Standard Rates For Billing of Civil Works
Standard Rates For Billing of Civil Works
Base SOR:- MPPWD SOR, for Building work and Electrical work w.e.f. 01.12.2020 with its amendment up to amendment No.2 and applicable NSOR items.
Rates as per MPPWD SOR for various civil Structures i.e. Structure foundations, Control Room Buildings, Cable trenches, Fencing work etc. as listed below for 400 KV/220
KV/132 KV substations of MPPTCL against the name of structure in column No. 7 are as per Standard Measurement Book (volume-I & volume-II) and in accordance with
the drawings mentioned in the SMB's. The rates mentioned in column No. 7 are excluding cost of excavation, filling, back filling and as mentioned in remark column,
which shall be payble separately as per actual work done on the basis of MPPWD SOR w.e.f. 01.12.2020 and applicable NSOR items.
Reference of SMB Pg
Rate
No.
as per MP PWD SOR
w.e.f. 01.12.2020 for
[Link]. SOR No. Service Master No Particulars of Civil Structure Unit Reamrks
Buildings work &
Electrical works and
applicable NSOR items
Volume-I
1 33 KV Structure Foundations Vol-I/P-1 to 18
(i) 123 NSOR 4000225 33 KV Gantry (1 GO3) Vol-I / P-1 1 No. 36039.80
(ii) 124 NSOR 4000226 33 KV Main Bus (1 BO4) Vol-I / P-3 1 No. 73003.58
(iii) 125 NSOR 4000227 33 KV Auxilary Bus (1BO5) Vol-I/P-5 1 No. 49126.20
(iv) 126 NSOR 4000228 33 KV Isolator (1DO3) Vol-I/P-7 1 No. 10016.73
(v) 127 NSOR 4000229 33 KV CT/PT/LA/PI Vol-I/P-9 1 No. 3786.50
(vi) 128 NSOR 4000230 33 KV CB Vol-I/P-11 1 No. 12693.05
(vii) 129 NSOR 4000231 33 KV, 36 KV/12MVAR Capacitor Bank Vol-I/P-13 1 No. 58293.34
(viii) 130 NSOR 4000232 33 KV NCT Vol-I/P-15 1 No. 3771.79
(ix) 131 NSOR 4000233 33 KV Special PI Vol-I/P-17 1 No. 10173.92
2 132 KV Structure Foundations Vol-I/P-19 to 38
(i) 132 NSOR 4000234 132 KV Main Bus (3B04) Vol-I/P-19 1 No. 37474.44
(ii) 133 NSOR 4000235 132 KV Gantry (3GO2) Vol-I/P-21 1 No. 73659.53
(iii) 134 NSOR 4000236 132 KV Auxilary Bus (3BO3) Vol-I/P-23 1 No. 47746.56
(iv) 135 NSOR 4000237 132 KV PT (3VO4) Vol-I/P-25 1 No. 8363.69
(v) 136 NSOR 4000238 132 KV C.C (3KO2) Vol-I/P-27 1 No. 8063.20
(vi) 137 NSOR 4000239 132 KV Isolator (3DO2) & (3DO5) Vol-I/P-29 1 No. 15592.51
(vii) 138 NSOR 4000240 132 KV PI (3PO2) & 132 KV CT (3 CO5) (For non BC soil) Vol-I/P-31 1 No. 3140.53
--198--
SMB (Gist)
Modified as on 1st Sept 2022
Reference of SMB Pg
Rate
No.
as per MP PWD SOR
w.e.f. 01.12.2020 for
[Link]. SOR No. Service Master No Particulars of Civil Structure Unit Reamrks
Buildings work &
Electrical works and
applicable NSOR items
SMB (Gist)
Modified as on 1st Sept 2022
Reference of SMB Pg
Rate
No.
as per MP PWD SOR
w.e.f. 01.12.2020 for
[Link]. SOR No. Service Master No Particulars of Civil Structure Unit Reamrks
Buildings work &
Electrical works and
applicable NSOR items
(ii) 167 NSOR 4000269 Stage-II-Complete structural work above Plinth Beam Level to Vol-I/P-101 to 110 1 job 1688248.79
slab cast level
(iii) 168 NSOR 4000270 Stage-III-Complete plaster (external and internal ), Sanitary Vol-I/P-118 to 134 1 job 1070295.31 Also excluding external and
fittings (excluding Sewage system), water supply fitting only, internal sanitary and water
Rain water pipe, Grills, Shutters, flooring, doors and windows supply pipe line work
work etc. all complete.
(iv) 169 NSOR 4000271 Stage-IV-Complete Electrification works i/c all Electrical Vol-I/P-135 to 139 1 job 128040.00
Fixtures.
(v) 170 NSOR 4000272 Stage-V-Complete Putty and Painting Vol-I/P-140 to 147 1 job 226895.80
(ii) 172 NSOR 4000274 Stage-II-Complete structural work above Plinth Beam Level to Vol-I/P-166 to 178 1 job 2334962.98
slab cast level
(iii) 173 NSOR 4000275 Stage-III-Complete plaster (external and internal ), Sanitary Vol-I/P-191 to 212 1 job 1575505.33
fittings (excluding Sewage system), water supply fitting only, Also excluding external and
Rain water pipe, Grills, Shutters, flooring, doors and windows internal sanitary and water
work etc. all complete. supply pipe line work
(iv) 174 NSOR 4000276 Stage-IV-Complete Electrification works i/c all Electrical Vol-I/P-213 to 217 1 job 178438.00
Fixtures.
(v) 175 NSOR 4000277 Stage-V-Complete Putty and Painting Vol-I/P-218 to 230 1 job 314911.45
--200--
SMB (Gist)
Modified as on 1st Sept 2022
Reference of SMB Pg
Rate
No.
as per MP PWD SOR
w.e.f. 01.12.2020 for
[Link]. SOR No. Service Master No Particulars of Civil Structure Unit Reamrks
Buildings work &
Electrical works and
applicable NSOR items
(ii) 177 NSOR 4000279 Stage -II (Part-A)- Complete structural and masonary work Vol-I/P-255 to 269 1 job 3313130.91
above Plinth Beam Level to slab cast level (Ground Floor).
(iii) 178 NSOR 4000280 Stage -II (Part-B) Complete structural and masonary work above Vol-I/P-287 to 294 1 job 3352504.49
ground floor slab to first floor slab level. Also excluding external and
internal sanitary and water
(iv) 179 NSOR 4000281 Stage-III-Complete plaster (external and internal ), Sanitary Vol-I/P-306 to 331 1 job 4058821.69 supply pipe line work
fittings (excluding Sewage system), water supply fitting only,
Rain water pipe, Grills, Shutters, flooring, doors and windows
work etc. all complete.
(iv) 180 NSOR 4000282 Stage-IV-Complete Electrification works i/c all Electrical Vol-I/P-333 to 337 1 job 491662.00
Fixtures.
(v) 181 NSOR 4000283 Stage-V-Complete Putty and Painting Vol-I/P-338 to 355 1 job 835932.84
Grand Total of 400 KV Control Room Building S-Type 13225425.79
8 Transformer Foundation Vol-I/P-356 to 374
(i) 182 NSOR 4000284 33 KV Station Transformer Vol-I/P-356 1No 12227.39
(ii) 183 NSOR 4000285 132/33 KV 40/50 MVA X-Mer Foundation excluding Anciliary Vol-I/P-358 1No 125127.87
Except ancillary
Foundation but incluiding Jacking Pad
foundations
(iii) 184 NSOR 4000286 132/33 KV 40/63MVA X-Mer foundation excluding Ancilary Vol-I/P-361 to 362 1No 104761.83
foundation but including Jacking Pad
--201--
SMB (Gist)
Modified as on 1st Sept 2022
Reference of SMB Pg
Rate
No.
as per MP PWD SOR
w.e.f. 01.12.2020 for
[Link]. SOR No. Service Master No Particulars of Civil Structure Unit Reamrks
Buildings work &
Electrical works and
applicable NSOR items
Volume -II
1 Cable Trench
(i) Brick Masnory Cable trench Vol-II/P-1 to 17
189 NSOR 4000291 A Type Vol-II/P-1 to 3 M 7497.87
190 NSOR 4000292 B Type Vol-II/P-4 to 6 M 5219.60
191 NSOR 4000293 C Type Vol-II/P-7 to 9 M 4239.73
Also excluding Top Slab
192 NSOR 4000294 D Type Vol-II/P-10 to 11 M 2493.21
and corners
193 NSOR 4000295 E Type Vol-II/P-12 to 13 M 1778.60
194 NSOR 4000296 F Type Vol-II/P-14 to 15 M 1357.19
195 NSOR 4000297 G Type Vol-II/P-16 to 17 M 2117.30
(ii) RCC Cable Trench Vol-II/P-18 to 40
196 NSOR 4000298 A Type Vol-II/P-18 to 21 M 7484.20
197 NSOR 4000299 B Type Vol-II/P-22 to 25 M 5674.43
198 NSOR 4000300 C Type Vol-II/P-26 to 28 M 4425.36
Also excluding Top Slab
199 NSOR 4000301 D Type Vol-II/P-29 to 31 M 3236.07
and corners
200 NSOR 4000302 E Type Vol-II/P-32 to 34 M 2329.10
201 NSOR 4000303 F Type Vol-II/P-35 to 37 M 1730.53
202 NSOR 4000304 G Type Vol-II/P-38 to 40 M 2775.17
--202--
SMB (Gist)
Modified as on 1st Sept 2022
Reference of SMB Pg
Rate
No.
as per MP PWD SOR
w.e.f. 01.12.2020 for
[Link]. SOR No. Service Master No Particulars of Civil Structure Unit Reamrks
Buildings work &
Electrical works and
applicable NSOR items
SMB (Gist)
Modified as on 1st Sept 2022
Reference of SMB Pg
Rate
No.
as per MP PWD SOR
w.e.f. 01.12.2020 for
[Link]. SOR No. Service Master No Particulars of Civil Structure Unit Reamrks
Buildings work &
Electrical works and
applicable NSOR items
(v) 233 NSOR 4000334 Stage -V Complete Electrification work i/c All Electrical Fixtures Vol-II/P-176 to 178 per job 72995.50
(v) 238 NSOR 3011144 Stage -V Complete Electrification work i/c All Electrical Fixtures Vol-II/P-195 to 197 per job 47403.50
SMB (Gist)