: Accounting Controlling Cost Center Accounting Planning Cost and Activity Inputs KP06 – Change
Now maintain the above parameters and click on “Overview Screen ” button.
So it will take you to another screen as follow:
Click on “Next combination” Button till u comes to “1300 – Machine B Cost Center”.
It will display the following screen:
CONTROLLING Page 60
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Click on “Next combination” Button till u comes to “1400 – Assembling Cost Center”.
It will display the following screen:
Click on “Next combination” Button till u comes to “6600 – repairs & Maintains Cost Center”.
It will display the following screen:
Click on “Next combination” Button till u comes to “6700 – Quality control Cost Center”.
It will display the following screen:
CONTROLLING Page 61
CONTROLLING CONFIGURATION AND STUDY MATERIAL
After entering above parameters save the activity and back to Manu screen.
Path: Accounting Controlling Cost Center Accounting Information System Reports for Cost Center Accounting
Plan/Actual Comparisons S_ALR_87013611 - Cost Centers: Actual/Plan/Variance
Path: Accounting Controlling Cost Center Accounting Planning Cost and Activity Inputs KP06 – Change
CONTROLLING Page 62
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Now maintain the above parameters and click on “Overview Screen ” button.
So it will take you to another screen as follow:
Click on “Next combination” Button till u comes to “1130 – Production Overheads Cost Center”.
It will display the following screen:
Click on “Next combination” Button till u comes to “2100 – Administration Cost Center”.
It will display the following screen:
CONTROLLING Page 63
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Click on “Next combination” Button till u comes to “3100 – Material Management Cost Center”.
It will display the following screen:
Click on “Next combination” Button till u comes to “4100 – Sales & Distribution Cost Center”.
It will display the following screen:
Click on “Next combination” Button till u comes to “4200 – Marketing Cost Center”.
It will display the following screen:
CONTROLLING Page 64
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Click on “Next combination” Button till u comes to “6100 – Personal Dept Cost Center”.
It will display the following screen:
Click on “Next combination” Button till u comes to “6200 – Canteen & Welfare Cost Center”.
It will display the following screen:
Click on “Next combination” Button till u comes to “6300 – Dispensary Cost Center”.
It will display the following screen:
Click on “Next combination” Button till u comes to “6200 – Canteen & Welfare Cost Center”.
It will display the following screen:
CONTROLLING Page 65
CONTROLLING CONFIGURATION AND STUDY MATERIAL
After entering above parameters just click on save button and back to Manu screen.
Path: Accounting Controlling Cost Center Accounting Information System Reports for Cost Center Accounting
Plan/Actual Comparisons S_ALR_87013611 - Cost Centers: Actual/Plan/Variance
CONTROLLING Page 66
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Path: Accounting Controlling Cost Center Accounting Planning Planning Aids KPSI - Plan Reconciliation.
By default this
check box will be
selected so we
should be
deselect it
Once you execute the screen just go back from this screen to Easy Access screen.
CONTROLLING Page 67
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Path: Accounting Controlling Cost Center Accounting Information System Reports for Cost Center Accounting
Plan/Actual Comparisons S_ALR_87013611 - Cost Centers: Actual/Plan/Variance
Path: Accounting Controlling Cost Center Accounting Planning Cost and Activity Inputs KP06 - Change
After maintaining the above parameters just click on overview screen button.
So it will take to following screen:
CONTROLLING Page 68
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Click on “Next combination” Button till u comes to “1200 – Machine A Cost Center”.
It will display the following screen:
Click on “Next combination” Button till u comes to “1300 – Machine B Cost Center”.
It will display the following screen:
Click on “Next combination” Button till u comes to “1400 – Assembling Cost Center”.
It will display the following screen:
CONTROLLING Page 69
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Click on “Next combination” Button till u comes to “6600 – Repairs & Maintains Cost Center”.
It will display the following screen:
Click on “Next combination” Button till u comes to “67600 – Quality Control Cost Center”.
It will display the following screen:
Click on “Next combination” Button till u comes to “6800 – Power dept Cost Center”.
It will display the following screen:
CONTROLLING Page 70
CONTROLLING CONFIGURATION AND STUDY MATERIAL
After entering above parameters save the activity and back to easy access screen.
Path: Accounting Controlling Cost Center Accounting Information System Reports for Cost Center Accounting
Plan/Actual Comparisons S_ALR_87013611 - Cost Centers: Actual/Plan/Variance
Path: Accounting Controlling Cost Center Accounting Planning Cost and Activity Inputs KP06 - Change
CONTROLLING Page 71
CONTROLLING CONFIGURATION AND STUDY MATERIAL
After maintaining the above parameters just click on overview screen button.
So it will take to following screen:
Click on “Next combination” Button till u comes to “1110 – Wages Cost Center”.
It will display the following screen:
Click on “Next combination” Button till u comes to “1130 – Production Overheads Cost Center”.
It will display the following screen:
CONTROLLING Page 72
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Click on “Next combination” Button till u comes to “1200 – Machine A Cost Center”.
It will display the following screen:
Click on “Next combination” Button till u comes to “2100 – Administration Cost Center”.
It will display the following screen:
Click on “Next combination” Button till u comes to “3100 – Material Management Cost Center”.
It will display the following screen:
CONTROLLING Page 73
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Click on “Next combination” Button till u comes to “4100 – Sales & Distribution Cost Center”.
It will display the following screen:
Click on “Next combination” Button till u comes to “4200 – Marketing Cost Center”.
It will display the following screen:
Click on “Next combination” Button till u comes to “4300 – Advertisement Cost Center”.
It will display the following screen:
CONTROLLING Page 74
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Click on “Next combination” Button till u comes to “6100 – Personal dept Cost Center”.
It will display the following screen:
Click on “Next combination” Button till u comes to “6200 – Canteen & welfare Cost Center”.
It will display the following screen:
Click on “Next combination” Button till u comes to “6300 – Dispensary Cost Center”.
It will display the following screen:
CONTROLLING Page 75
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Click on “Next combination” Button till u comes to “6400 – storage dept Cost Center”.
It will display the following screen:
Click on “Next combination” Button till u comes to “6500 – Vehicles & Internal Cost Center”.
It will display the following screen:
Click on “Next combination” Button till u comes to “6900 – Telephone Dept Cost Center”.
It will display the following screen:
CONTROLLING Page 76
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Click on “Next combination” Button till u comes to “6910 – Rent Dept Cost Center”.
It will display the following screen:
After entering above parameters save the activity and back to easy access screen.
Path: Accounting Controlling Cost Center Accounting Information System Reports for Cost Center Accounting
Plan/Actual Comparisons S_ALR_87013611 - Cost Centers: Actual/Plan/Variance
CONTROLLING Page 77
CONTROLLING CONFIGURATION AND STUDY MATERIAL
-----------------------------------------------------------------------------------------------------------------------
Allocation of services cost centers cost among services receiving cost center:
The allocation may be made basing on posted to cost center or a activities of a cost center.
The system provides the following allocation methods:
1. Periodic Re-Posting
2. Distribution
3. Assessment
4. Indirect Activity Allocation
In above first 3 methods are used for Distribution of cost and last method is used for Distribution of Activates
In the above screen give Cycle name and Start Date and pres enter button.
CONTROLLING Page 78
CONTROLLING CONFIGURATION AND STUDY MATERIAL
In the above screen maintain the Text and flag the check box Iterative and pres on button.
It takes you to another screen as follow:
In the above screen maintain Segment name and description. Under “Segment Header” tab Receiver rule “1 Variable
Portions” and [Link] Type “6 plan stat. key figures”.
After maintain above parameters click on another tab “Sender/Receivers” so it will display following screen:
CONTROLLING Page 79
CONTROLLING CONFIGURATION AND STUDY MATERIAL
In the above screen maintain sender cost center, sender cost element and receiver cost center under
“Senders/Receivers” tab.
After this click on “Receiver Tracing Factor” tab so it will take you to following screen;
In the above screen maintain Version , [Link] fig and pres on save button to save the activity.
After saving click on button so it will display new screen for another segment as follow:
CONTROLLING Page 80
CONTROLLING CONFIGURATION AND STUDY MATERIAL
In the above screen maintain Segment name and description. Under “Segment Header” tab Receiver rule “1 Variable
Portions” and [Link] Type “6 plan stat. key figures”.
After maintain above parameters click on another tab “Sender/Receivers” so it will display following screen:
In the above screen maintain sender cost center, sender cost element and receiver cost center under
“Senders/Receivers” tab.
After this click on “Receiver Tracing Factor” tab so it will take you to following screen:
CONTROLLING Page 81
CONTROLLING CONFIGURATION AND STUDY MATERIAL
In the above screen maintain Version, Stat. Key fig and pres on save button to save the activity.
After saving click on button so it will display new screen for another segment as follow:
In the above screen maintain Segment name and description. Under “Segment Header” tab Receiver rule “1 Variable
Portions” and [Link] Type “6 plan stat. key figures”.
After maintain above parameters click on another tab “Sender/Receivers” so it will display following screen:
CONTROLLING Page 82
CONTROLLING CONFIGURATION AND STUDY MATERIAL
In the above screen maintain sender cost center, sender cost element and receiver cost center under
“Senders/Receivers” tab.
After this click on “Receiver Tracing Factor” tab so it will take you to following screen;
In the above screen maintain Version , [Link] fig and pres on save button to save the activity.
After saving click on button so it will display new screen for another segment as follow:
CONTROLLING Page 83
CONTROLLING CONFIGURATION AND STUDY MATERIAL
In the above screen maintain Segment name and description. Under “Segment Header” tab Receiver rule “1 Variable
Portions” and [Link] Type “6 plan stat. key figures”.
After maintain above parameters click on another tab “Sender/Receivers” so it will display following screen:
In the above screen maintain sender cost center, sender cost element and receiver cost center under
“Senders/Receivers” tab.
After this click on “Receiver Tracing Factor” tab so it will take you to following screen;
CONTROLLING Page 84
CONTROLLING CONFIGURATION AND STUDY MATERIAL
In the above screen maintain Version , [Link] fig and pres on save button to save the activity.
After saving click on button so it will display new screen for another segment as follow:
In the above screen maintain Segment name and description. Under “Segment Header” tab Receiver rule “3 Fixed
Percentages”.
After maintain above parameters click on another tab “Sender/Receivers” so it will display following screen:
CONTROLLING Page 85
CONTROLLING CONFIGURATION AND STUDY MATERIAL
In the above screen maintain sender cost center, sender cost element and receiver cost center under
“Senders/Receivers” tab.
After this click on “Receiver Tracing Factor” tab so it will take you to following screen;
After entering above parameters click on save button and go back to easy access screen.
CONTROLLING Page 86
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Deselect this
Test Run
Click on this F4
function to assign your
Method
Now put your curse on Senders and click it will show the following screen with al senders:
CONTROLLING Page 87
CONTROLLING CONFIGURATION AND STUDY MATERIAL
CONTROLLING Page 88
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Now click on back and put you curser on Number of receivers and click on so it will show the following
window:
Now click on back button till you go back to easy access screen:
Path: Accounting Controlling Cost Center Accounting Information System Reports for Cost Center Accounting
Plan/Actual Comparisons S_ALR_87013611 - Cost Centers: Actual/Plan/Variance
CONTROLLING Page 89
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Deselect this
Test run
In the above screen just Deselect Test run and click on execute button.
CONTROLLING Page 90
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Path: Accounting Controlling Cost Center Accounting Information System Reports for Cost Center Accounting
Plan/Actual Comparisons S_ALR_87013611 - Cost Centers: Actual/Plan/Variance
CONTROLLING Page 91
CONTROLLING CONFIGURATION AND STUDY MATERIAL
In the above screen enter new Cycle name and start date and pres enter button.
So it will display following screen:
CONTROLLING Page 92
CONTROLLING CONFIGURATION AND STUDY MATERIAL
In the above screen under Tab “Segment Header” enter segment name and description, maintain Rule as “1 Variable
Portions”, [Link] Type as “8 Plan Activity” and click on TAB “Sender/Receivers”
In above screen maintain Sender and Receiver parameters and click on Tab “Receiver Tracing Factor”
CONTROLLING Page 93
CONTROLLING CONFIGURATION AND STUDY MATERIAL
After maintain parameters in above screen just save the activity and back to easy access screen.
Deselect this
Test Run Box
CONTROLLING Page 94
CONTROLLING CONFIGURATION AND STUDY MATERIAL
CONTROLLING Page 95
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Path: Accounting Controlling Cost Center Accounting Information System Reports for Cost Center Accounting
Plan/Actual Comparisons S_ALR_87013611 - Cost Centers: Actual/Plan/Variance
CONTROLLING Page 96
CONTROLLING CONFIGURATION AND STUDY MATERIAL
SPLITING
In every cost center we may have activity dependent cost or activity independent cost. It the cost center has a multiple
activities the activity independent cost is to be related distributed among the activities by specifying same distribution
rule it no distribution rule is specify the system split the activity independent cost equally among the activity.
Database Table: TSC0A, TSC0B, TSC0C, TSC0D, TSC0E, TSC0F, TSC0G, TSC0H, TSC0I
\In the above screen maintain the parameters as specified and click on executive button.
So it displays the following screen:
In the above screen keep curser on “CTR 1200” and click on button .
So it displays the following screen:
CONTROLLING Page 97
CONTROLLING CONFIGURATION AND STUDY MATERIAL
Path: SPRO Controlling Cost Center Accounting Planning Allocations Activity Allocation Splitting Define
Splitting Structure.
In the displayed screen under Dialog Structure double click on “Splitting Rules”
CONTROLLING Page 98
CONTROLLING CONFIGURATION AND STUDY MATERIAL
In the above screen enter new Rule name, text and method as “22”, pres enter and save the screen.
Now select the rule which you created and double click on “Selection for rules” under Dialog Structures.
In the above screen once you assign version “0” double click on “Splitting Structures” under Dialog Structure.
So it will display another screen as shown below:
CONTROLLING Page 99
CONTROLLING CONFIGURATION AND STUDY MATERIAL
In above screen give new structure name and text and save it.
Select the structure you created and double click on “Assignments” under Dialog Structure.
In the above screen give new assgnmnt, text and select your rule and pres enter.
Select your assgnmnt as you created above and double click on “Selection for Assignment” under Dialog Structure
In the above screen assign Cost elements and Activity Types and save the screen.
Once you saved the activity back to easy access screen.
Path: SPRO Controlling Cost Center Accounting Planning Allocations Activity Allocation Splitting Assign
Splitting Structure to Cost Centers
Select this
Check Box
In the above screen select your cost center check box and keep the curser on your splitting Structure
Now following Manu path as follow:
In the above screen you can see your cost center is assigned to your Splitting Structure
Now save the screen and back to easy access.
Maintain the above parameters and select executive button so it will display the following screen:
Path: Accounting Controlling Cost Center Accounting Information System Reports for Cost Center Accounting
Plan/Actual Comparisons S_ALR_87013611 - Cost Centers: Actual/Plan/Variance
Cost center budgeting provides a further method of planning in addition to primary cost and secondary cost planning.
This tool enables you to carry out a comparison between actual postings and plan budgets. You can thus determine
when the budget is exceeded and carry out timely availability checks. You can create budgets
You can see the budget data in a budget report. The budget report compares plan data , commitment data, and actual
data (resulting from actual postings) as well as the allotted and available amounts.
Prerequisites
Before you can plan your budget, you must create a budget profile during Customizing for Cost Center Accounting.
Alternatively, you may use an existing profile. You can change the following budget profile settings when you are
planning your budget:
Decimal places
Scaling factor
Distribution Keys
Procedure
To execute budget planning, proceed as follows:
Enter a budget profile.
The budget profile parameters specification of:
– The budgeting time period, in the past, or in the future
– The starting year in which budget planning is to begin
– The scaling and decimal places for the display of values in budget planning
– Period planning or fiscal year planning
– Default values for the distribution key.
[Link] Overview screen to access the overview screen of the annual values. You can then change the budget
of your cost center.
1. If you entered a cost center group in the initial screen of budget planning, you can choose Group structure
y/n function to display or hide the group structure.
If you choose Y, the system displays the top node of the group with the sum of all the planned budgets of
the lower-level cost centers.
2. If you have selected period values in the budget profile, you can choose Period overview to switch from the
list of annual values to the list of period values for a cost center.
The system distributes the plan annual value to the individual periods according to the distribution key
defined in the budget profile. You can change this distribution key in the period screen if required.
You can only select true distribution keys. True distribution keys break down an annual value into
monthly values, so that the sum of the monthly values equals the original annual value.
3. Choose Period values in the Annual values overview screen to display the individual period values for each
cost center. You can select a given period, or view all the period values of a cost center or cost center
group.
Path: SPRO Controlling Cost Center Accounting Budget Management Define Budget Planning Profiles.
In this above screen give new profile name, text and maintain other parameters.
Then click on save button and back to SPRO screen.
Path: Accounting Controlling Cost Center Accounting Planning Cost Center Budgets KPZ2 – Change
Select your Profile, Cost Center Group and pres enter button or button.
So it will take you to follow screen:
Now click on button and save the transaction so it will post the transaction.
When it posted it will posted with an Document number. in above case that document number is “100002”
Path: Accounting Controlling Cost Center Accounting Information System Reports for Cost Center Accounting
Plan/Actual Comparisons S_ALR_87013611 - Cost Centers: Actual/Plan/Variance
In the above screen 150000 is the amount posted to 1110 cost center. If we need to repost of that amount to other cost
center that means out of 150000 you want to post 50000 to other cost center like 1200 so for that do as follow:
In the above screen select the 150000 amount and delete, after deleting type required amount like above I had given
100000 and pres enter button so it automatically creates another line item with balance 50000 out actual like item of
150000. now change the cost center for other line item as you wish.
Path: Accounting Controlling Cost Center Accounting Information System Reports for Cost Center Accounting
Plan/Actual Comparisons S_ALR_87013611 - Cost Centers: Actual/Plan/Variance
Path: Accounting Controlling Cost Center Accounting Actual Postings Activity Allocation KB21N – Enter
After entering the data save the screen and back to easy access.
Sender Activity
Path: Accounting Controlling Cost Center Accounting Actual Postings Sender Activities KB51N – Enter
After entering the data save the screen and back to easy access.
Actual Price
Path: Accounting Controlling Cost Center Accounting Actual Postings Actual Price KBK6 - Enter
Once you enter the above parameters click on “Next Combination” button so it will display next Cost center “1300 –
Machine B” enter required entries as below:
Once you enter the above parameters click on “Next Combination” button so it will display next Cost center “1400 –
Assembling” enter required entries as below:
After entering above entries save the activity and back to easy access.
Path: Accounting Controlling Cost Center Accounting Actual Postings Statistical Key Figures KB31N - Enter
After you enter the above entries save the screen and back to easy access.
Path: Accounting Controlling Cost Center Accounting Period-End Closing Current Settings S_ALR_87005742 -
Define Assessment
After maintain above parameters pres button, so it will take you to following screen:
In above screen provide Segment Name, Description and for Receiver Rule “1 Variable Portions” for [Link] Type “5
Actual Statistical Key Figures”.
And go to Tab “Senders/Receivers”
In above screen maintain above parameters for Cost Center, Cost Element and Cost Center under Receiver.
Not go to Tab “Receiver Tracing Factor”
In the above screen for [Link] Fig maintain value and click on save button to save the activity.
In above screen provide Segment Name, Description and for Receiver Rule “1 Variable Portions” for [Link] Type “5
Actual Statistical Key Figures”.
And go to Tab “Senders/Receivers”
In above screen maintain above parameters for Cost Center, Cost Element and Cost Center under Receiver.
Not go to Tab “Receiver Tracing Factor”
In the above screen for [Link] Fig maintain value and click on save button to save the activity.
Now back to easy access screen.
Path: Accounting Controlling Cost Center Accounting Period-End Closing Single Functions Allocations KSU5
- Assessment
In the above screen assign your assessment cycle which your created in above step, maintain other parameters and
executive the section
Now place your curser on Senders and pres on Sender button. So it will display all sender list as follow:
Now back to the screen and place the curser on Number of Receivers and click on Receiver button.
So it will display the following screen:
Enter into the above path or transaction code so it will display the below screen:
Put the curser on either of the Object’s in above table and click on button so it will display clear
calculation as follow:
Enter into the above path or transaction code so it will display the below screen:
In the above screen give new Cycle name, Start date and click enter button so it will take you to following screen:
In the above screen maintain text and click on button so it display the below screen:
In the above screen first maintain Segment name and Description, under Tab “Segment Header” as Rule “1 Variable
Portions” and as [Link] Type “7 Actual Activity”.
Now click on Tab “Sender/Receivers”, so it will display the following screen:
In the above screen maintain the Cost center, Activity Type under Sender and under Receiver maintain cost Center and
click on Tab “Receiver Tracing Factor” so it will display the following screen:
Enter into the above path or transaction code so it will display the below screen:
In the above screen under Cycle assign above cycle name and maintain the above parameters.
In the above screen place the curser on senders and click on button so it will display the following screen:
In the above screen you can absover the sender details now back to previous screen.
Now place the curser on Number of receivers and click on so it will display the screen as below:
In the above screen you can find the no of recovers an amount received now back to easy access screen.
Splitting Cost
Enter into the above path or transaction code so it will display the below screen:
In the above screen maintain cost center and other parameters and click on button so it will display the following
screen:
In the above screen place the curse on cost center line item and click on so it will display the following
detail list:
Actual Activity
------------------ X 100
Plan Activity
Target Cost is used to compare with the actual cost for variance analysis.
COMMITMENT MANAGEMENT
(This activity we already did when we configure Enterprise Structure so look in that material)
Step 2: Assign Financial Management area to company code
(This activity we already did when we configure Enterprise Structure so look in that material)
Enter into the above path or transaction code so it will display the below screen:
In the above screen against to your FM area we have to assign our Fiscal Year Variant which we already created in
finance.
Now click on (SAVE) button to save the activity and back to SPRO screen.
Path: SPRO Controlling Cost Center Accounting Commitments and Funds Commitments Field Control for Funds
Commitment Assign field status variant to company code
Enter into the above path or transaction code so it will display the below screen:
In the above screen enter your company code and click enter button or click on button.
So your company code will appear at the top of screen as below:
In the above screen against to your company code on clicking of F4 function assigh “FMRE” that is “Earmarked fund
Status Variant” assign.
Now click on (SAVE) button to save the activity and back to SPRO screen.
Path: Accounting Public Sector Management Funds Management Master Data Account Assignment Elements
Commitment Item FMCIA - Individual Processing
Enter into the above path or transaction code so it will display the below screen:
In the above window enter your FM area and pres enter button.
So it will display the following screen:
In the above screen enter Commitment item and click on (Create) button.
It will activate other below fields as below:
In the above screen enter name, Description of Commitment and Financial Trans as “30” , Commitment item cat as “3”
Because this commitment I am creating for “Purchase account”.
Like above you can create any number of commitment items as client required. Each commitment item should assign to
a relevant GL Account as below step.
Path: Accounting Financial Accounting General Ledger Master Records G/L Accounts Individual Processing
FS00 - Centrally
Enter into the above path or transaction code so it will display the below screen:
In the above screen enter your GL Account number and click on edit button. Now go to “Create/Bank/Interest” tab under
“Bank/financial details in company code” assign your commitment item to “Commitment Item” field.
After maintain all above parameters save the GL Account and back to Easy access screen.
Path: Accounting Controlling Cost Center Accounting Actual Postings Funds Commitment FMZ1 - Create
Enter into the above path or transaction code so it will display the below screen:
Maintain the above parameters and click on enter button so it will display the following screen as below;
In the above screen maintain Original amount and commitment item as we create above step and assign G/L Account,
Cot center.
Path: Accounting Financial Accounting Accounts Payable Document Entry F-43 - Invoice – General
Enter into the above path or transaction code so it will display the below screen:
In the above screen enter The Document Date, Posting Date, Company Code, Currency/Rate and Account(Vendor no).
After entering above parameters click Enter button so it will display the following screen:
In the above screen enter invoice amount in Amount Coolum, enter Text, Pstky (Posting key that is GL Debit) and
Account that is G/L Account of Purchases.
After entering above parameters click Enter button so it will display the following screen:
In the above screen in amount column enter “ * ” symbol and in text column enter “ + ” symbol and click on
button .
In above screen select your Business area, Cost Center, Profit Center, Earmarked Funds and pres enter button.
Now in the same screen go to Manu bar “ Document – Simulate” as it shows below:
INTERNAL ORDER
Internal orders are used to plan, collect, analyze and monitor the cost of a specific job of cost. This can be used for
collection of cost of revenue information for:
1. Budget Profile
2. Settlement Profile
3. Planning Profile
4. Object Class
5. Functional area to be updated
6. Release Status
7. Control indicators for revenue postings
8. Commitment item & integrated Planning data
9. Field selection
10. Number Intervals
Internal orders are normally used to plan, collect, and settle the costs of internal jobs and tasks. The SAP system enables
you to monitor your internal orders throughout their entire life-cycle; from initial creation, through the planning and
posting of all the actual costs, to the final settlement and archiving:
Order management within a company usually differentiates between sales-oriented orders, and internal orders. Sales-
oriented orders (production or sales orders) are intended mainly for the logistical control of input factors and sales
activities. Internal orders are categorized as either:
Orders used only for monitoring objects in Cost Accounting (such as, advertising or trade fair orders)
Productive orders that are value-added, that is, orders that can be capitalized (such as in-house construction of
an assembly line).
Internal order management is the most detailed operational level of cost and activity accounting. It can be used for:
Cost monitoring, for example, where costs need to be looked at from object-related aspects, unlike in Cost
Element Accounting or Cost Center Accounting
Assisting decision-making, when you need to decide between in-house production and external
procurement
An enterprise’s internal orders can be used for different controlling purposes. For more information, see Classified by
Controlling Objectives.
Features
You can use master data to assign certain characteristics to your internal orders, which enables you to control
which business transactions can be used with the internal order.
Internal order planning enables you to roughly estimate the costs of a job before the order starts and to make
an exact calculation at a later date. You can choose between various planning approaches to compare the
effectiveness of different methods.
You can assign and manage budgets for internal orders.
You apply the actual costs incurred by a job to your internal orders using actual postings. In Financial
Accounting, you can assign primary cost postings (such as the procurement of external activities and external
deliveries) directly to internal orders.
In period-end closing you can use various different allocation methods (for example, overhead costing) to
allocate costs between different areas of Cost Accounting.
Order settlement enables you to transfer the costs incurred by an order to the appropriate receivers.
The information system for internal orders enables you to track planned and assigned costs on your orders in
each stage of the order life-cycle.
You can archive internal orders that you no longer require. See Archiving.
An internal order is used to monitor parts of the costs, and under certain circumstances, the revenues of the
organization.
You can create an internal order to monitor the costs of a time-restricted job or the costs (and revenues, if required) for
the production of activities. Internal orders can also be used for the long-term monitoring of costs.
Overhead cost orders are used for the time-restricted monitoring of overhead costs (that are incurred when you
execute a job) or for the long-term monitoring of parts of the overhead costs.
Investment orders let you monitor investment costs that can be capitalized and settled to fixed assets.
Accrual orders enable you to monitor period-related accrual calculation between expenses posted in Financial
Accounting and the costing-based costs debited in Cost Accounting.
Orders with revenues let you monitor costs and revenues that are incurred for activities for external partners,
or for internal activities that do not form part of the core business for your organization.
You can use model orders as a reference, when creating new internal orders.
You can find further information on the internal order types mentioned above, in Orders Classified by Content.
Are revenue postings are allowed (an order with revenues can only be settled to a G/L account or a business
segment)?
Is the plan integration with Cost Center Accounting and Activity-Based Costing active?
The system also uses the order type to determine default values for the various master data fields and to define given
attributes for the assigned orders.
With above path or Transaction code you will be entering to screen there click on so it will display the
following window:
In the above small window enter “01” as Order Category and pres enter button.
So it will display the below screen:
In the next step u have to maintain number ranges so click on “Number range Interval Edit button ”
In the above screen go to Manu bar “Group – Insert ” so it will display the following window:
In the above screen you can watch your Internal Order number range. Now flag the check box and double click your
internal order type which appears under the “Not Assigned” and click on button. So your Internal
Order Type will assign to your number range as below:
As the above screen showes your internal order type is assigned to your number range.
Maintain Settlement
In the above screen double click on “Assign Number Range for Settlement Documents”
In the above screen flat the check box “Standard accounting document”. Select and double click on your controlling area
under “Not assigned”. Now click on button so your controlling area will automatically assigned to
number range as follow:
Availability Control: The real time checking of the availability of funds, in order to identify possible budget under runs
or overruns when funds are being committed.
Overhead Cost Orders (CO-OM-OPA): An internal active funds controlling system that can identify possible budget under
runs or overruns when funds are being committed in respect of transactions assigned to projects.
Availability control can help you recognize possible budget overruns in time and can automatically trigger different
actions.
You configure availability control for each budget profile. You can define one or more tolerance limits for the different
activity groups within a budget profile. When these tolerances are reached, you can have the system trigger specific
actions (warning, warning with Mail, error message).
Path: SPROControllingInternal Orders Budgeting and Availability Control Define Tolerance Limits for Availability
Control
In the above screen maintain the parameters and save the screen and back to SPRO screen.
Assignments Assignments You can maintain the organizational assignments for your order (for
example, Company code, Business area)
Control Status A status documents the current processing status of an internal order.
It informs you that a particular status has been reached (for example,
"Order released"), and determines which business transactions you
can use.
System statuses are set by the system and inform you that
a given function has been performed on the internal order.
For example, if you release an internal order for actual
postings, the system automatically sets the appropriate
system status.
A User status is a status that you define to supplement
existing system statuses. You define user statuses in
Customizing, in a status profile, and then enter this in the
corresponding order type.
The system and user statuses currently active for an order are
displayed on the Control Data screen. Before executing a business
transaction for an internal order, ensure that at least one active status
allows it, and that none of the active statuses prohibits it.
Currency
Statistical key figure
Whether integrated planning is active
When you set the indicator for internal orders or projects, note that a
project cannot be plan integrated and statistical at the same time.
Period-end closing Period-end closing This is where you maintain, for example:
Settlement to one This is where you maintain the parameters for order settlement to one
Receiver receiver (Settlement cost element and receiving Cost center or
receiving G/L account).
General data General data In this sub screen you maintain general data, such as Applicant and
Responsible person for the order. This data is for information purposes
only and is not checked by the system.
Investments Investment This is where you maintain all the parameters required for capital
management investment orders (for example, Investment profile, Scale, Investment
reason)
Assignment to This is where you assign the order to one or more investment program
investment program / items.
Appropriation request
Simulation data for This is where you maintain the data for asset depreciation of the
depreciation investment order (for example Asset class).
Joint venture This is where you maintain all the additional parameters you need to
use the Joint Venture component. The system only displays this group
box when you activate the component.
In the above screen entry your “Order Type” which you created above steps.
In the above screen enter the text and other parameters as you required and go to tab “Prd-end closing”
It will as below:
In the above screen we entered the “Settlement Cost element” and “Cost Center” now clicks on tab “Control data”:
Maintain the above parameters under tab “Assignments” and go to another tab “Control Data”
In the above screen we entered the “Settlement Cost element” and “Cost Center” now clicks on tab “Control data”:
Click on this
button to change
the status
Now save the order. When u save the order it will save with a number that will display in the status bar as bellow.
Like this we can create any number of internal as per the client requirement.
Integrated planning for Internal Orders with Cost Centers or Business Processes
In integrated planning for internal orders, cost centers or business processes, you can integrate cost element and
activity input planning for an internal order with cost center or business process planning. You can do this in a plan
version. All the planned business allocations on the internal order (also repostings, assessments and so on) are then
automatically updated on the sender/receiver cost center, or on the sender/receiver business process.
You can only use integrated planning for Internal Orders with Cost Center Accounting or Activity Based Costing, if the
internal order already exists at the time of cost center or business process planning. You cannot lock the plan version.
You can only plan locally for internal orders that are not plan-integrated. The same applies to internal orders that did not
exist when you planned the cost centers or business process. You can also manually plan costs and activities on receiver
cost centers or business processes, when required.
Cost center two plans to take 2000 production hours from cost center one, using an internal order. The planning of
activities on the cost center and internal order can be integrated, because the internal order already exists in the
system, and the same time horizon is planned. If integrated planning is active, the scheduled activity for the order is
updated on cost center one. The settlement of the internal order in the plan is updated on cost center two (the receiving
cost center).
Cost center three plans to take 700 production hours from cost center one. No internal order exists at the time of cost
center planning. The internal order is created later and so cannot be integrated into planning. You need to execute cost
center planning manually, and independently from order planning.
Integrated Planning of Internal Orders with Profit centers, and the Extended General Ledger
If you activate integrated planning with Profit Center Accounting and the Extended General Ledger, the system transfers
planning data for internal orders and Cost Center Accounting to Profit Center Accounting and the Extended General
Ledger.
You need to activate the Integrated Planning indicator in the version. This ensures that the system makes the planning
data for internal orders available to other applications in the SAP system.
Path: AccountingControllingInternal Orders Planning Cost and Activity Inputs KPF6 - Change
In the above screen maintain all parameters and pres on “overview screen” button
So it takes you to the following screen as follow:
In the above screen enter the Cost element and Total plan cost values for order “90001 – Advertisement” and click on
In the above screen enter all relevant values to order “90002 – Profit analysis”
Save the screen and back to easy access screen.
The budget is the approved cost structure for an internal order or an order group.
In contrast to planning, budget management is binding. In the planning phase you need to estimate costs, whereas
during the approval phase, funds are prescribed by the budget.
Original Budget
This is the budget originally assigned, before any updates were made.
Budget Updates
Unforeseen events, additional requirements, for example, price rises for external activities, and so on. This may
mean you need to update the original budget, in the form of:
Supplements
Returns
Current Budget
This is derived from the budget types already mentioned:
Original budget
+ Supplements
- Returns
= Current budget
The method for assigning and updating budget and for configuring availability control for internal orders or order groups
is similar to that for projects, except that projects are organized in a hierarchy.
In the above screen enter your order number and pres enter or click on button.
So it will display the screen as bellow:
In the above screen enter the values for “overall”, “2008” and save the screen.
It takes to previous screen. Now enter another order as below:
In the above screen enter your order number and pres enter or click on button.
So it will display the screen as bellow:
In the above screen enter the values for “overall”, “2008” and save the screen and back to easy access screen.
In the above screen maintain the above information and click on button.
In the above screen it displays the plan, variance values. Once have a look on that and back to easy access.
Once you enter the above parameters click on enter button so it will take to following screen:
In the above screen maintain Amount, Cost Center, Order, PStky (Posting key), Account and click on enter button.
It will display another screen as below:
In the above screen maintain Amount, Cost Center, Order, PStky (Posting key), Account and click on enter button.
It will display another screen as below:
In the above screen maintain Amount, Cost Center, Order, PStky (Posting key), Account and click on enter button.
In the above screen click on “MORE” button so it will display the following screen:
In the above screen assign Segment as “Project - 1” and pres on enter button
Now go to Manu bar “Document - Simulate” so it will display the following screen as below:
Go to Manu bar “Document – Post ” so it will post the above document to tables with the reference an document number
a bellow:
In the above screen maintain the above information and click on button.
Path: Accounting Financial Accounting Accounts Receivable Document Entry F-22 - Invoice – General.
In the above screen I maintain the Document Date, Posting Date, Company Code, Currency/Rate, PstKy (Posting Key),
Account (Customer Account number).
Once you maintain all above click enter button so it will display another screen as follow:
In the above screen maintain the amount, PstKy, Account (Sales Account) and pres enter button so it will display another
Screen.
In the following screen click on button. So it will display the following screen:
In the above screen maintain above parameters and pres in enter button.
In the above screen maintain the above information and click on button.
It is a tool used to estimate standard cot per unit of a product & to determine the cost of goods manufactured & cost of
goods sold. This tool contains the following areas:
COMPONENTS OF COST
5. Material Cost
6. Process or Conversion cost
7. Overheads
Manufacturing or Production Overheads
Administrative Overheads
Selling and Distribution Overheads
Product Cost Planning (CO-PC-PCP) is an area within Product Cost Controlling (CO-PC) where you can plan costs for
materials without reference to orders, and set prices for materials and other cost accounting objects.
You can use Product Cost Planning to analyze the costs of your company’s products such as:
Manufactured materials
Services
Other intangible goods
You can analyze costs to help provide answers to questions such as:
Cost Estimate with Quantity Structure Costing materials based on a quantity structure in PP
Price Update Transferring the results of material cost estimates to the material
master
Reference and Simulation Costing Planning new products and services using base planning objects
Easy Cost Planning and Execution Rapid cost planning without master data within an ad hoc cost
Services estimate
The following graphic provides an overview of the organizational structures required for costing:
Features
The following table gives you an overview of the menu and functions of Product Cost Planning:
Cost estimate for multiple Used to process mass data, and is created
Material Costing Edit
materials with BOM and automatically with Production Planning data
Costing Run
routing (product cost estimate)
Reference and Simulation Created using data you enter manually (unit
Base object cost estimate
Costing costing)
Easy Cost Planning & ... Created using a planning form (costing
Execution Services Edit ... Ad hoc cost estimate model) that can access the data in the SAP
Ad hoc Cost Estimate system
Material Costing Price Transfer of cost estimate results to the material master record
Update
Material Costing Master Definition of procurement alternatives and mixing ratios for a mixed cost
Data for Mixed Cost estimate
Estimate
Easy Cost Planning & Define planning forms for Easy Cost Planning
Execution Services Edit
Costing Model
Information System Reports for Product Cost Lists of existing material and base
Planning object cost estimates
Detailed reports
Comparison reports
BOMs are used in their different forms in various situations where a finished product is assembled from several
component parts or materials. Depending on the industry sector, they can also be called recipes or lists of ingredients
and so on.
They contain important basic data for numerous areas of a company, for example:
· MRP
· Material provisions for production
· Product costing
· Plant maintenance
You can create the following BOMs in the SAP system:
· Material BOMs
· Equipment BOMs
· Functional location BOMs
· Document structures
· Order BOM
· Work breakdown structure (WBS) BOM
Bills of material are used in their different forms in various situations where a finished product is assembled from several
component parts or materials. Depending on the industry sector, they may also be called recipes or lists of ingredients.
The structure of the product determines whether the bill of material is simple or very complex.
Where-used list
You can generate where-used lists to determine in which bills of material certain components are used.
BOM comparison
By using a bill of material comparison you can compare two different bills of material with each other.
For information on how to perform a BOM comparison, refer to the SAP documentation, PP - Bills of Material.
You can call up the BOM comparison function in Plant Maintenance using the following menu sequence:
Note: To configure this step we need to have one Finished good and few (At least 2) Raw materials through Transaction
Code: MM01 and maintain the attributes to material types like FERT, ROH through Transaction Code: OMS2
When you are creating finished good you should take selections as below:
Path: Logistics Production Master Data Bills of Material Bill of Material Material BOM CS01 – Create
In the above screen provide your Raw Material number, plant, BOM Usage, Valid From and pres enter button so it display
actual screen as below:
In the above screen under components provide all raw materials and quantities which are used to produce a finished
good in this BOM.
Now save the activity.
It will display the following message:
Operations are carried out at a work center. In the SAP system work centers are business objects that can represent the
following real work centers, for example:
· Machines, machine groups
· Production lines
· Assembly work centers
· Employees, groups of employees
Together with bills of material and routings, work centers belong to the most important master data in the production
planning and control system. Work centers are used in task list operations and work orders. Task lists are for example
routings, maintenance task lists, inspection plans and standard networks. Work orders are created for production,
quality assurance, plant maintenance and for the Project System as networks.
The data is grouped thematically together in screens and screen groups. Examples of such screen or screen groups are:
· Basic Data
· Assignments (to cost centers, Human Resource Management System (HR))
· Capacities
· Scheduling
· Default values
· Hierarchy
· Technical data
Path: Logistics Production Master Data Work Centers Work Center CR01 – Create
In the above screen enter your plant, new entry for Work center and Work center Category and pres enter button so it
will take you to another screen below:
In the above screen under Tab “Basic data” enter Location, usage and Standard value key.
After entering above parameter click on Tab “Costing”.
So it will display following screen:
In the above screen new Work Center and click on enter button so it will display below screen:
In the above screen under Tab “Basic data” enter Location, usage and Standard value key.
After entering above parameter click on Tab “Costing”.
So it will display following screen:
In the above screen new Work Center and click on enter button so it will display below screen:
In the above screen under Tab “Basic data” enter Location, usage and Standard value key.
After entering above parameter click on Tab “Costing”.
So it will display following screen:
A routing is a description of which operations (process steps) have to be carried out and in which order to produce a
material (product). As well as information about the operations and the order in which they are carried out, a routing
also contains details about the work centers at which they are carried out as well as about the required production
resources and tools (includes jigs and fixtures). Standard values for the execution of individual operations are also
saved in routings.
Routing
Rate routing
Reference operation set
Reference rate routing
A routing is used as a source for creating a production order or a run schedule header by copying.
Routings enable you to plan the production of materials (products). Therefore, routings are used as a template for
production orders and run schedules as well as a basis for product costing.
Integration
In order to You also require the components
Plan the usage of materials Material master (LO-MD-MM)
Plan the use of work centers Work centers (PP-BD-WKC)
Plan the external processing of operations Purchasing (MM-PUR)
Plan quality inspections that accompany Quality planning (QM-PT)
production
Prepare cost calculation according to Controlling (CO)
routings
Plan and to document changes to routings Engineering Change Management (LO-ECH)
Classify routings Classification system (CA-CL)
Automatically calculate the planned values CAPP Standard Value Calculation (PP-BD-CAP)
for the activities to be produced
In the SAP system, routings have the same basic structure as the following objects:
· Master recipes
· Inspection plans
· Maintenance plans
· Standard networks
Therefore, routings are cumulated with these objects under the super ordinate term Task list.
In a routing you plan
Path: Logistics Production Master Data Routings Routings Standard Routings CA01 - Create CA01 -
Create
In the above screen assign your Raw material number, plant and Key date details and pres enter button so it take to
another screen as below:
In the above screen maintain usage and Status and click on Button so it will take you to another
screen as below:
Inter above screen enter work centers as we created above screen and select “PP01”as Control key for all Work centers
under Control Key field.
Now select first line “0010” as shown above and double click on Control key “PP01” against “1000” Work center so it will
display following screen:
In the above screen maintain Setup, Machine, Labor values under Std Value and Un values and pres back button so
it take you to following screen:
In the above screen select “0020” and double click on “PP01” under Control Key field so it display the following screen:
In the above screen maintain Setup, Machine, Labor valued under Std Value and Un values and pres back button so
it take you to following screen:
In the above screen select “0030” and double click on “PP01” under Control Key field so it display the following screen:
In the above screen maintain Labor value under Std Value and Un values and save the activity so it will display the
following message:
A definition of how values posted in the sap system are calculated. A costing sheet consists of one or moor of the
following lines:
1. Base Lines -
These contain the amount or quantity on which the overhead is calculated. Base rows contain the
calculation base of the overhead costing: the cost elements and origins to which overhead is to be applied you can take
the calculation bases directly from the costing sheet and then maintain them as necessary.
For each controlling area, you assign individual cost elements or cost element intervals, or organs or
origin intervals, to the calculation bases.
For production overhead costs, we can differentiate between fixed and variable costs for the
calculation base. In this way, you can charge the fixed and variable portions of the activity price differently for activity
types.
For material overhead cost, you can differentiate the materials used. If you want to define different
material overhead costs for particular raw materials we can define origin groups and define your own calculation bases
for particular or origin groups.
2. Calculation Lines -
These contain the percentage rate to be applied to one or more baselines
3. Total Lines -
These contain the sum of the base amount and calculated amounts.
Where they used to calculate overhead. We define the overhead rows by assigning an overhead rate to
them. An overhead row references one or more base rows or totals rows. The amount contained in these rows along with
the percentage rate calculated using the overhead rates determines the overhead amount. You can take the overhead
rates directly from the costing shet and then maintain them as necessary, or define them separately.
The overhead row contains a credit key that defines which object is credited during the overhead
calculation. You can either take the credit keys directly from the costing sheet and then maintain them as necessary, or
define them separately in the define credit activity.
6. Overhead cost controlling, where they are used to calculate resource pries
Path: SPRO Controlling Product Cost Controlling Product Cost Planning Basic Settings for Material Costing
Overhead Define Costing sheet rows
By the above transaction it will display the following screen pres on button:
In the above under Costing field give new entry and description and save the activity.
Now select the same and click on “Costing Sheet Rows” under Dialog Structure.
It will display the following screen:
In the above screen maintain above table and select firs row “10” and click on “Base” under Dialog Structure. So it will
display the following screen:
It will ask for Controlling area in a small box enter it and pres enter button.
In the above screen enter cost elements range and double click on “Costing sheet rows” under Dialog Structure so it will
display the following screen:
Now in the above row select row “30” and double click on “Base” under Dialog Structure, so it will display the following
screen:
It will ask for controlling area in a small box enter it and pres enter button.
In the above screen enter cost elements range and double click on “Costing sheet rows” under Dialog Structure so it
will display the following screen:
Now in the above row select row “50” and double click on “Base” under Dialog Structure, so it will display the following
screen:
It will ask for controlling area in a small box enter it and pres enter button.
In the above screen enter cost elements range and double click on “Costing sheet rows” under Dialog Structure so it
will display the following screen:
In the above screen select row “20” and double click on “Overhead rate” under Dialog Structure.
So it will display following screen:
In the above screen maintain Overhead rate table and click on “Costing sheet rows Rows” under Dialog Structure.
So it will display the following screen:
In the above select Row “20” and click on “Credit” under Dialog Structure.
So it will display the following screen:
It will ask for Controlling area in a small box enter it and pres enter button.
In the above screen under Credit table maintain the above parameters and click on “Costing sheet rows” under Dialog
Structure.
So it will display the following screen:
In the above screen select row “40” and double click on “Overhead rate” under Dialog Structure.
So it will display following screen:
In the above screen maintain Overhead rate table and click on “Costing sheet rows Rows” under Dialog Structure.
So it will display the following screen:
In the above select Row “20” and click on “Credit” under Dialog Structure.
So it will display the following screen:
It will ask for controlling area in a small box enter it and pres enter button.
In the above screen under Credit table maintain the above parameters and click on “Costing sheet rows” under Dialog
Structure.
So it will display the following screen:
In the above screen select row “60” and double click on “Overhead rate” under Dialog Structure.
So it will display following screen:
In the above screen maintain Overhead rate table and click on “Costing sheet rows Rows” under Dialog Structure.
So it will display the following screen:
In the above select Row “20” and click on “Credit” under Dialog Structure.
So it will display the following screen:
It will ask for controlling area in a small box enter it and pres enter button.
After maintain above Credit table save the activity and back to SPRO screen.
Purpose
Costing with a quantity structure is a tool for planning costs and setting prices for materials without reference to orders.
It is used to calculate the cost of goods manufactured and cost of goods sold for each product unit. You can use the
results of material cost estimates with a quantity structure to valuate materials at standard prices.
Implementation Considerations
Before a cost estimate with a quantity structure can be created, a bill of materials and routing (PP) or a master recipe
(PP-PI) must exist for the material being costed.
A cost estimate with a quantity structure uses the PP or PP-PI master data to determine the materials and internal
activities required to manufacture the product. The cost estimate is created automatically using this data.
Calculation of (Cost of Goods Manufactured) COGM and (Cost of Goods Sold) COGS
You can use the Product Cost Planning functions to calculate the cost of goods manufactured (COGM) and cost of goods
sold (COGS) for products such as materials and services. The costs may then be analyzed and used in business decisions
(such as whether to make or buy).
The cost of goods manufactured is composed of material and production costs, process costs and overhead (such as
material and production overhead). The cost of goods sold consists of the cost of goods manufactured together with
sales and administration overhead costs.
The following graphic shows how the COGM and COGS are calculated using Product Cost Planning:
To calculate the COGM and COGS for materials, you can execute a material cost estimate (with or without quantity
structure).
To calculate the COGM and COGS for products that do not have any master data (such as services or materials at the
planning stage), you can avail yourself of the Reference and Simulation Costing functions. For further information, see
the following:
Before costing, check all the settings in Customizing for Product Cost Planning that apply to the calculation of costs. For
further information, see the following:
You can use the following reports in the Product Cost Controlling Information System to analyze the costs:
The costing variant contains control parameters and settings for costing. These settings determine how costing is
executed, such as which prices the system uses to cost materials, activities, and business processes.
The control parameters in the costing variant and the settings you need to make will vary depending on whether you are
creating a material cost estimate or a base object cost estimate.
Each costing variant specifies a particular valuation variant and costing type.
A costing variant for material cost estimates contains additional control parameters, such as for automatic
determination of the quantity structure and for updating the prices in the material master.
The costing variant contains all the control parameters for costing.
The costing variant for a material cost estimate contains the following
control parameters:
Costing type
Valuation variant
ate control
Quantity structure control (only relevant for cost estimates with quantity structure)
Transfer control (optional)
Reference variant (optional)
Since this costing variant can be used for cost estimates both with and without quantity structure, you must also make
the settings that are only relevant for cost estimates with quantity structure even if you are only executing a cost
estimate without quantity structure.
o Whether transfer control can be changed when calling the cost estimate
o Whether an active standard cost estimate can be transferred if the cost estimate for a material contains errors
o Whether you can transfer the cost components that were entered in the form of an additive cost estimate
o Whether the additive costs for materials with the special procurement types stock transfer or production are
included in another plant
o Whether the costing results can be saved and what values are updated
The cost component split is always updated. You must specify whether the following values are also updated:
- Itemization
- Log
o Whether the user can change the update parameters and the parameters for transfer control
o Whether the cost component split can be saved in the controlling area currency in addition to the company
code currency
o Whether you can cost across company codes with this costing variant
Standard Settings
The standard system contains a number of predefined costing variants. To check which parameters are inked to these
costing variants, use the Check settings function or choose the Check costing variants function in the detail screen.
A standard cost estimate calculates the standard costs for a semifinished or finished product. Costing type 01
specifies that the results of this cost estimate are written to the material master as the standard price, and thus can be
used to valuate inventories. Costing variant PPC1 specifies valuation variant 001, quantity structure determination ID
PC01, and date control PC01. No transfer control takes place.
You create a modified standard cost estimate when the data for costing has changed within a planning period. Costing
type 12 specifies that the results of this cost estimate are used only for informational purposes. Costing variant PPC2
specifies valuation variant 009, quantity structure determination PC01, and date control PC05.
You create a current cost estimate when you want to make a decision based on the current price of the material.
Costing type 13 specifies that the results of this cost estimate are used only for informational purposes. As an
alternative, you can set the indicator Prices other than standard price in the costing type so that the results of this cost
estimate can be written to the material master as a planned price. Costing variant PPC3 specifies valuation variant 009,
quantity structure determination PC01, and date control PC04.
The preliminary cost estimate for the product cost collector is used to calculate preliminary costs on the basis of the
quantity structure of a production process. Costing type 19 means that this cost estimate is only relevant for product
cost collectors. Costing variant PREM specifies valuation variant 001, transfer control PC02, and date control PC01.
Quantity structure determination is not relevant, as quantity structure is determined through the production process.
Path: SPROControllingProduct Cost ControllingProduct Cost PlanningMaterial Cost Estimate with Quantity
StructureDefine Costing Variants
2) Click on this
Details button
1) Select PPC1
Variant
In the above screen select “PPC1” Costing Variants and click on Details button as I shown in above screen.
It displays the following screen:
In the above screen first go to tab “Overhead” in this tab you can view tow Buttons 1. Costing Sheet (Overhead on
Finished Goods, Semi Finished Goods), 2. Costing Sheet (Overhead on Material Consumption).
1) Agents 1st button Costing Sheet (Overhead on Finished Goods, Semi Finished Goods) drag the button and select your
Costing sheet (in above case it is “1102 1102 Cost of goods Manufacturi”)
2) Agents 2nd button Costing Sheet (Overhead on Material Consumption) drag the button and select your Costing sheet
(in above case it is “1102 1102 Cost of goods Manufacturi”)
So it will be as bellow:
Now click on save button to save the activity and back to SPRO screen.
Controlling (CO)
The cost component structure groups cost elements into cost components
to show the following information:
o Cost of a process
Cost Component
The costs from a cost estimate are assigned to cost elements and cost components.
The following graphic illustrates how cost components, cost component structures, and cost views are customized:
Cost components are grouped into a cost component structure. A cost component structure can have up to 40 cost
components. However, if the cost components contain both fixed and variable costs, the number of costs components is
limited to 20.
Examples of cost components are:
Raw materials
Personnel costs
Production costs
Overhead: material
Overhead: production
Overhead: administration
Overhead: sales and distribution
External activities
Other costs
If you are using a particular costing variant, the system determines the cost component structure for this costing variant
and creates the cost component split for the costing results accordingly.
All costing variants for the standard cost estimate in a company code must be linked to the same cost component
structure. Otherwise you cannot transfer costing results from other plants for specially-procured materials.
For costing variants that are not set for the standard cost estimate, you can assign the cost component structure
separately for each plant or for each costing variant.
The values for each cost component are updated in the currency of the company code to which the material is assigned.
You can define a cost component structure so that the cost estimate for a finished product shows the origin of the costs
for the semifinished products and raw materials.
You can define the cost component structure to have a validity period. You can specify the date from which the structure
is to be valid. This means that you can use an alternative cost component structure for the cost estimate without having
to change an existing structure. In addition, cost estimates that have already been saved can still be interpreted by the
system.
Through the cost components that you list in the cost component structure, you specify the following:
· Which costs are included
· Whether the variable costs or the total costs are included
· Whether the cost of goods manufactured or the sales and administration costs are included
· Whether the costs for inventory valuation, tax-based inventory valuation, and commercial inventory valuation
are included
If you use a cost component structure in Customizing to create a primary cost component split for products, the cost
component splits of the items that are relevant to costing are included in the primary cost component split. In addition
to materials, internal activities and process costs can also have cost component splits.
You can create cost component views on the basis of the Customizing settings for the cost components. When you
display a material cost estimate, cost component views show the costing results according to different viewpoints.
Path: SPRO Controlling Product Cost Controlling Product Cost Controlling Basic Settings for Material Costing
Define Cost Component Structure
in the above screen select “01” under Cost [Link] field and double click on “Assignment: Cost Component – Cost
Element Interval”.
An new window will display as below:
In this window click on .
In above screen main table with cost elements and cost components. Now double click on “Cost Components with
Attributes” under Dialog Structure
So it will display following screen:
In the above screen double click on “Raw Materials” so it will display the following screen:
In the above screen maintain the above parameters as you required and as I shown above.
Save the activity and click on “Cost Component Structure” under dialog structure
So it will display the following screen:
In the above screen select “Active” check box for “[Link] - 01”.
Save the screen and back to SPRO screen.
This cost estimate is a tool for planning material costs without reference to orders, and for setting prices for materials. It
is used to calculate the cost of goods manufactured and cost of goods sold for each product unit.
The following functions are available for material cost estimates with quantity structure:
The cost estimate with quantity structure enables you to calculate the non-order-related cost of goods manufactured
and the cost of goods sold for products, based on the BOMs and routings (PP).
Path: Accounting Controlling Product Cost Controlling Product Cost Planning Material Costing Cost Estimate
with Quantity Structure CK11N – Create
In the above screen enter your Finished good number, plant, Costing variant as “PPC1 (Standard Cost Estimation)” and
Costing Version as “1”
Maintain
Future dates
In the above screen under Tab “Dates” for “Costing Date from”, “Qty Structure Date”, “Valuation Date” should maintain
future dates and “Costing Date To” should be maintain last date of plan of production.
Previous standard price Release a new standard cost estimate. The current
standard price becomes the previous standard price.
You can use the results of the standard cost estimate to valuate the materials for standard prices (see graphic). When
you release the standard cost estimate, the price in the material master is updated as the standard price and the
materials are revaluated. From this point on, all the material movements are valuated at the new price. However, this
applies only to materials with S price control.
Costing can access the future or current standard price in the material master for material valuation purposes, provided
you have defined the appropriate strategy in the valuation variant in Customizing for material valuation (see graphic).
For more information, see Define Valuation Variants in the Implementation Guide for Product Cost Planning.
Prerequisites
To update the standard cost estimate results as the standard price in the material master record, the following
conditions must be met:
The cost estimate has the status KA: Costed without errors. Only the results of cost estimates without errors
can be updated.
The costing results have been saved to the database. To be able to save a cost estimate, you must ensure that
the indicator Saving allowed is turned on in the costing variant.
The setting has been made to update the costing results as the standard price. For this, the indicator Standard
price indicator must be turned on in the costing type.
In addition, the costing type must also specify that the date of costing is saved to the database, and that this
date is always the start of period.
The period of validity of the cost estimate (Costing date from) must correspond with the current period in the
material master. You cannot update the standard price for periods that have elapsed. To release the costing results, you
must wait until the relevant posting period has arrived.
The following graphic provides an overview of updating the costing results as the standard price:
To set a new standard price in the material master, you must mark and release the standard cost estimate. Before you
can mark and release a standard cost estimate, you must allow standard cost estimates to be marked and released in a
company code.
If you mark a standard cost estimate for a material, the price calculated in the standard cost estimate is transferred into
the material master record as the future standard price (see graphic). However, the materials with "S" price control
continue to be valuated with the current standard price (see graphic).
If you release a standard cost estimate for a material, the marked price is transferred into the material master record
as the current standard price for the current period. This price is then active for external accounting. The materials
with "S" price control are valuated with the new standard price. The current standard price becomes the previous
standard price (see graphic).
You can repeat the marking at any time. However, this can only be done once in a period. For this reason, you should
check the costing results before marking and releasing. To do this, use the reports in the Product Cost Controlling
Information System.
You can use the Information System to make comparisons, such as using a price from the material master, or the future
or current standard price, to the costing results. This enables you to correct any variances before the materials are
valuated with the new standard price.
Once you have released the cost estimate, you cannot create a new standard cost estimate in this period. Although you
can delete a released cost estimate, the materials are still valuated with the released standard price. When a current
standard cost estimate is deleted, the previous standard price no longer becomes the current standard price. To
determine a new standard price, you have to carry out costing, marking and releasing afresh.
Marking, releasing, and marking allowance are protected by authorization checks. The person authorized to execute
these functions must enter the authorization object K_FVMK (CO-PC: Release/marking product costing) in the user
master record.
Path: Accounting Controlling Product Cost Controlling Product Cost Planning Material Costing CK24 - Price
Update
Take next
month planed
period
In the above window give future month periods details in “Posting period/Fiscal year” field and provide information to
Company code, plant, Material and click on button so it will display the below screen:
2. Assign PPC1
1. Click on your
company code
In the above screen click on your company code so it will display an small sindow in that window select “PPC1” as
Costing variant and save the activity and back to main sceen.
Production orders can only be processed and back flushed in the linked. Planned orders that were created in APO are
converted into production orders in the linked system. The current production order data relevant for planning is
transferred from the R/3 or ERP system to APO.
Features
You can use the production order to specify:
· What is to be produced?
· When production is to take place
· Which capacity is to process the order?
· How much production costs?
Path: SPRO Production Shop Floor Control Master Data Order Define Order Types
In the above screen select “PP01” line and click on (Details) button so it will take you to other screen as below:
In the above screen “Co Partner update” make it “Active” and save the activity and back to SPRO Screen.
We define the data that influences master data selection or order master data maintenance:
You can decide whether production versions are selected automatically or manually.
The task list application is predefined as 'P'. However, you can also specify an additional task list application.
The routing selection ID defines, for example, the ranking order for routing selection.
Routing selection defines whether routings are to be selected and if so, how (manually or automatically) and
whether reference operation sets can also be selected.
Alternative sequences and sequence exchange define whether alternative sequences are permitted and how
the sequences are to be exchanged.
The task list type defines which routing type is permitted for production orders.
Operation check defines whether operation detail screens are to be checked when the operations are
transferred to the order.
Routing text defines that the text from the routing header is copied into the order.
You can activate the entry tool for operations to help you when you create operations.
BOM application defines how the BOM alternatives are to be automatically selected.
Path: SPRO Production Shop Floor Control Master Data Order Define order type-dependent parameters
In the displayed screen click on button so it will display the following window:
In the above window take plant as 1000 and Order Type as “PP01” and click on continue button or click on enter, so the
selection plant 1000 will appears on the top of the window as below:
Now select the plant 1000 and click on (Copy) button so it will display the below window:
In the above screen change Plant value to your plant value in above case my plant is “1102”and “Reduction Strategy”
under Operation, “Substitute MRP ctrller” , “Substitute Scheduler” under “Assignment” should blank, so delete the
values in these fields.
Now pres enter button so it will display previous screen now click on (save) button and back to SPRO screen.
You can make the checking rule as well as the actual check itself dependent on the following parameters:
Plant
Order type
Operation
The operation can have the following characteristics:
Order created
release (d) order
Whether an availability check is to be carried out when you create or release an order
Whether an availability check is to be carried out when you save an order that has been created or released
Path: SPRO Production Shop Floor Control Operations Availability Check Define Checking Control
In the displayed screen click on button so it will display the following window:
In the above window take plant as 1000 and order type as pp01 and pres enter button so it will display those values at
the top to window as below:
Now like above screen showes select two values 1) 1000 (Plant), PP01 (Type) 1 (Business Function); 2) 1000 (Plant),
PP01 (Type), 2 (Business Function) and click on (Copy) button.
So it will display below screen.
In the above screen to Plant field give your plant number and other all parameters are same and pres enter button so it
will display another screen as below:
In the above screen to Plant field give your plant number and other all parameters are same and pres enter button so it
will display another screen, save the activity and back to SPRO screen.
the scheduling function calculates the production dates and capacity requirements for all operations within an order or a
collective order.
A system function that determines the start and end time of a service assignment.
Scheduling is based on the start and end time and estimated duration of a service task, taking availability information
for the service employee into account. Scheduling can be performed manually by the resource planner for the service
center, or be executed by the system according to certain specifications.
The main objectives of the scheduling function of IS-Oil downstream are as follows:
The system calculates the start and finish dates of orders or of operations in an order.
Material requirements planning: In-house production times and delivery times specified in the material master
record are taken into account.
Capacity planning: Scheduling is performed using routings. A distinction is made between lead time scheduling
in which capacity loads are not taken into account, and finite scheduling in which capacity loads are taken into
account.
Networks: Scheduling calculates the earliest and latest dates for the execution of the activities, and the
capacity requirements and floats.
"Today" scheduling: a scheduling type for rescheduling an order if the start date is in the past
Path: SPRO Production Shop Floor Control Operations Scheduling Define Scheduling Parameters for Production
Orders
In the displayed screen click on button so it will display the following window:
In the above small window provide required parameters as above and pres enter button so it will display the those at the
top of window:
Now select the plant 1000 and click on (Copy) button so it will display the below window:
In the above screen change plant number to your plant number and pres on enter button.
It will display the previous screen with your plant. Now save the activity and back to SPRO screen.
We define the confirmation parameters for each plant and order type. The parameters are split up as follows on tab
pages
o Control
The properties of the control key Process control are defined elsewhere in Customizing (it can also be called
using the symbol next to the control key). It controls the execution of the confirmation processes.
You can define how quantities are determined for automatically generated confirmations (milestone/progress
confirmation).
o Checks
What happens when the sequence of operations is not adhered to during confirmation or
What happens when you want to confirm a larger quantity than was confirmed for the preceding operation You
can choose between a termination message, an error message, a warning message and an information
message.
whether you want the total confirmed quantity of an operation checked for under delivery or over delivery
tolerance in the order header
What effect a QM result recording has on the confirmation.
whether dates (for example, posting date, end of lead time, etc) should also be displayed with a date that is
further in the future than the time of creation
o HR Update
o Selection
You specify that only open orders are selected in the collective order.
o Goods movements
Using the all components indicator, you can specify that the system should display all the components assigned
to the operation in the goods movement overview (in other words, not only back flushed components).
However, if you do not branch to the material overview at confirmation, the system only posts back flushed
components.
o Confirmation function
You can define here whether a partial confirmation, a final confirmation or a final confirmation with clearing of
open reservations is to be proposed for the confirmation.
o Error handling/logs
You can use the indicator Actual costs to specify that the log is also displayed if there are no error messages
(thus only warnings or information messages). You can use the Error handling indicator to specify that an error
log is displayed for incorrect items in goods movements (for back flush or automatic goods receipts). You then
have another opportunity to correct the items with errors before saving, with the aid of the material overview.
Define the confirmation parameters for each plant and order type.
Path: SPRO Production Shop Floor Control Operations Confirmation Define Confirmation Parameters
In the displayed screen click on button so it will display the following window:
In the above window take plant as 1000 and Order Type as “PP01” and click on continue button or click on enter, so the
selection plant 1000 will appears on the top of the window as below:
Now select the plant 1000 and click on (Copy) button so it will display the below window:
In the above screen change plant number to your plant number and pres on enter button.
It will display the previous screen with your plant. Now save the activity and back to SPRO screen.
The costing variant contains the control parameters for the cost estimate.
In this step you check the costing variants that are used for the following in Product Cost by Order:
The SAP standard system contains the following costing variants for manufacturing orders:
This valuation variant controls which prices are used for the valuation of materials, external activities and
subcontracting and which activity prices are used for the valuation of activity types and business processes.
Furthermore, the costing sheet that you assign to this valuation variant is defaulted into the master data of the
manufacturing order. This costing sheet is used for overhead calculation in preliminary costing for the manufacturing
order and actual overhead calculation in period-end closing.
This costing type specifies that the costing results are updated as actual costs.
This valuation variant determines which activity prices are used to valuate the activity types and business
processes on which the following activites are performed in the actual data:
- Manual allocation
- Automatic allocation through confirmation in PP
- The manufacturing order is charged through the template allocation
Note: While it is technically possible to have two costing variants with the same costing type and valuation variant, this
should be avoided to prevent data from being overwritten. This is because the key structure for the costing results in the
database uses the costing type and the valuation variant, rather than the costing variant.
Path: SPRO Controlling Product Cost Controlling Cost Object Controlling Product Cost by Order Manufacturing
Orders Check Costing Variants for Manufacturing Orders (PP)
In the above screen select “PPP1” Costing Variant and double click on that, so it will display the following screen:
In the above screen click on button so it will display the following screen:
In the above screen first click on “Overhead” tab. In this screen against “Costing Sheet” button assigh your Costing
sheet as above shown.
This step is only relevant if your have specified price control V in the material master records of semifinished products or
finished products.
In this step you specify how the receipts for materials with price control V are valuated.
When the master record of a material specifies price control V, the value for the credit is determined using a valuation
variant. You must define this valuation variant separately for each valuation area. The valuation variant determines
which material price is used for the credit posting.
For materials with price control S, on the other hand, the credit posting is always made at standard [Link] you deliver to
stock at a price that is not the standard price, the system will report an output price variance in variance calculation.
Path: SPRO Controlling Product Cost Controlling Cost Object Controlling Product Cost by Order Define Goods
Received Valuation for Order Delivery
By the above transaction it will display the following screen, click on button.
In the above screen give your plant number under “[Link]” and “[Link]” as “007”.
A key specifying that the object is to be selected during results analysis or when work in process is calculated.
Each order for which you want to create work in process (WIP) must receive a results analysis key. The presence of a
results analysis key in the order means that the order is included in WIP calculation during period-end closing.
The results analysis key can be specified as a default value for each order type and plant. It is then added to the order
master record when an order of a particular order type is created.
For each combination of controlling area, results analysis version, and results analysis key, you then later specify the
valuation methods according to status.
You can also assign the source cost elements under which an order is debited to different line IDs for each results
analysis key. This updates the results analysis data under different results analysis cost elements. This is recommended
when you are using multiple results analysis methods in parallel. For example, if you calculate work in process at actual
costs in the Product Cost by Order component and want to calculate results analysis data in the Product Cost by Sales
Order component, the results analysis data is updated under results analysis version 0. To enable different groupings of
costs, you update the results analysis data according to the results analysis key. Whether you update the results
analysis data according to the results analysis key is defined in the results analysis version.
WIP calculation determines the value of the unfinished products in the Product Cost by Period component and in the
Product Cost by Order component. WIP calculation in Product Cost by Order or Period is used chiefly in make-to-stock
production, sales-order-related production with a valuated sales order stock, and engineer-to-order environments with a
valuated project stock.
If you are using a nonvaluated sales order stock or a nonvaluated project stock, the work in process for orders that are
assigned to a sales order item or project is normally calculated using results analysis for the sales order item or project.
However, you can use the indicator Calculate WIP for manufacturing orders in sales-order-related production or the
indicator Calculate WIP for manufacturing orders in engineer-to-order in the results analysis version to specify that work
in process can be calculated separately for the assigned orders. In this case the results analysis key in the order
takes precedence:
If no results analysis key is specified in the order, the actual costs for the order are included in results analysis
for the sales order or project. Settlement is through the sales order or project.
If a results analysis key is specified in the order, work in process is created and settled for the order in the
amount of the actual costs incurred. These costs are not included in results analysis for the sales order or
project. This method is particularly recommended when you are manufacturing across company codes.
You control whether a sales order stock or a project stock is valuated or non valuated in the requirements class.
Path: SPRO Controlling Product Cost Controlling Cost Object Controlling Product Cost by Order Period-End
Closing Work in Process Define Results Analysis Keys
By the above transaction it will display the following screen, click on button.
In the above key enter RA Key and Text. Now save the activity and back to SPRO screen.
A version that enables multiple valuations of the same object (such as a sales order item) in results analysis and in the
calculation of work in process.
Example
For balance sheet purposes, the object is valuated using a method that determines the value of the unfinished
products on the basis of the actual cost incurred to date.
For internal analysis purposes, the value of the unfinished products is determined using a method that includes
unrealized profits.
All results analysis data (work in process in the Product Cost by Period component, and work in process or reserves for
unrealized costs in the Product Cost by Order component) calculated in results analysis is updated on the order with
reference to the results analysis version. This enables you to calculate work in process on the basis of multiple results
analysis versions simultaneously. This means that you can use different results analysis versions to do the following:
Define different methods of WIP calculation You can create results analysis versions along with operational
valuation that are based an "internal" results analysis version created for internal purposes, rather than on
multiple valuation. This means that you can use different results analysis versions to:
- Define different amounts of work in process to be capitalized If you are operating in different countries,
you can
- Define different results analysis versions to take into account the different legal requirements in each
country.
Calculate work in process at actual costs in up to three valuation views in the Product Cost by Order component
If you are using transfer prices, you can calculate the results analysis data in the following valuation views:
Legal view
Group view
Profit center view
In the Product Cost by Period component, the work in process at target costs is always calculated in the operational
valuation view.
Path: SPRO Controlling Product Cost Controlling Cost Object Controlling Product Cost by Order Period-End
Closing Work in Process Define Results Analysis Versions
By the above transaction it will display the following screen, click on button.
In the above screen when you click on New Entries it will display an “Restrictions” window. In that window double click
on your Controlling area.
In the above window against “Technical RA Cost Element” assign your Secondary Cost element as I shown in above
window.
Now save the activity and back to SPRO screen.
In this step you define a valuation method for the calculation of work in process.
This creates the link between the controlling area, the results analysis key, the results analysis version, and the system
status.
When you create new valuation methods, you specify whether the work in process should be valuated at target costs or
actual costs.
In the Product Cost by Period component the work in process is valuated at target costs. The valuation is made on the
basis of the quantities confirmed at the operations or reporting points.
calculation due to scrap confirmations at subsequent operations In the period-end closing activities in the Product
Cost by Period component, the relevant quantities (WIP quantities) are valuated according to the valuation variant for
work in process and scrap (target costs) and reported as work in process.
In the Product Cost by Order component the work in process is normally valuated at actual costs. The value of the work
in process is the difference between the debit and the credit of an order as long as the order has the status PREL
(partially released) or REL (released).
The following status codes are relevant for WIP calculation in this component:
If the status is PREL or REL, the system creates work in process in the amount of the actual costs with which the order is
debited.
If the status is DLV or TECO, the system cancels the work in process. The difference between the debit through actual
costs postings and the actual credit of the order from goods receipts is interpreted as a variance with this status.
If you want to calculate the work in process at actual costs, create a valuation method for each combination of
controlling area, results analysis version, and results analysis key for the statuses that are relevant to WIP calculation.
This valuation method must specify the following:
How the work in process should be calculated when the order status is PREL
How the work in process should be calculated when the order status is REL
How the work in process should be calculated when the order status is DLV
How the work in process should be calculated when the order status is TECO
If you valuate the work in process at actual costs, you must make sure that the work in process that is created and
settled in a period can be canceled at a later time. You do this by defining valuation methods for the cancellation.
o PREL - The order is partially released. An order is partially released for which the individual operations are
released.
When an order has the status PREL and REL, in the Product Cost by Period
component the system creates work in process by multiplying the WIP quantity by the target costs in accordance with
the valuation variant for work in process and scrap (target costs).
If you want to calculate work in process at target costs, then for each combination of controlling area, results analysis
version, and results analysis key, you must specify a valuation method for the statuses relevant to WIP calculation.
Proceed as follows:
For the status PREL, enter the status number 1. The system generates a valuation method of results analysis
type S (calculate work in process based on the target costs).
For the status REL, enter status number 2. The system generates a valuation method of results analysis type S
(calculate work in process based on the target costs).
Path: SPRO Controlling Product Cost Controlling Cost Object Controlling Product Cost by Order Period-End
Closing Work in Process Define Valuation Method (Actual Costs)
By the above transaction it will display the following screen, click on button.
In the above “Valuation type” window click on “Actual Costs” so it will display the following screen:
In the above window maintain parameters as in shown and click on continue button or click on enter button so it will
take you to previous screen:
Now again click on button, it will display the “Valuation type” window.
In the above “Valuation type” window click on “Target Costs” so it will display the following screen:
In the above window maintain parameters as in shown and click on continue button or click on enter button.
In this step you create line IDs. The line IDs group the work in process and reserves for unrealized costs according to
the requirements of Financial Accounting.
The work in process and reserves for unrealized costs are calculated as a total for each order and distributed to the
line IDs. You can then define separately for each line ID whether the work in process for that line ID must be capitalized.
WIP calculation updates the work in process and reserves for unrealized costs on the order, grouped by line ID. To
transfer the data to Financial Accounting, you must define posting rules that associate the data with G/L accounts.
Path: SPRO Controlling Product Cost Controlling Cost Object Controlling Product Cost by Order Period-End
Closing Work in Process Define Line IDs
By the above transaction it will display the following screen, click on button.
1. Determine which cost elements you have to assign to line IDs. To display the cost elements valid in your controlling
area, go into Cost Center Accounting and select Reporting -> Master data index -> Cost [Link] must also assign
settlement cost elements that you use in the allocation structure to a line ID. Example: Suppose you are using a
nonvaluated sales order stock. You have not selected Settlement by cost element in the allocation structure. The
system settles the actual costs charged to manufacturing orders to a sales order item. Settlement is made under a
settlement cost element that you have specified in the allocation structure. You must assign this settlement cost
element to a line ID.
2. Enter the controlling area, your results analysis version and, if necessary, your results analysis key.
3. Enter the cost elements, as in your cost element list, under which the primary postings are to be written to the
orders, or to the standard cost estimate. You can mask these entries. If you enter 00004+++++, for example, all cost
elements from 400000 to 499999 will be included. If you want particular cost elements to be treated separately, enter
them without masking (example: 0000415000). Numeric values must be entered right-justified. Alphanumeric values
must be entered left-justified. For material costs, you can define separate line IDs for particular origin groups by entering
origin groups in the costing views of the relevant material master records, and entering these origin groups with the
relevant cost elements in the line IDs. If you don't want to differentiate the line IDs by origin group, mask the origin
group (i.e., enter ++++).
4. Enter the secondary cost elements under which internal cost allocations are written to the orders or under which the
cost estimate on which the the target cost calculation is based are updated. For production costs, you can define
separate line IDs for particular cost centers, or cost centers and activity types, by entering a cost center and an activity
type for secondary cost elements. If you want to differentiate the production costs only by cost elements, mask the cost
center and activity type with ++++. If you want to create separate line IDs for the fixed and variable costs from Cost
Center Accounting, you can enter "V" or "F" in the var-fixed costs column.
8. If you are valuating the work in process with actual costs, also enter the cost elements, as in your cost element list,
under which debits from deliveries and partial deliveries are posted.
Path: SPRO Controlling Product Cost Controlling Cost Object Controlling Product Cost by Order Period-End
Closing Work in Process Define Assignment
By the above transaction it will display the following screen, click on button.
After maintaining the above parameters save the activity and back to SPRO screen.
If you use a results analysis version that is in the standard system, you only have to enter the results analysis cost
elements for the data to be calculated.
- Controlling area
o You must assign all debits, such as for material withdrawals, internal activates, external activities, and overhead to
line IDs of category K (costs). The system creates work in process for each debit posting that is updated under one of
these cost elements. These values are updated under the results analysis cost elements (cost element category 31) that
you specify under Define update.
o You must assign all credits, such as for material issues and order settlement to line IDs of category A (settled costs).
For each credit posting that is updated under one of these cost elements, the system reduces the work in process.
This category indicates whether the cost elements under which the costs are written in the cost estimate on which
target cost calculation are based are relevant to WIP calculation. (See also: Define Valuation Variant for WIP and Scrap
(Target Costs).
o Create line IDs of category K (costs) for costs relevant to valuation (such as, direct material costs).
o Create line IDs of category N (do not take into account) for costs for which no work in process is to be created (such
as production overhead). If you do not create line IDs for these costs, the system issues an error message. The
apportioned values are updated to the order under the cost elements that you specify here. For the specified cost
elements you may have to do the following:
o Define reports that show the work in process and possibly the reserves according to you requirements
o Define posting rules that assign the work in process and reserves to G/L accounts so that these values can be passed
on to Financial Accounting
Path: SPRO Controlling Product Cost Controlling Cost Object Controlling Product Cost by Order Period-End
Closing Define Update
By the above transaction it will display the following screen, click on button.
After maintaining the above parameters save the activity and back to SPRO screen.
In this step you specify the G/L accounts in Financial Accounting to which the work in process is settled. You assign a
results analysis cost element or a group of results analysis cost elements to two G/L accounts.
A posting document is generated in Financial Accounting on the basis of the settlement of work in process.
If you have specified a profit center in the order (product cost collector or manufacturing order) the data is also
forwarded to Profit Center Accounting.
You can assign the results analysis data to the G/L accounts at the following levels:
If you are calculating the work in process at actual costs, the system creates reserves for unrealized costs if the credit
for the production order based on goods receipts is greater than the debit of the order with the actual costs incurred to
date. In this case the following results analysis categories are created:
Reserves for unrealized costs must be shown as a liability. If you create line IDs for all three results analysis categories
through the assignment, you must define posting rules for all three categories.
1. Decide which G/L accounts you want to settle work in process to.
- Controlling area
- Company code
You can also specify G/L accounts in the posting rules for which the Post automatically only indicator in the G/L account
master is selected. If the G/L account you enter in the posting rules does not have the Post automatically only indicator
selected, and if you have to make correction postings for results analysis data, (such as work in process), you have the
following options:
- You can use a different G/L account for the correction posting.
4. When you have finished this step, set the "Financial accounting" indicator for the results analysis version.
5. If you are using Profit Center Accounting, you also define posting rules for the work in process that cannot be
capitalized.
Path: SPRO Controlling Product Cost Controlling Cost Object Controlling Product Cost by Order Period-End
Closing Define Posting Rules for Settling Work in Process
By the above transaction it will display the following screen, click on button.
After maintaining the above parameters save the activity and back to SPRO screen.
When a production order is created the following actions are carried out:
· A routing is selected, its operations and sequences are transferred to the order
· The bill of materials is exploded and the items in the bill of material are transferred to the order
· Reservations are generated for bill of material items held in stock
· The planned costs for the order are generated
· The capacity requirements are generated for the work centers
· Purchase requisitions are generated for non-stock items and externally-processed operations
A production order specifies which material is to be produced, where it is to be produced, which operations are required
to do this and on which date production is to take place. It also defines how the order costs are to be settled.
As described in this procedure, production orders can be created manually without being previously requested.
Alternatively, they can be automatically created by converting a planned order. During requirements planning (MRP
run), planned orders are created at every BOM level to cover requirements. For materials produced in-house, a
secondary requirement is also generated when the BOM is exploded, which is necessary for producing the end product
or assembly. For externally produced materials, an ordering transaction is initiated when a purchase requisition is
generated.
Planned orders generated in the MRP run can be converted individually into production orders from the current
stock/requirements list. They can also be grouped together by the MRP run and converted into production orders
together. These production orders can be released together.
Scrap Scrap quantity that occurs O Enter, if required, in the base The system
portion during production unit of measure increases the
order by this
proportion
Scheduling Key which specifies the R Retain, if necessary Defines which date
type scheduling type for detailed is entered by the
scheduling (backward, forward user and which
and so on) date is calculated
by the system
Path: Logistics Production Shop Floor Control Order Create CO01 - With Material
Quantity to produce
In the above screen enter Total quantity to be produced and under “Dates” enter future dates to “Finish, Start” and pres
enter button.
The above table shows the cost of production. Back to main screen.
Now to release the order either pres “Ctrl+F1” or in the Manu bar “Functions – Release”
It will give you a message:
Make a note of the order number and back to easy access screen.
Path: Logistics Production Shop Floor Control Goods Movements MB1A - Goods Issue
In the above screen give Movement Type is “261”, plant and Storage Location. Now pres enter button.
It will display the following screen:
In the above screen enter the Cost Center, Order number which you got from above step, raw material numbers (raw
material number which are used in creation BOM)and quantity.
Pres enter button and save the screen.
Back to easy access.
Path: Logistics Production Shop Floor Control Confirmation Enter CO15 - For Order
In the above screen enter your Production order number and pres enter:
In above screen under “Confirmation Type” take “Final Confirmtn” radio button.
Yield to Conf is “500”
Now save the activity and back to easy access.
Path: Logistics Production Shop Floor Control Period-End Closing Overhead Calculation KGI2 - Individual
Processing
In the above screen maintain period, de-select “Test Run” and select “Dialog Display” check box and execute
In the above screen select your [Link] and click on Details Button.
In the above screen flag the check box of “Transfer to financial Accounting”.
Path: Accounting Controlling Product Cost Controlling Cost Object Controlling Product Cost by Order Period-
End Closing Single Functions Work in Process Individual Processing KKAX - Calculate
Now place your curser on “ORD 60003305” and go to Man bar “Goto – Wip report”.
Path: Logistics Materials Management Inventory Management Goods Movement Goods Receipt MB31 - For
Order
In the above screen maintain required parameters as above and pres enter.
So it will display the following screen:
In the above screen pres enter button and save the screen. so it will issue the following message.
PROF
ITABILITY ANALYSIS
Profitability Analysis (CO-PA) enables you to evaluate market segments, which can be classified according to products,
customers, orders or any combination of these, or strategic business units, such as sales organizations or business
areas, with respect to your company's profit or contribution margin.
The aim of the system is to provide your sales, marketing, product management and corporate planning departments
with information to support internal accounting and decision-making.
Two forms of Profitability Analysis are supported: costing-based and account-based.
· Costing-based Profitability Analysis is the form of profitability analysis that groups costs and revenues
according to value fields and costing-based valuation approaches, both of which you can define yourself. It
guarantees you access at all times to a complete, short-term profitability report.
· Account-based Profitability Analysis is a form of profitability analysis organized in accounts and using an
account-based valuation approach. The distinguishing characteristic of this form is its use of cost and revenue
elements. It provides you with a profitability report that is permanently reconciled with financial accounting.
Using the SAP master data (customer, product, customer hierarchy) or CO-PA derivation rules, the system can derive
additional characteristics based on the ones entered manually or transferred from primary transactions. The
combination of characteristic values forms a multidimensional profitability segment, for which you can analyze
profitability by comparing its costs and revenues.
The actual postings represent the most important source of information in CO-PA. You can transfer both sales orders and
billing documents from the Sales and Distribution (SD) application component to CO-PA in real time. In addition, an
interface program is available to let you transfer external data to the SAP system. You can also transfer costs from cost
centers, orders and projects, as well as costs and revenues from direct postings (G/L account postings in FI, orders
received in MM, and so on) or settle costs from CO to profitability segments.
In costing-based CO-PA, you can valuate incoming sales orders or billing documents to automatically determine
anticipated sales deductions or costs. You can also revaluate your data periodically to adjust the initial, real-time
valuation or add the actual costs of goods manufactured.
In CO-PA Planning, you can create a sales and profit plan. Whereas both types of Profitability Analysis can receive actual
data in parallel, there is no common source of planning data. Consequently, you always plan either in accounts
(account-based CO-PA) or in value fields (costing-based CO-PA). In costing-based CO-PA you can use automatic
valuation to calculate planned revenues, sales deductions and costs of goods manufactured based on the planned sales
quantity.
Structures
To use Profitability Analysis (CO-PA), you have to create structures first. The possible valuation levels are determined in
the creation of structures.
To create the structures, you need to define the operating concern as well as the characteristics and value fields
belonging to the operating concern.
From a technical point of view, you are actually creating different tables. To find out how these tables are related to
each other, you can consult the section Database Tables for CO-PA Transaction Data.
In the operating concern, you can define your structures so that the revenues and sales deductions (= value fields) that
are shown correspond to the respective levels (customer, customer group, sales office, and product (= characteristics)).
Characteristics
The characteristics in Profitability Analysis represent those criteria according to which you analyze your operating results
and your sales and profit plan.
Valid values of these characteristics are combined to form profitability segments. You can use concepts within the SAP
System, such as "Customer" and "Sales organization," to define characteristics. In addition, you can manually define
your own characteristics when you customize your SAP System.
The characteristics you define are stored in a field catalog. Using the function Maintain operating concern, you can
select characteristics from this field catalog to define your operating concerns.
The semantic meaning of a characteristic is determined by the data element to which it is assigned. The data element
contains the texts that appear on the screen and in lists for the characteristic.
Fixed characteristics
A number of fundamental characteristics are automatically predefined in every operating concern. These include the
product number, company code, billing type, business area, sales order, customer, and the controlling area, to name but
a few.
In addition, each type of Profitability Analysis has its own fixed characteristics:
Predefined characteristics
In addition to the fixed characteristics, a number of other predefined characteristics are available in the field catalog.
Such characteristics include customer group, customer district, and country, and they can be added to your operating
concern if desired.
Customer-Defined Characteristics
In addition to these predefined characteristics, you can also define your own additional ones. You define these in the
field catalog— independent of any client or operating concern —and can later add them to your operating concerns.
You can define your operating concerns by using characteristics that already exist in other applications. For example,
you can select fields from the tables for customer master records, material master records, and sales documents. You
can also select the partner roles defined in the structure PAPARTNER in the Sales and Distribution (SD) application and
use them as characteristics in Profitability Analysis.
The table that you take a characteristic from is referred to as that characteristic’s origin table. Characteristics that you
take from the SAP table are then derived automatically from the key fields in the SAP table. The system creates the
necessary derivation steps automatically.
Your operating concern contains the characteristic Customer district, which comes from the sales data in customer
master table KNVV. The key fields of this table are the customer number, sales organization, distribution channel, and
division. When you make a posting that contains these four characteristics, the system automatically derives the correct
customer district.
Custom Characteristics
If the characteristic categories are insufficient for your needs, you can define completely new characteristics from
scratch for exclusive use in Profitability Analysis. To derive values for these newly defined characteristics, you need to
create your own derivation rules.
To define such a characteristic, you need to specify the technical name, a description, a short text, a title, and the data
type and length of its values. The texts you enter for this characteristic are used to identify the characteristic on
transaction screens and in lists.
Value fields
The value fields contain values and quantities that were updated or planned for particular objects.
In costing-based profitability analysis, value fields represent the highest level of detail at which you can analyze
quantities, revenues, sales deductions, and costs for profitability segments in profitability analysis or contribution margin
accounting. You are able to define the revenues and costs that go into specific value fields for profitability reports or
sales and profit planning when you set up your SAP System.
Example
You can define your sales deductions to reflect the structure of sales deductions in SD conditions.
For the cost of goods manufactured, costs can be represented in accordance with the costing sheet in material
costing (or summaries thereof).
Value fields are only required in costing-based Profitability Analysis. These are the fields that contain the currency
amounts and quantities that you want to analyze in CO-PA. They represent the structure of your costs and revenues.
The semantic meaning of a value field is determined by the data element to which it is assigned. The data element
contains the texts that appear on the screen and in reports for the value field.
Value fields can be categorized according to how and when they are defined:
· Predefined value fields
Value fields that are used frequently are predefined in the standard system. These include fields such as revenue, sales
quantity, incoming freight, outgoing freight, and others. You can select those predefined value fields that you wish to
transfer into your own operating concern.
A representation of a part of an organization for which the sales market is structured in a uniform manner.
By setting off the costs against the revenues, you can calculate an operating profit for the individual market segments
that are defined by a combination of classifying characteristics (such as product group, customer group, country, or
distribution channel). The market segments are called profitability segments.
All the characteristics in the operating concern are used in the line item. However, you can restrict the characteristics for
a profitability segment that forms the basis for valuation. This is because it is unnecessary and impractical for a
profitability segment to use characteristics that are almost always populated and each has a different value. You should
deactivate such characteristics when creating a profitability segment. Otherwise the data volume of the profitability
segments is too large and hampers system performance.
One characteristic that should not be used in profitability segments is the sales order in repetitive manufacturing.
Before you can execute some of the functions for Profitability Analysis (CO-PA), you first need to specify the operating
concern for which the function is to be performed and the type of Profitability Analysis (costing-based or account-based)
you wish to use.
You set the operating concern by defining its settings and specifying the desired type of Profitability Analysis in a dialog
box. The settings in this dialog box are then valid until you log out of the system or reset the operating concern.
When you first call up a function that requires an operating concern, the dialog box appears automatically if the
operating concern has not yet been set.
If you only have one operating concern or generally only work with one operating concern, it makes sense to enter this
operating concern and the required type of Profitability Analysis in your user master data. By doing so, the dialog box
will no longer appear, even when you logon again to the system. The system then uses the operating concern and the
type of Profitability Analysis stored in the user master record. Moreover, you can call up the dialog box at any time to
switch to a different operating concern or to the other type of Profitability Analysis. The entries stored in the user master
record then apply all the while you are still logged on to the system.
Path: SPROControlling Profitability Analysis Structures Define Operating Concern Maintain Operating Concern
In the above window give new name to “Operating concern”, and click enter button so it will display the following
information window:
In above screen provide Description, flag check boxes “Costing-based”, ”Account-base” and first save the activity and
click on button.
It will display another screen below:
In the above window in “Chars” tab under “Transfer from” select “REGID – Region” as I shown above and click on
(Transfer Fields) so the field will transfer to “Data Structure” window as below:
In the above screen in “Value Fields” tab under “Copy from” window select required Value fields.
As the above list base on your requirement select Value Fields as I shown above and click on (Transfer Fields) so
the field will transfer to “Data Structure” window as below:
In the above screen under “ATTRIBUTES” tab provide “Operating Concern Currency”, “Fiscal Year Variant” and click on
save button, it will give you the following box with a message:
When you transfer data to Profitability Analysis, the system derives the appropriate operating concern from the
controlling area, and derives the controlling area, in turn, from the company code. In Customizing, therefore, you
have to assign each operating concern at least one controlling area. Generally, you assign several controlling areas.
Path: SPRO Enterprise Structure Assignment Controlling Assign controlling area to operating concern
in the above window give your controlling area and pres enter so it will appears you controlling area on the top to
window.
In the above screen your controlling area is at top so assign your “Operating Concern” now save the activity and back to
SPRO screen.
In the above window enter your Operating Concern and click on enter button.
All revenues, sales deductions and other values (such as transfer prices) are defined as conditions in SD. In this step,
you assign these conditions to the corresponding CO-PA value fields.
Note that certain limitations exist on the transfer of condition values of billing documents to CO-PA.
1. To transfer condition types for sales revenues and sales deductions to CO-PA, you need to make sure that the
condition types and linked to an account in FI that is also defined as a cost element of the category "11" (revenue
element) or "12" (sales deduction) in CO. These condition types must be assigned to a CO-PA value field. Condition types
linked to FI accounts that are defined as cost elements of another category are not transferred to CO-PA, even when the
condition type has been assigned to a CO-PA value field.
2. Condition types such as "VPRS" ("Cost") that are defined as statistical in SD are always transferred to CO-PA if they
are assigned to a value field.
3. All condition types that you want to transfer to CO-PA must be active in the SD pricing procedure. Inactive conditions
in a billing item are not transferred. If all the conditions in a billing item are inactive, that item is not transferred to CO-
PA. Conditions do not need to be active, however, to be transferred with sales order items, since the transfer of
incoming sales orders is always statistical.
It is also possible to transfer conditions from MM to update billing data in pooled payment in the IS Retail system. These
are transferred according to the same rules as SD conditions.
Conditions from SD are always transferred to CO-PA with "+" signs, with the exception of credit memos and returns. The
reason for this is that the signs for revenues are handled differently in the different applications of the system. For
example, revenues are positive in SD, while they are negative in FI. Consequently, CO-PA accepts all the values as
positive, and then subtracts deductions and costs from revenues in the information system.
Note that the indicator Transfer +/- signs is not used to compare the different use of +/- signs between FI or SD and CO-
PA. If you activate this indicator, only the positive and negative values for the condition in question will be balanced. his
guarantees that the sum of the negative and positive condition values is displayed as a correct total value in the value
field assigned to that condition.
Prerequisites:
The level of detail of the valuation in the SD billing document must meet the requirements for value fields in
Profitability Analysis.
It is not necessary to activate the conditions for transferring sales order data, since this transfer is solely for statistical
purposes.
Path: SPRO Controlling Profitability Analysis Flows of Actual Values Transfer of Billing Documents Assign Value
Fields
In the above screen double click on “Maintain Assignment of SD Conditions to CO-PA Value Fields”
So it will display the following screen in that click on button:
Maintain the above parameters and save the activity and back to SPRO screen.
A number of quantity fields are defined and used in the SD billing system. In this step you assign these to the
corresponding quantity fields in costing-based Profitability Analysis (CO-PA).
Assign all the quantity fields you want to transfer from the billing system to costing-based CO-PA. Additional Information
You can transfer the billed quantity to costing-based CO-PA using the sales unit as well as the stock keeping unit. The
assignment you make here is valid for both profitability planning and for actual postings.
This assignment is particularly important for planning, because the system can automatically derive the unit for the
quantities you plan manually for individual products.
Path: SPRO Controlling Profitability Analysis Flows of Actual Values Transfer of Billing Documents Assign
Quantity Fields
In the above screen select the relevant fields, save the activity and back to SPRO screen.
You can transfer direct primary postings from Financial Accounting (FI) and Materials Management (MM) to profitability
segments.
You post special direct costs from sales, such as transport insurance for a certain delivery, and would like to assign
these primary costs directly to a profitability segment.
You post an invoice for promotional events and you want this invoiceto appear statistically in the responsible
marketing cost center, and at the same time assign it to a profitability segment in Profitability Analysis. In this case,
you would assign the invoice to both a cost center and a profitability segment.
You create automatic postings in Materials Management and you want these revenues and expenses from the
evaluation of material stocks to be posted automatically to Profitability Analysis. This instance also requires that you
define "Automatic assignment to a profitability segment".
In this activity, you define the PA (Profitability Analysis) transfer structure FI, which you use to post costs and revenues
directly to profitability segments. In the PA transfer structure "FI", you specify how the cost elements are to be defined
to the CO-PA value fields.
You can choose to transfer the posted amount to CO-PA as well. For this, include in the assignment the corresponding
quantity field along with the value field(s).
Since this maintenance dialog is also used in the definition of PA transfer structures for other allocations, there are
several selection options that do not apply to the PA transfer structure "FI". These options are discussed below under
"Activities".
Activities
2. Divide your cost elements according to how you want to group them in Profitability Analysis, and create assignment
lines accordingly. Note: The indicator for quantity billed/delivered is not relevant for PA transfer structure FI and hence
should not be activated.
3. For each assignment line, enter the cost element or the cost element group to be assigned. As the source, activate
the "Costs/Revenues" option.
4. For each assignment line, enter the value field (or, if the costs are split into fixed and variable portions, both value
fields) into which costs/revenues are to be imported.
Path: SPRO Controlling Profitability Analysis Flows of Actual Values Direct Posting from FI/MM Maintain PA
Transfer Structure for Direct Postings.
In the above screen select “FI – Financial Accounting --> CO-PA” and click on “Assignment lines” under Dialog Structure.
It will display the following screen:
On that click on button:
In above screen enter new Assgnmnt values like “60,70” with Text and save the activity.
Now select “Assgnmt line 60” and click on “Source” under Dialog Structure
It will display the following screen:
In the above screen enter Cost Element values and click on “Value Fields” under Dialog Structure.
It will display another screen in it click on button.
In the above screen provide parameters as I shown and click on “Assignment lines” under Dialog Structure.
It will display the following screen:
In the above screen select “70 – Advertisement” and click on “Source” under Dialog Structure,
It will display the following screen:
In the above screen enter Cost Element values and click on “Value Fields” under Dialog Structure.
It will display another screen in it click on button.
In this step you define rules for allocating cost center costs and process costs to Profitability Analysis (CO-PA) in the form
of cycles.
1. The header of the cycle contains the parameters that are valid for the entire cycle. This includes the sender
selection type, where you specify for actual data whether you want to assess all costs together or fixed and variable
costs separately.
2. The segments contain the combinations of sender cost centers/sender processes and receiver profitability segments
that are processed using a single distribution rule.
Specify either an assessment cost element or an allocation structure, which determines more than one
assessment cost element for each cost element group. The sender cost centers/sender processes are credited
using these secondary cost elements (cost element category 42). In account-based CO-PA, the receiver
profitability segments are also credited using this cost element.
Specify either single value fields for the fixed and variable costs, respectively, or a PA transfer structure that
determines more than one value field for each cost element group.
Specify the rule which you want to use to credit the sender.
Note that, for technical reasons, you can only use an allocation structure or a PA transfer structure with sender rule "1"
(posted amounts).
Define the tracing factor, the rule which determines how the values are distributed to the receivers. For
example, you can distribute certain percentages to the different receivers or distribute using certain values
(such as the quantity sold or the revenue) as an allocation base. If you choose to use an allocation base, choose
the receiver rule "Variable portions".
Path: SPROControlling Profitability Analysis Flows of Actual Values Transfer of Overhead Assess Cost Center
Costs / Process Costs Define Structure of Cost Center Assessment/Process Cost Assessment
In the above screen double click on “Create Actual Assessment”, it will display the following screen:
In the above screen provide Cycle name to “Cycle” field and enter “Start Date” pres enter butto so it will take you to
following screen:
In the above screen enter values to “Text”, CO Area”, and “TF basis” as I shown above and click on
“Attach Segment” Button.
It will display another screen as below:
In the above screen select “13 – PS Settlement” under Alloc. structure and double click on “Assignments” under Dialog
In the above screen enter new assignment with text and pres enter button.
Select above assignment line which we just enter and click on “Source” under dialog structure, it will display the
following screen:
In the above screen enter cost elements and click on “Assessment cost element” under dialog structure, it will display
the following screen:
In the above screen click on enter PSG under “Receiver cat” and flag the check box “By Cost Element”.
Save the activity and click on back button till you get segment screen as below:
In the above screen under “Receiver Tracing Factor” enter Recore type, Plan/[Link] values and save the activity.
Back to SPRO screen.
Path: SPRO Controlling Profitability Analysis Flows of Actual Values Activate Profitability Analysis
In the above screen against to your [Link] assign “4 – Component active for bouth types of profitability analysis”.
Save the activity and back to SPRO screen.
Path: SPRO Controlling Profitability Analysis Flows of Actual Values Information System Report Components
Define Key Figure Schemes
In the above screen enter new values to “Key Figure Scheme”, “Medium-Lenth Text”.
Click on “Element of the key figure scheme” under dialog structure.
It will display the following screen:
In the above select “9002 Revenue” in “Value field” and pres on button.
In the above screen select “9008 Cost of goods sole” in “Value field” and pres button.
It will shows as below:
In the above screen after entering all information click on “ ” button 2 times save the activity.
Back to SPRO screen.
Transaction Code:KE31
In the above screen double click on “Create Profitability Report” it display the following screen:
In the above screen give new name to report (name should start with Y or Z) and description.
Select radio button “Basic Report”
Click on Create button it will displays the following screen:
In the above screen right side under “Chart List” select following fields”
1. Country
2. Region
3. Company code
4. Fiscal Year.
Once you select those fields click on ([Link]) button so it will transfer field as below:
In the above screen click on check box against “country” so it will display following screen:
In the above screen to “Local Variable” field enter “Country” and click continue button or click enter button.
Now click on check box against “region” so it will display following screen:
In the above screen to “Local Variable” field enter “Region” and click continue button or click enter button.
Now click on check box against “Company Code” so it will display following screen:
In the above screen to “Local Variable” field enter “ComCode” and click continue button or click enter button.
Now click on check box against “Fyscal Year” so it will display following screen:
In the above screen to “Local Variable” field enter “FyscalYear” and click continue button or click enter button
It will display the following screen:
In the above screen click on “Key figures” tab so it will display the following screen:
In the above screen under “Variables” tab, against “key figure scheme” field select your key figure.
Under Available Key Figure box select your Key figure and click on Left arrow button so it will transfer to next box as
below
In the above screen you can view the key figure transfer.
Now click on “Variables” [Link] will display the following screen:
Path: SPRO Controlling Profit Center Accounting Basic Settings Controlling Area Settings Activate Direct
Postings Set Control Parameters for Actual Data
By the above transaction code it will display the following screen click on
In the above screen for your controlling area provide year and flag the check boxes to “Line items, Online Transer”
fields.
Save the activity and back to SPRO screen.
Path: SPRO Controlling Profit Center Accounting Basic Settings Controlling Area Settings Activate Direct
Postings Plan Versions Maintain Plan Versions
In the above screen select version “0” and double click on “Setting for Profit Center Accounting”
Actual Postings
Path: SPROControllingProfit Center AccountingActual PostingsBasic Settings: ActualDefine Number Ranges for
Local Documents
In the above screen click on (Groups) so it will display the following screen:
Go to Manu bar “Group + insert” it will display a box asking Company code:
In the above screen enter your company code and pres enter button.
So it will display the following screen:
In above screen maintain number inter values as I shown save the activity and back to SPRO screen.
Path: SPRO Controlling Profit Center Accounting Actual Postings Choose Additional Balance Sheet and P&L
Accounts Choose Accounts
In the above screen enter you elements range and enter Default Profit center.
Now click on it will display the following screen:
In the above screen click on create button so it will display the following screen:
In the above screen enter all the values as I shown and pres enter button so ti will display the following screen:
In the above screen first go to “Shipping” tab in that assign Storage location as I shown in above and save the activity.
Post: LogisticsSales and Distribution Shipping and Transportation Outbound Delivery Create Single Document
VL01N - With Reference to Sales Order
In the above screen give at least 10 days future date, and give Order number which we got from above step and pres
enter button so it will display the following screen:
In the above screen first click on “Picking” tab and in it under “Picked Qty” field give the quantity of goods how much
you want to pick now(General total quantity that order contain)
Now click on “Post goods issue” button so it will post the data and issue the following message.
In the above screen provide the delivery document number and click on enter button so it willdisplay the following
screen:
In the above document just click on save button so it will save the document and post the entry to FI.
It will display the following screen
In the above screen go to manu bar “Billing document + change” it will display the following screen:
In the above screen click on “Accounting” button so it will display the following window:
1. Accounting Document
2. Sales Documents
3. Profit Center Documents
4. Profitability analysis
In the above screen double click on each line one by one it will display the documents each.
Path: Accounting Financial Accounting General Ledger Posting FB50 - Enter G/L Account Document or F-02 -
General Posting
Enter the above debit values with Cost Center, Profit Center, and Segment.
Path: AccountingControlling Profitability Analysis Actual Postings Period-End ClosingTransfer Cost Center
Costs/Process CostsKEU5 – Assessment
In the above screen give periods (From, To values), Deselect Test Run check box, Assign your cycle to Cycle field and
execute the activity it will display the following screen:
In the above screen keep your curser on Senders value and click on Sender button it will show the values in the same
way keep your curser on Number of receivers value and click on Receiver button it will display the values back to easy
access screen.
In the above screen select those parameters for which you want to drag the report and click on executive button it will
display following:
-------------------------------------------------------******-------------------------------------------------------------------