Dropped Object Protection Standards
Dropped Object Protection Standards
Summary
Performance
SECE System Standard Revision Revision Date Page
1
SECE Number: M1 SECE: - Dropped Object Protection Revision: Draft Rev B2 Date: 01/10/2013
Goal:
Prevent any significant loss of hydrocarbon containment or major structural failure following a dropped object or swinging load event.
Scope / Equipment
Scope
Scope
The following is included within the dropped object protection scope:
Impact decks.
Swinging load protection.
Dropped object protection to subsea architecture pipelines and risers.
Limit switches / locking keys to prevent lifting over hydrocarbon containing equipment / pipework.
Excluded from Scope
Dropped loads during well operations and COMOPS.
Notes
2
Principal Interacting SECEs
P1 Structural Integrity
C5 Riser ESDVs
M1.4_F1 Impact decks are Provide The elements making up the Provide references Results of periodic topside Provide references
capable of absorbing references to the: dropped object protection have to the: structural inspection and to the:
the impact energies been designed and constructed dropped object incidents are
Asset plot Asset plot Relevant work
identified in Table 1. to withstand the accidental reviewed by the relevant
plans. plans. instructions.
loads identified by the dropped Technical Authority.
NOTE Topside Topside The electronic
object assessment.
dropped Dropped object Engineering critical assessment (or other)
Protection is provided
object risk The data sheets for elements risk are carried out where required. system used to
commensurate with
assessment. making up the dropped object assessment. schedule
the risk of dropped The potential impacts changes
Relevant protection have been reviewed. Asset safety inspection and
objects from the asset to lifting operations /
performance The review has confirmed that philosophy. maintenance.
and the consequence modifications to the platform
standards the structure is capable of TOTAL’s Change control
of damage to the decks are assessed in
(See meeting functional assessment of procedure.
accordance with the local
3
M1 SECE Sub System: Dropped Object Protection
4
M1 SECE Sub System: Dropped Object Protection
M1.4_F2 Swinging load Provide See M1.4.1 See M1.4.1 Results of periodic topside See M1.4.1
protection e.g. bumper references to the: structural inspection and
bars are capable of swinging load incidents are
Asset plot
absorbing the impact reviewed by the Technical
plans.
energies identified in Authority.
Topside
Table 1
dropped Engineering critical assessment
NOTE object are carried out where required.
assessment.
Protection is provided The potential impacts changes
commensurate with Relevant to lifting operations /
performance
the risk of swinging modifications to swinging load
standards
load from the asset protection are assessed in
(See
and the consequence accordance with the local
interactions
of damage to the change control procedure.
above).
impacted object.
NOTE
Swinging load protection e.g.
bumper bars are inspected at
intervals specified in the
maintenance management
system. Inspection frequency
should be consistent with the
Structural Inspection Strategy.
Sufficient baseline data are
available to permit an
assessment of the continuing
integrity of dropped object
protection following discovery
of any anomaly or any
5
M1 SECE Sub System: Dropped Object Protection
M1.4_F3 Protection on subsea Provide Dropped object protection on Provide references Results of periodic subsea Provide references
pipelines, risers and references to the: subsea pipelines / risers and to the: structural inspection and to the:
architecture are architecture has been defined dropped object incidents are
Subsea Subsea Relevant work
capable of absorbing by means of appropriate reviewed by the Technical
layouts. layouts. instructions.
the impact energies dropped object studies. Authority.
Subsea Subsea CMMS /
identified in Table 1
dropped The elements making up the dropped object Engineering critical assessment Maintenance
NOTE object risk subsea structure dropped risk are carried out where required. management
assessment. object protection have been assessment. system
Protection is provided The potential impacts changes
Pipeline designed and constructed to Topside Change control
commensurate with to lifting operations /
MAPD withstand the accidental loads dropped object procedure.
the risk of dropped modifications to subsea
(where identified by the subsea risk Maintenance
objects from the asset dropped object protection are
applicable). dropped object risk analysis. assessment. management
and the consequence assessed in accordance with the
of damage to the The data sheets and other Pipeline local change control procedure. procedure.
pipeline / riser / subsea relevant detail design MAPD. Area Inspection
NOTE Manual:
architecture. . documentation for the
elements making up the subsea Subsea dropped object Asset Integrity
dropped load protection has protection e.g. mattresses and Strategy
been reviewed. The review has protection frames are Inspection
confirmed that elements are inspected at intervals specified Strategy
capable of meeting functional in the maintenance Structural
requirements. management system. Inspection
Inspection frequency should be Database
Vendors used to procure Inspection
consistent with the Structural
structural elements are on the Anomaly
Inspection Strategy.
approved vendor list. Management
Sufficient baseline data are Procedure.
Review of the selected
available to permit an
6
M1 SECE Sub System: Dropped Object Protection
7
M1 SECE Sub System: Dropped Object Protection
8
M1 SECE Sub System: Dropped Object Protection
M1_V1 Review any changes made to the asset which may M1 - All
effect the assets provision for dropped object
protection since the last operational verification
visit.
M1_V2 Confirm that all standard work text instructions have M1 - All
scheduled within the maintenance management
system have been completed as scheduled.
9
Table 1 – [HOLD FACILITY] Dropped Object Protection Requirements
e.g. Topside dropped load e.g. Platform Weather deck. [HOLD REFER TO DROPPED [HOLD REFER TO DROPPED
protection OBJECT RISK ASSESSMENTS] OBJECT RISK ASSESSMENTS]
e.g. Topside dropped load e.g. Platform Weather deck. [HOLD REFER TO DROPPED [HOLD REFER TO DROPPED
protection OBJECT RISK ASSESSMENTS] OBJECT RISK ASSESSMENTS]
e.g. Topside swinging load e.g. Swinging object protection frame for the exhaust stack. e.g. 18kJ e.g. 6.0te swinging load - 10°,
protection 20m rope length
[HOLD REFER TO DROPPED
OBJECT RISK ASSESSMENTS] [HOLD REFER TO DROPPED
OBJECT RISK ASSESSMENTS]
e.g. Topside swinging load e.g. Tote tank area central vertical bumper barrier e.g. 27kJ e.g. (6.0te swinging load - 10°,
protection 30m rope length)
[HOLD REFER TO DROPPED
OBJECT RISK ASSESSMENTS] [HOLD REFER TO DROPPED
OBJECT RISK ASSESSMENTS]
e.g. Subsea pipeline e.g. PL XXX 36-inch export pipeline – Concrete mattresses [HOLD REFER TO DROPPED [HOLD REFER TO DROPPED
protection protecting the pipeline in the vicinity of the platform Xm to SSIV. OBJECT RISK ASSESSMENTS] OBJECT RISK ASSESSMENTS]
e.g. Subsea architecture e.g. Protection frame covering SSIV XXX [HOLD REFER TO DROPPED [HOLD REFER TO DROPPED
protection OBJECT RISK ASSESSMENTS] OBJECT RISK ASSESSMENTS]
HOLD – INSERT RELEVANT HOLD – INSERT RELEVANT INFORMATION HOLD – INSERT RELEVANT HOLD – INSERT RELEVANT
INFORMATION INFORMATION INFORMATION
10
SECE Number: M2 SECE:- Blast Resistant Construction Revision: Draft Rev B2 Date: 01/10/2013
Goal:
To reduce the consequences of design case blast overpressures upon sensitive receptors (including people, plant and equipment).
Scope / Equipment
Scope
The scope of the above SECE includes doors and other penetrations within the blast wall.
Notes
P1 Structural Integrity
11
SECE Sub Number: M2.1 SECE Sub System: Blast Walls and their associated penetrations.
M2.1_F1 Blast Walls, including Provide reference Reasonably foreseeable Provide reference Operational assurance is Provide reference
doors and other to: explosions and sensitive to: provided by routine to:
penetrations through receptors are recorded in the inspections, carried out in
them are designed and Table 1. asset fire and explosion risk Table 1. GS EP EXP
accordance with relevant work
constructed to analysis (FERA). Asset FERA. 311 Plant
instruction at frequencies
withstand design Structural / Integrity
Asset explosion models scheduled in as scheduled in
explosion other response Minimum
determine the blast the asset maintenance
overpressures. to blast Inspection
overpressures arising from management system.
analysis. Requirement
Table 1 of this reasonably foreseeable
Changes to the system are in s
performance standard explosions.
accordance with the Total GSP EP EXP
summarises each of The structural design change control procedure. 213
the blast walls and philosophy considers the
their design reasonably foreseeable Minimum
overpressures. explosion pressures detailed Maintenance
within the FERA and includes Requirement
strategies for their mitigation. s
Asset
Blast resistant construction Inspection
Basis Of Design detail the and
specification of the structures Maintenance
with respect to over pressure. Management
Drawings of the blast System
structures provide Total Change
confirmation that the Control
structures are as per required Procedure.
by the BOD.
12
Availability References Means of Assurance References Means of Assurance References
Design Operational
M2.1_S1 Blast Walls and M3. Not applicable. Not applicable. Not applicable. Not applicable.
penetrations to retain
their fire rating
following the
realisation of the
design case explosion.
13
Table 1 – Register of Asset Blast Resistant Constructions
Blast Resistant Construction Design Overpressure Basis Provide References to Source Drawing References
& Location Analysis and Construction
Specifications
Provide details such as type of Summarise the design basis. List all source references and Detail all relevant drawings.
construction and its location and specifications.
what it is installed to protect.
Provide details such as type of Summarise the design basis. List all source references and Detail all relevant drawings.
construction and its location and specifications.
what it is installed to protect.
14
OPERATIONAL VERIFICATION VSEL 3
15
SECE Number: M3 SECE:- Fire Mitigation Revision: Draft Rev B2 Date: 01/10/2013
Goal:
To prevent premature failure of safety critical components and to contain the spread of smoke or fire for a predetermined period of time.
Scope / Equipment
Scope
Fire and blast rated barriers /enclosures, Passive Fire Protection (PFP) coatings.
Scope includes all blast rated walls, fire rated walls, self-closing doors, floors, roofs, partitions, galley shutters etc. including machinery
enclosures, PFP applied to structures, walls, vessel/piping and/or their supports, risers/pipelines, ESDV/SDVs.
Penetrations in fire or blast rated barriers e.g. doors, windows, cables, pipes and seals are also part of the PS scope.
PFP coating may be pre-fabricated panels, boxes, shells, fibre blankets, epoxy (normally intumeSECEnt) or cementitious. GRE/GRP, silicones
and gums may also have been used.
Structures, vessels or other equipment deemed to have sufficient inherent fire protection e.g. reinforced concrete and have not been given a
specific fire rating are outwit the scope of this PS.
Notes
16
E1 Alarm and PA System
M4 Temporary Refuge
P1 Structural Integrity
SECE Sub-System Number: C11.1 SECE Sub-System: Passive Fire Protection (PFP)
M3.1_F1 PFP applied to BDV and Provide reference External fire events are defined Provide references Operational assurance is Provide reference
ESDV protect the to: within the asset fire and to the: provided by routine to:
valves from external explosion risk assessment. inspections, carried out in
thermal flux such that GS EP SAF Asset basis of GS EP EXP
The asset PFP philosophy accordance with relevant work
continued valve 337 design 311 Plant
describes which vulnerable instruction at frequencies
operation is possible Passive Fire document. Integrity
receptors require PFP. scheduled in as scheduled in
for the time periods Protection: Asset PFP Minimum
The BDV and ESDV P&IDs have the asset maintenance
defined in Table 1. Basis of assessment. Inspection
been reviewed. The review management system.
Design. Relevant P&IDs Requirement
Note: Endurance confirms that the PFP has been Changes to the system are in
Table 1 of indicating PFP s
times need to be this specified correctly (as indicated clad valves. accordance with the Total GSP EP EXP
consistent with the Performance by the P&ID legend). Asset PFP change control procedure. 213
QRA and fire and Standard. protection Minimum
explosion risk philosophy. Maintenanc
analysis. e
Requirement
17
SECE Sub-System Number: C11.1 SECE Sub-System: Passive Fire Protection (PFP)
s
Asset
Inspection
and
Maintenanc
e
Managemen
t System
Total
Change
Control
Procedure.
M3.1_F2 PFP are applied to See M3.1_F1 The ducting basis of design Provide references See M3.1_F1 See M3.1_F1
ducting fire louvers specifies that fire compartment to the:
and firewall penetrations are to be
penetrations. maintained by provision of fire Ducting Basis
louvers to a specification of at of Design.
Installed PFP, as
least the fire compartment Ducting
summarised in Table 1,
through which it is being drawings.
will meet or exceed
penetrated. Fire
the rating of the
compartment
penetrated fire Each duct passing through a fire
drawings.
compartment. compartment wall has been
identified on the ducting layout
drawings.
Each fire louver and
penetration drawing has been
reviewed to confirm that the
18
SECE Sub-System Number: C11.1 SECE Sub-System: Passive Fire Protection (PFP)
M3.1_F4 PFP will be resistant to: See M3.1_F1 The PFP data sheets provide Provide references See M3.1_F1 See M3.1_F1
The chemicals/ information regarding their to the:
environment into suitability for chemical
exposures and environmental PFP data sheet
which it is being
conditions. references.
applied.
PFP
The reasonably A PFP assessment has been
assessment.
foreseeable performed which examined the
potential thermal location of the PFP and the
shock loads (ie likely environmental conditions
from deluge/ and chemical exposures.
water cannon). The PFP drawings have been
Damage caused reviewed against the PFP
vibration/ report. The review confirmed
movement etc of that the PFP has been correctly
the substrate to specified on the drawings.
which it is applied.
19
Availability References Means of Assurance Design References Means of Assurance References
Operational
M3.1_A1 PFP unavailable for See M3.1 See M3.1 See M3.1 See M3.1 Provide
more than a single shift references to the:
are subject to a
Risk
document risk
assessment
assessment, otherwise
procedure.
M3.1 functionality are
available for at least
95% of the time (Hold:
Revise this statement
to be consistent with
the QRA).
M3.1_S1 PFP will survive the Not applicable. - - See M3.1_F1 See M3.1_F1
design fire scenarios
for the time specified
in the standard to
which the PFP is
installed.
M3.1_S1 PFP will be rated to at GS EP SAF 337. See M3.1_F4 See M3.1_F4 See M3.1_F4 See M3.1_F4
least the same blast
resistance as the
surface/structure it is
applied to.
20
Table 1 – Installed PFP Design Criteria
Receptor Being Protected Duration the Protected PFP Specification Relevant Drawings Fire / Other Risk
Valve Must Remain Assessment That Defines
Functional (min) the Design Fire Scenario
Hold: State valve/ wall/ structure etc Hold: Provide information Hold: Specify the PFP rating ie Hold: List relevant drawings Hold: Provide a reference to
that is being protected. where for PFP protected A60/J30 etc. showing the applied PFP. the source fire risk
valves. Enter ‘ Not assessment that identifies
Applicable’ if the receptor the fire hazard.
being protected is not a
valve.
Hold: State valve/ wall/ structure etc Hold: Provide information Hold: Specify the PFP rating ie Hold: List relevant drawings Hold: Provide a reference to
that is being protected. where for PFP protected A60/J30 etc. showing the applied PFP. the source fire risk
valves. Enter ‘ Not assessment that identifies
Applicable’ if the receptor the fire hazard.
being protected is not a
valve.
Hold: State valve/ wall/ structure etc Hold: Provide information Hold: Specify the PFP rating ie Hold: List relevant drawings Hold: Provide a reference to
that is being protected. where for PFP protected A60/J30 etc. showing the applied PFP. the source fire risk
valves. Enter ‘ Not assessment that identifies
Applicable’ if the receptor the fire hazard.
being protected is not a
valve.
21
OPERATIONAL VERIFICATION VSEL 3
M3_V1 - - Review any changes made to the PFP or to plant that M3_F1
may affect the deployment of PFP since the last
operational verification visit.
Confirm that the modifications have been subjected
to the relevant change management system and that
any actions arising have been satisfactorily closed
out.
22
SECE Number: M4 SECE System: Temporary Refuge Revision: Livermore Rev Date: 30/05/2013
B1.
Goal:
Provide safe refuge for personnel on the asset for as long as required for a controlled evacuation to be carried out and to ensure easy, fast and safe access to means of
evacuation.
Scope / Equipment
Notes
Note 1
Temporary Refuge is a term applicable to offshore facilities and infers a level of protection is provided for individuals against the effects of Major Accident Hazards (MAH)
(smoke, heat radiation, blast, toxic gases) for a necessary endurance period. The term ‘Muster Point’ covers a wider scope that could include one or more of the following
examples: the main muster area onshore; the main muster area inside a TR; the main muster area offshore where no designated TR is provided e.g. unmanned installation,
the secondary muster area and the life boat embarkation area etc. Certain muster areas may also have protective features such as a fire/blast wall.
Note 2
The Temporary Refuge (TR) is a Safety Critical system made up of a number of individual SECEs. As a result of this, performance requirements for the TR systems can be
found in their individual Performance Standards rather than within this document. Where applicable, these interactions have been highlighted in the interacting SECE
23
below so that a cross reference to relevant performance standards can be made.
Note 3
The PS for the TR will be very installation specific. Please refer to CR SAF 351 for further details.
Maintained Power Supplies - Required to supply essential systems necessary for the emergency response plan to be executed during a Major
E9
Accident.
M3 Fire Mitigation - Maintain the integrity of the TR and muster areas against identified fire scenarios.
M2 Blast Resistant Construction – Maintain the integrity of the TR and muster areas against reasonably foreseeable over pressure.
P11 HVAC Systems - To prevent the ingress or build-up, of flammable gas-air mixtures or life threatening atmosphere in/into the TR.
E5 Internal Communication - Required for communication with personnel onboard to escape and muster.
E6 External Communications – Required for communicating with external parties for evacuation.
E3 Emergency Lighting - A minimum level of illumination is required to enable escape, muster and evacuation during a Major Accident.
M7 Firewater Systems - Required to rapidly reduce the production of heat and smoke from a fire in the TR.
E1 Alarm and PA System – Required to alert personnel of the requirement to abandon asset.
E2 Egress and Access Routes - Required during a Major Accident to enable personnel to escape to muster in the TR, or to leave the TR to a
proceed to a location for evacuation.
24
SECE Sub System:
25
SECE Sub System:
are constructed to a
leakage standard of
0.25 ac/hr. The actual
numerical value is not
critical and should not
be considered in
isolation. More
technical advice on this
issue can be found in
ISO 15138 and
Operations Notice 27.
Provide sufficient space at muster areas to allow the muster of [HOLD – Insert POB of asset as stated in Safety Case / COMAH Safety Report] and ensure easy, fast and safe
entering of the evacuation systems in question
M4.1_ F2 The total surface of all Provide reference Asset EER philosophy outlines Provide reference See M4.1_ F1 See M4.1_ F1
muster (embarkation) to: the minimum space to:
areas is not less than N requirements for all asset
GS EP SAF 351. EER
x 0.35 m2, and muster areas.
Philosophy.
adequate access to EERA.
A review of relevant EERA.
evacuation systems is
documentation and functional Relevant asset
provided.
specifications has been functional
Note - N being the undertaken to confirm that the specifications
maximum number of room for mustering to be and
persons likely to be at provided for both normal documentation
the same time on the operational periods and Escape and
installation. Additional maintenance periods (if there is evacuation
space for stretcher increased manning) is drawings.
26
SECE Sub System:
M4.1_ A1 The TR and muster - TR and muster area reliability / Provide reference Ongoing suitability is addressed Provide reference
areas are available at availability is assured through to: within the scope of the risk to:
all times the platform adherence to standards and assessment in support of the
Total Change Total Change
is manned. procedures, regular inspections Safety Case / COMAH Report
Control Control
and reporting, monitoring and and updates of supporting
Procedure. Procedure –
completion of corrective work studies.
Asset ISSOW Asset safety
orders (as per priority
procedure. Changes to the system are in case / COMAH
assignment).
accordance with the Total Report.
Temporary / permanent change control procedure. Relevant
changes to the system are in supporting
accordance with the Total safety studies
change control procedure and e.g. EERA, FEA,
Integrated Safe System Of Work QRA.
27
Availability / References Means of Assurance Design References Means of Assurance References
Reliability Operational
(ISSOW).
M4.1_ S1 The TR continue to Provide reference Various formal safety studies Provide reference Ongoing suitability is addressed Provide reference
perform is function to: have been undertaken to assess to: within the scope of the risk to:
where subjected to all TR and muster area exposure to assessment in support of the
Facility Relevant Change
reasonably foreseeable MAHs. Recommendations from Safety Case and updates of
safety safety studies Control
MAHs e.g. loss of these studies have been supporting studies.
philosophy. e.g. Procedures
containment, and incorporated into the design
EERA. Dropped object Changes to the system are in Facility safety
environmental events where appropriate. The
EER assessments. accordance with the Total case / COMAH.
for a period of [HOLD] primary means of limiting TR
Philosophy. Fire and change control procedure. Relevant
minutes. and muster area exposure to
TR functional explosion supporting
MAHs has been through
Note - Temporary specification. assessment safety studies
location rather than protection.
refuges are designed (FEA).
and protected for the Continual review of platform Quantified Risk
period of time required layout and facility drawings in Assessment
to ensure safe muster, relation to TR location has been (QRA).
search and rescue undertaken during project TR impairment
operations (if defined design stages e.g. FEED, Detail analysis
in EER analysis), design etc. EERA.
embarkation and Facility safety
Note - As stated in Note 2, The
abandonment of the philosophy.
Temporary Refuge (TR) is a
installation during a Facility layout
Safety Critical system made up
dimensioning review.
of various individual SECEs.
accidental event.
Many of these interacting
SECEs are required to fulfil a
28
Survivability References Means of Assurance Design References Means of Assurance References
Operational
The probability that Provide reference Various formal safety studies Provide reference Ongoing suitability is addressed Provide reference
the TR will be to: have been undertaken to assess to: within the scope of the risk to:
prevented from TR and muster area exposure to assessment in support of the
Asset TR Total Change
performing its function MAHs. Recommendations from Safety Case and updates of
impairment Control
due to the occurrence these studies have been supporting studies.
analysis. Procedure –
of other reasonably incorporated into the design of
Asset QRA. Changes to the system are in Asset safety
foreseeable events are the asset and TR where
Asset ALARP accordance with the Total case / Report.
no greater than 1x10-3 appropriate.
demonstration. change control procedure. Relevant
The asset TR Impairment supporting
analysis has shown the risk of safety studies
TR impairment as being ALARP. e.g. EERA, FEA,
The TRIF calculated in the QRA, TR
analysis is HOLD per year. This impairment
is in agreement with TRIF analysis.
calculated in asset QRA of
HOLD.
Note – The following is
provided for guidance only.
Sufficient evidence is required
to demonstrate that the
frequency with which
accidental events will result in a
29
Survivability References Means of Assurance Design References Means of Assurance References
Operational
M4_V1 Review any changes made to the asset which affect M4 - All
the TR since the last operational verification visit.
M4_V3 Confirm that all standard work text instructions have M4 - All
scheduled within the maintenance management
system have been completed as scheduled.
30
OPERATIONAL VERIFICATION VSEL 3
31
OPERATIONAL VERIFICATION VSEL 3
32
SECE Number: M5 SECE Lifeboats: - Fire pumps Revision: Draft Rev B2 Date: 01/10/2013
Goal:
Upon manual or automatic demand, to deliver suitable quality firewater at the required flow, pressure and duration into the firewater ring main.
Scope / Equipment
Scope
Fire water pumps i.e. Main fire water pumps, fire water supply pumps feeding the main fire water pumps (if provided and critical to meet the
goal ) e.g. sea water lift pumps, fuel supplies, surge protection, instrumentation and control. There are (State numbers of pumps> x <Enter
configuration type e.g.50%, 100%, etc) fire pumps, (Indicate their location on the Facility).
Notes
33
C4 Emergency Shutdown Systems
M6 Firewater Main
M7 Firewater Systems
By automatic or manual activation, the system is able provide sufficient firewater of appropriate quality into the ring main to adequately service firewater user points.
M5.1_F1 The firewater pumps Provide reference Reasonably foreseeable fires Provide reference Operational assurance is Provide reference
will provide to: have been identified and are to: provided by routine inspection to:
firewater at Hold detailed within the asset fire and function checks, carried
GS EP GS EP SAF 322 GS EP EXP 311
barg pressure at and explosion risk out in accordance with relevant
SAF321 – Fire – Fixed Fire Plant Integrity
Hold m3/hr into the assessment. work instruction at frequencies
Pump Water Minimum
firewater ring main scheduled in as scheduled in
Stations and The asset fire and gas Systems.
the asset maintenance Inspection
for at least Hold Fire Water protection philosophy Asset fire and Requirements
management system.
hours. Mains. defines how firewater is to explosion risk GSP EP EXP 213
assessment. Changes to the system are in
Note: The stated (Additional be used to mitigate the Minimum
Asset fire and accordance with the Total Maintenance
duration is to facilitate references are reasonably foreseeable fires
gas protection change control procedure. Requirements
safe, mustering and provided within defined within the fire and
philosophy. Asset Inspection
evacuation of the General explosion risk assessment.
Specification). Fire pump data and
personnel.
The philosophy defines the sheets. Maintenance
The safety critical required deluge/ spray and Asset active Management
duration does not duration requirements for firewater System
relate to asset the worst case simultaneous protection Total Change
protection 3/6 hours layout
fire zone deluge activation Control
as defined within GS
34
SECE Sub System:
35
SECE Sub System:
M5.1_F3 The firewater Provide reference The firewater source/s are Provide reference See M5.1_F1. See M5.1_F1.
provided by the fire to: defined within the asset fire to:
water pumps will be and gas protection
GS EP Asset fire and
of a quality so as not philosophy.
SAF321 – Fire gas
to be detrimental to Pump Where relevant, the protection
the efficiency of Stations and required specification of philosophy.
firewater users. Fire Water firewater for user points is Firewater
Mains detailed within the firewater user data
further references user datasheets.
36
SECE Sub System:
37
SECE Sub System:
availability.
The status of the firewater pumps is made visible to personnel in diverse asset locations.
M5.1_F4 The status of the Provide reference The locations at which Provide reference See M5.1_F1. See M5.1_F1.
criteria defined to: M5.1_F1 functionality to:
within M5.1_F1 is criteria are to be displayed is
GS EP Asset fire
made visible to SAF321 – Fire defined within the asset fire
pumps
personnel in Hold: Pump and gas protection
human
List the locations. Stations and philosophy.
machine
Fire Water The locations of the interface
Mains. firewater human machine basis of
(Further interfaces are defined within design.
references are the firewater user
provided within requirement specification.
the General
The specification has been
Specification).
reviewed confirming that
M5.1_F4 functionality is fully
enacted.
The operation of the firewater pumps does not give rise to surge, vacuum or water hammer pressures that may adversely affect the functionality and/or availability of the
fire ring main.
M5.1_F5 A surge valve/ pump Provide reference The surge, vacuum and Provide reference Maintenance and See M5.1_F1.
soft start/ to: water hammer pressures to: functionality checks of the
associated with the protective systems are
accumulator system GS EP Documents
operation of the fire pumps performed at intervals
(Hold delete/add as SAF321 – that describe
38
SECE Sub System:
appropriate) has Fire Pump have been calculated and the MAH scheduled in Hold: Define the
been installed to Stations reported. events. relevant maintenance
and Fire The surge/vacuum/ water Surge, vacuum management system.
mitigate the adverse
Water hammer protective system and water Any deficiencies found
effects of fire pump
Mains basis of design has been hammer during the above likely to
operation. reviewed. The review analysis affect the functionality,
Further
confirmed that pump surge, report. availability or survivability of
references are
vacuum and water hammer Specification/ the surge protection system
provided within
pressures will not affect the Data sheet for is treated as a downgraded
the General
functionality and/or the surge situation and managed
Specification.
availability of the fire ring protection accordingly.
main. system or
systems.
The firewater pump enclosures are constructed so as to enable the fire pumps to function for duration at least equal to that defined within M5.1_F1 during reasonably
foreseeable fires and explosions (external to the enclosures).
M5.2_F1 The firewater pump - Reasonably foreseeable fires Provide reference Operational assurance is Provide reference
enclosures are H/J60 and explosions are defined to: provided by routine to:
Hold: Revise to within the fire and explosion inspections, carried out in
Asset fire and accordance with relevant work GS EP EXP 311
enable the fire risk analysis.
explosion instruction at frequencies Plant Integrity
pumps to function The firewater pumps analysis. scheduled in as scheduled in Minimum
for duration at least enclosures are designed to Data sheets for the asset maintenance Inspection
equal to that defined protect the pumps from Requirements
PFP applied to management system.
within M5.1_F1 reasonably foreseeable fires GSP EP EXP 213
the enclosures. Changes to the system are in
during reasonably and explosions allowing Minimum
Specification/ accordance with the Total
foreseeable fires and Maintenance
39
SECE Sub System:
explosions (external their functionality to be data sheets for change control procedure. Requirements
to the enclosures). sustained for a duration the fire pump Asset Inspection
defined within M5.1_F1. enclosures wrt and
The data sheet/s for the fire explosion Maintenance
Management
pump enclosures have been overpressure
System
reviewed with respect to the design.
Total Change
protection they provide Control
against the reasonably Procedure.
foreseeable fires and
explosions detailed within
the asset fire and explosion
risk assessment.
The review confirmed that
the fire pumps will continue
to function for the duration
defined within M5.1_F1
resulting from reasonably
foreseeable fire and
explosions.
A sufficient quantity of diesel fuel oil is stored and made available to the firewater pump diesel engines to enable the pumps to run for a period of time defined within
M5.1_F1.
M5.3_F1 Hold m3 of diesel - The required diesel fuel oil Provide reference Operational assurance is Provide reference
fuel oil is stored and consumed by the fire pump to: provided by routine inspection to:
made available to engines to meet and function checks, carried
Asset fire and out in accordance with relevant GS EP EXP 311
the firewater pump functionality M5.1_A1 has
40
SECE Sub System:
diesel engines. been calculated. gas protection work instruction at frequencies Plant Integrity
The diesel fire pump engine philosophy. scheduled in as scheduled in Minimum
and associated diesel tank/s Diesel fire the asset maintenance Inspection
data sheets have been management system. Requirements
pump engine
GSP EP EXP 213
reviewed. data sheet. Changes to the system must be
Minimum
The review confirmed that Diesel fuel oil in accordance with the Total
Maintenance
capacity change control procedure.
The installed diesel fuel oil Requirements
tank is 120% (Hold: Change calculations. Asset Inspection
as necessary) of the required Fire pump and
capacity to meet M5.1_A1 diesel supply Maintenance
(based upon full diesel data sheet/s. Management
engine load conditions). System
Total Change
Control
Procedure.
M5.3_F2 Trace heating has - The environmental basis of Provide reference See M5.3_F1. See M5.3_F1.
been applied to the design conditions have been to:
diesel fuel oil system reviewed and compared to
Diesel
to maintain the the diesel waxing
supplier’s data
temperature of temperature. This review
sheet.
diesel above its wax has shown that diesel
Environmental
formation waxing is credible. Hold:
basis of design.
temperature of Hold Delete this row if waxing is
Drawings
Deg C. not reasonably foreseeable.
P&IDs
41
SECE Sub System:
M5.1_A1 Unless subject to a Provide reference The availability has been Provide reference See M5.1_F1. See M5.1_F1.
risk assessment the to: assured by provision of n to:
functionality defined (Hold – insert number)
Asset QRA. GS EP SAF
in M5.1 is available independent firewater
321 Fire
at all times that a pumps where failure of one
Pump
reasonably of the pumps will not
Stations and
foreseeable demand prevent the functionality
Fire Water
may be placed upon defined within M5.1_F1.
Mains.
the firewater pumps. Each firewater pump has Asset fire and
42
Availability / References Means of Assurance Design References Means of Assurance References
Reliability Operational
43
Availability / References Means of Assurance Design References Means of Assurance References
Reliability Operational
M5.3_A1 The availability of an - The P&IDs of the diesel fuel Provide reference See M5.3_F1. See M5.3_F1.
individual diesel fuel oil supply lines have been to:
oil storage vessel reviewed. The review of
PFDs/ P&IDs
44
Availability / References Means of Assurance Design References Means of Assurance References
Reliability Operational
M5.1_S1 The functionality - The fire pumps are located in M5.2 See M5.2. See M5.2.
defined above will be a safe position and/or
capable of surviving housed within enclosures
reasonably designed to protect them
foreseeable MAH from reasonably foreseeable
events for a period hazards for a duration at
of time at least equal least equal to that defined
to that defined within M5.1_A1. Hold: Revise
within M5.1_A1. this statement to reflect the fire
and asset fire and gas
protection philosophy.
45
Survivability References Means of Assurance Design References Means of Assurance References
Operational
46
OPERATIONAL VERIFICATION VSEL 3
47
OPERATIONAL VERIFICATION VSEL 3
48
SECE Number: M6 Firewater Ring Main & Supports Revision: Draft Rev B2 Date: 09/10/2013
Goal:
To provide an independent means for all personnel to escape from the asset in the event that primary and preferred means of evacuation are unavailable.
Scope / Equipment
Scope
The following is included within the scope of this PS:
Firewater ringmain piping, associated valves, supports, control and instrumentation.
The following is omitted from the scope of this PS:
Cathodic protection system, if provided – Considered under P18.
Deluge system – Considered under M7.
Manual fire fighting equipment - Considered under M10.
Foam Systems - Considered under M8.
Fire water Pump - Considered under M5.
Sprinklers and Fine Water Spray Systems - Considered under M9.
Notes
Firewater main over pressure protection is detailed within performance standard M5
The functionality of the jockey pump/s is not safety or environmentally critical.
49
SECE Number SECE System
M5 Firewater Pumps
M7 Firewater Systems
Functionality References Means of Assurance Design References Means of Assurance Operational References
Upon demand the firewater ring main is capable of conveying the required pressure and flow of firewater to all of its the user points.
M6.1_F1 The firewater main GS EP SAF 321 The pump performance Provide The firewater main is subject to Provide references
and its associated Fire pump discharge curves and the fire references to: detailed inspection, maintenance and to:
valves and supports is stations and fire pump surge, hammer and functional testing defined within
The pump The relevant
constructed so as to water mains. vacuum analysis have been HOLD: Define the relevant
discharge maintenance
contain the firewater reviewed. maintenance management system.
Further curve/s. management
within it for all
references are The fire water system The fire Any proposed changes to the system.
foreseeable
provided within components (flanges, fittings, pump surge, firewater main are assessed in Change
operating conditions.
the GS. line pipe, etc.) are designed hammer and accordance with local change control control
to ASME B 16.5 for flange vacuum procedures. procedure.
class 150#. analysis.
Firewater
The above reviews confirmed
main P&IDs.
that the fire main at least
meets the functional
specification.
M6.1_F2 The firewater main - The asset fire system basis of Provide The management of the firewater Provide references
can maintain the design defines the reasonably isolation valves is controlled in
50
SECE Sub System:
Functionality References Means of Assurance Design References Means of Assurance Operational References
pressure and flow to foreseeable simultaneous fire references to: accordance with local procedures. to:
each user point for all zones and other fire water
The fire Ongoing performance of the Procedures
foreseeable fire users. The basis of design is
system basis firewater main is assessed as part of that cover the
demand scenarios. an input into the fire system
of design. M6.1_F1 operational assurance operation of
hydraulic analysis.
The firewater activities. firewater
A hydraulic analysis of the system main isolation
firewater main has been hydraulic valves.
performed. analysis.
A review of the analysis
confirms that the firewater
main allows the flow and
pressure functional
requirements of the firewater
users to be at least met.
M6.1_F3 The firewater main is See M6.1_F1. The fire main P&IDs and fire Provide See M6.1_F1. See M6.1_F1.
designed so as to system basis of design have references to the:
deliver firewater been reviewed.
Firewater
from at least two
The review confirmed that system basis
opposing directions
the defined functional of design.
to each defined fire
specifications are at least Firewater
zone.
met. main P&IDs.
Note: This functional
requirement is not
applicable to some
jetties, certain
51
SECE Sub System:
Functionality References Means of Assurance Design References Means of Assurance Operational References
M6.1_F4 The fire main is See M6.1_F1. See M6.1_F2. See M6.1_F2. See M6.1_F1. See M6.1_F1.
served by isolation
valves that allow
isolation of damaged
sections of the fire
main whilst
maintaining firewater
supply to each fire
zone.
M6.1_F5 Access to the - Access to/from firewater GS EP SAF 351. Continued access / egress to the Provide references
firewater main main isolation valves is Escape, firewater main isolation valve is to the:
isolation valves is treated as secondary escape evacuation and assured by maintenance of good
Housekeeping
present at all times routes as defined within GS rescue from fixed housekeeping standards in
procedures.
the fire pumps are EP SAF 351, as such requiring installations. accordance with local procedures.
available. a width of at least 0.8m and
Provide
preferentially 1m.
references to the:
The layouts & elevation
Relevant
drawings/ three dimensional
firewater
models showing the relative
main plot/
location of the fire isolation
side
valves and adjacent plant and
elevation
equipment have been
drawings/ 3D
reviewed.
52
SECE Sub System:
Functionality References Means of Assurance Design References Means of Assurance Operational References
M6.1_F6 The position of each See M6.1_F1. The data sheets of the Provide See M6.1_F1. See M6.1_F1.
firewater main firemain isolation valves have references to the:
isolation valve is been reviewed. The review
Firewater
readily discernable confirms that suitable valve
main
by visual inspection. positional indicators are
isolation
present and that each valve is
In the case of valve data
clearly tagged.
remotely operated sheets.
valves, the position The user requirement Firewater
of the valve is also specifications for the panel
made apparent at firewater pump/ main control interface
the firewater pump panel/s have been reviewed. user
main control panel/s. requirement
The review confirmed that
specification.
the functional specifications
are at least met.
The functionality of the firewater ring main must not be impeded by low temperatures.
M6.1_F7 Sections of the - The historical environmental Provide See M6.1_F1. See M6.1_F1.
firewater ring main temperature of the asset references to the:
and associated location has been reviewed.
Asset/
valves that are The review confirmed that
project
vulnerable to the firewater system is prone
environ
freezing are to ice blockage. Hold: Revise
53
SECE Sub System:
Functionality References Means of Assurance Design References Means of Assurance Operational References
54
SECE Sub System:
Availability References Means of Assurance Design References Means of Assurance Operational References
M6.1_A1 Unless supported by Provide A reliability analysis of the Provide The availability of the firewater main Provide references
a risk assessment, the references to firewater system including references to the: system is underpinned by the to the:
functionality the: the firewater pumps and maintenance, inspection and testing
Firewater Downgraded
described above is associated ring mains has regime outlined in the functionality
QRA. system situations
available at all times been performed. criteria above.
reliability procedure.
the fire pumps are
The firewater main is analysis. Failure of the firewater main or its
available.
positioned and/or protected Vehicular associated supports and valves to
Note: This statement so as to avoid the risks impact risk meet the above functionality is
should reflect the associated with assessments. defined as being unacceptable and
assumed availability dropped/swining loads or Dropped are managed via the downgraded
documented in the vehicular impacts. object and situations procedure.
asset QRA. swinging load
The review indicated that the
assessments.
reliability of the fire main is
greater than that of the fire
pumps.
55
SECE Sub System:
Survivability References Means of Assurance Design References Means of Assurance Operational References
M6.1_S1 For a period of time See M6.1_F1. The requirement for the fire Provide references to M6.1_F4 M6.1_F4
defined within M5; main to survive MAH events the:
the functionality has been incorporated into
MAH analysis
described above does the firewater main basis of
documentation.
not be impaired by design.
Firewater main
reasonably
The fire main isometrics have Basis of Design.
foreseeable MAHs.
been reviewed. The review Relevant
has confirmed that the fire firewater main
main and associated isolation protection
valves are, so far as is philosophy.
reasonably practicable,
positioned and/or protected
to survive MAHs for a period
of time defined within M5.
See M6.1_F4.
56
OPERATIONAL VERIFICATION VSEL 3
57
OPERATIONAL VERIFICATION VSEL 3
confirm that:
The maintenance programme is being
executed to plan.
Identified issues are being tracked through
to completion.
58
SECE Number: M7 SECE System: Firewater Systems Revision: Rev B2 Date: 01/10/2013
Goals:
To contain and/or extinguish pool fires and reduce the effects of smoke and thermal radiation from all fire events.
Scope / Equipment
M7.4 Hydrants
Scope
The scope of this performance standards includes:
All firewater systems fed from the firewater pumps including, but not limited to:
o Deluge System including control system, dry deluge piping and nozzles .
o Fixed / Oscillating Firewater Monitors.
o Sprinkler System including the piping, the fusible head and nozzle.
o Hydrants.
o High Capacity Hose Reels.
The following is omitted from the scope of this PS:
59
Foam Systems – Covered under M8.
Liquid and gaseous extinguishing systems not fed from the firewater pumps – Covered under M9.
Portable / trolley mounted extinguishers – Covered under M10.
Notes
E1 PA/GA System.
M5 Firewater Pumps
M6 Firewater Main
M8 Foam Systems
60
SECE Sub System:
Distribute sufficient pressure / flow of water to meet the design application requirements in each deluge area
M7.1_F1 Deluge system meet Provide Reasonably foreseeable fires Provide references to Operational assurance is Provide reference to:
the minimum rates references to: are detailed and assessed the: provided by routine
and pressures shown within the asset fire and inspection and function GS EP EXP 311 Plant
GS EP SAF GS EP SAF 322 Integrity Minimum
in Table 1 presented explosion risk assessment. checks, carried out in
322. Asset fire and Inspection
at the back of this accordance with relevant
Table 1. The asset fire protection explosion Requirements
document. work instruction at
Asset fire philosophy details how fixed analysis. GSP EP EXP 213
frequencies scheduled in as
Note - Table 1 make protection fire fighting systems are to be Asset fire Minimum
scheduled in the asset
reference to the philosophy. used to mitigate fire hazards. protection Maintenance
maintenance management
firewater demand The philosophy enacts philosophy. Requirements
system.
design case to application rates specified in Asset fixed fire Asset Inspection and
emphasise that the GS EP SAF 322. system basis of Changes to the system are Maintenance
required design. in accordance with the Total Management System
The detailed active firewater
area/equipment Asset fixed fire change control procedure.
suppression layout drawings
coverage flows and system P&IDs and
define the type, number and
pressures must be layout drawings.
location of active firewater
achieved for the Fire System data
users.
maximum demand sheets.
case. The complete Based upon the firewater TA report
hydraulic data can be suppression layout drawings, confirming
difficult for older firewater hydraulic compliance with
facilities. To calculations have been codes, standards
complement the data performed. The calculations and statutory
extractable from the define the required flowrate regulations
hydraulic analysis and pressures to be delivered Affiliate / Asset
report, there may be at the deluge nozzles, these Procurement and
field test report on are presented in Table 1. QA Procedure
61
SECE Sub System:
62
SECE Sub System:
M7.1_F2 Deluge system is Provide The asset fire protection Provide reference to: See M7.1_F1. See M7.1_F1.
activated via the reference to: philosophy details the
Asset FERA.
following: activation philosophy for the
GS EP SAF Asset fire
deluge system.
[HOLD – Insert 322. protection
asset specific Firewater Documented confirmation by philosophy.
systems] e.g. functional suitably competent technical TA report
Automated specification authority that system confirming
signal from Fire . complies with company compliance with
and Gas Panel]. standards and statutory codes, standards
Manual release regulations. and statutory
valve at deluge Procurement and QA regulations
cabinet. procedures ensure original Affiliate / Asset
Manual release equipment and components Procurement and
button in control comply with the relevant QA Procedure
room. design codes, company
Fusible bulbs. standards and statutory
regulations.
M7.1_F4 Firewater at the most Provide The asset fire protection Provide reference to: See M7.1_F1. See M7.1_F1.
remote water spray reference to: philosophy details the
Asset FERA.
nozzle to be fully activation philosophy for the
GS EP SAF Asset fire
established within deluge system. Deluge
322. protection
[HOLD – Insert value] system response times have
Asset fire philosophy.
seconds from been determined based on
protection Firewater
confirmed detection. Total guidance and other
63
SECE Sub System:
Distribute sufficient pressure / flow of water to meet the design application requirements for fire monitors
64
SECE Sub System:
M7.2_F1 Fixed monitors Provide See M7.1_F1 See M7.1_F1 See M7.1_F1. See M7.1_F1.
achieve minimum references to:
rates and pressures
Table 1.
shown in Table 1
Asset fire
protection
philosophy.
M7.2_F2 Monitors are on Provide The asset fire protection Provide reference to: See M7.1_F1. See M7.1_F1.
actuation oscillate reference to: philosophy details how fixed
Asset fire
smoothly and fully in fire fighting systems are to be
Asset fire protection
the horizontal plane used to guard against fire
fighting philosophy.
(this is applicable for hazards.
philosophy. TA report
both manual and
Documented confirmation by confirming
automatic monitors).
suitably competent technical compliance with
authority that system codes, standards
complies with company and statutory
standards and statutory regulations
regulations. Affiliate / Asset
Procurement and QA Procurement and
procedures ensure original QA Procedure.
equipment and components
comply with the relevant
design codes, company
standards and statutory
regulations.
M7.2_F3 Helideck monitors See M7.2_F2 See M7.2_F2 See M7.2_F2 See M7.1_F1. See M7.1_F1.
65
SECE Sub System:
are pneumatically
operated and can be
remotely operated
from a remote
control panel, even
when all power is
lost.
Distribute sufficient pressure / flow of water to meet the design application requirements for sprinkler system
M7.3_F1 Sprinkler systems are See M7.1_F1 See M7.1_F1 See M7.1_F1 See M7.1_F1. See M7.1_F1.
supplied by the
firewater ring as
detailed in Tables 2 &
3.
M7.3_F2 Sprinkler system are Provide See M7.1_F2 See M7.1_F2 See M7.1_F1. See M7.1_F1.
activated via the reference to:
following:
Asset FERA.
HOLD – Insert Asset fire
asset specific protection
systems e.g. philosophy.
[Automated
signal from Fire
and Gas Panel].
Manual release
valve at deluge
cabinet.
66
SECE Sub System:
Manual release
button in control
room.
Fusible bulbs.
Distribute sufficient pressure / flow of water to meet the design application requirements for hydrants
M7.4_F1 Hydrants are located Provide The asset fire protection Provide references to: See M7.1_F1. See M7.1_F1.
such that all areas of references to: philosophy details how fixed
GS EP SAF 322.
plant not covered by fire fighting systems are to be
GS EP SAF Asset FERA.
any other area fire used to guard against fire
322. Asset fire
protection can be hazards.
protection
reached by two
Locations of the hydrants are philosophy.
hydrants.
shown on the Escape Route Escape Route and
and Safety Equipment layout Safety Equipment
plot plans which are layout plot plans.
displayed at strategic TA report
locations throughout the confirming
installation. compliance with
Documented confirmation by codes, standards
suitably competent technical and statutory
authority that hydrant regulations
location complies with Affiliate / Asset
company standards and Procurement and
statutory regulations. QA Procedure
Procurement and QA
procedures ensure original
67
SECE Sub System:
M7.4_F2 Hydrants to be Provide See M7.1_F1 See M7.1_F1 See M7.1_F1. See M7.1_F1.
capable of delivering references to:
a minimum flow-rate
GS EP SAF
of HOLD m3/hour.
322.
For safety of
personnel handling
the hose the hydrant
outlet pressure must
be limited to HOLD
barg.
Distribute sufficient pressure / flow of water to meet the design application requirements for high capacity hose reels
M7.5_F1 High Capacity Hose Provide The asset fire protection Provide references to: See M7.1_F1. See M7.1_F1.
reels to be located in references to: philosophy details how fixed
GS EP SAF 322.
nominated areas as fire fighting systems are to be
GS EP SAF Asset FERA.
indicated on the Fire used to guard against fire
322. Asset fire
& Safety Equipment hazards.
protection
Layout drawings.
Locations of the high capacity philosophy.
hose reels are shown on the Escape Route and
Escape Route and Safety Safety Equipment
Equipment layout plot plans layout plot plans.
68
SECE Sub System:
M7.5_F2 Each hose reel is of Provide Documented confirmation by Provide references to: See M7.1_F1. See M7.1_F1.
the drum type references to: suitably competent technical
TA report
mounted in cabinets authority that hose reel
GS EP SAF confirming
and capable of design, specification and
322. compliance with
delivering a minimum manufacture complies with
codes, standards
flow of HOLD the relevant design codes,
and statutory
m3/hour. company standards and
regulations.
statutory regulations.
Affiliate / Asset
Procurement and QA Procurement and
procedures ensure original QA Procedure
equipment and components
comply with the relevant
design codes, company
standards and statutory
regulations.
69
SECE Sub System:
M7_A1 Firewater delivery Provide reference Documented confirmation by Provide references See M7.1_F1. See M7.1_F1.
systems to be to: suitably competent technical to:
continuously available authority that the, specification
Asset active TA report
during platform and manufacture of relevant
Fire confirming
production. firewater systems complies
Protection compliance
with the relevant design codes,
In the event of critical philosophy. with codes,
company standards and
unavailability of the GS EP SAF standards and
statutory regulations.
firewater delivery 322 Fixed statutory
systems, with a Firewater Design reviews, approvals and regulations.
duration that exceeds Systems the associated QA/QC Affiliate / Asset
a single shift, processes completed during the Procurement
production operations engineering phase of the Asset and QA
may only continue in EPC provide the primary Procedure
controlled conditions, assurance activity that the
where a risk firewater delivery systems are
assessment has been fit for purpose.
completed and
accepted by senior
management; and
when suitable
temporary provisions
are in place.
Any failure of a safety
critical element to
70
SECE Sub System:
function on demand is
treated as
unacceptable and the
root cause identified
and rectified.
Planned outages are
subject to appropriate
risk assessment and
may require
alternative fire-fighting
systems to be put in
place during the period
of the outage.
M7_S1 Deluge skids to be Provide reference Various safety studies assess Provide references Ongoing suitability is addressed Provide
protected from fire to: the potential impairment of to the: within the scope of the risk reference to:
and explosion by safety systems during MAHs assessment in support of the
Asset active MAH analysis Total
location away from and makes recommendations Safety Case / COMAH and
Fire documentation Change
protected area. with respect to protection updates of supporting studies.
Protection TA report Control
71
SECE Sub System:
philosophy. strategy including achievement confirming Changes to the system are in Procedure
GS EP SAF of this through design location, compliance accordance with the Total Asset safety
322 Fixed redundancy and diversity in with codes, change control procedure. case /
Firewater equipment. standards and COMAH
Systems statutory Report.
The location relevant firewater
regulations Relevant
system has been reviewed. The
Affiliate / Asset supporting
review has confirmed that the
Procurement safety
equipment is, so far as is
and QA studies e.g.
reasonably practicable,
Procedure EERA, FEA,
positioned and/or protected to
QRA.
survive MAHs.
Documented confirmation by
suitably competent technical
authority that the, specification
and manufacture of relevant
firewater systems complies
with the relevant design codes,
company standards and
statutory regulations.
Design reviews, approvals and
the associated QA/QC
processes completed during the
engineering phase of the Asset
EPC provide the primary
assurance activity that the
firewater delivery systems are
fit for purpose.
72
SECE Sub System:
M7_S2 Deluge pipe work to be See M7.1_S1 See M7.1_S1 See M7.1_S1 See M7.1_S1 See M7.1_S1
routed to minimise
effect of predicted
explosion
overpressure.
M7_S3 Single items of fire See M7.1_S1 See M7.1_S1 See M7.1_S1 See M7.1_S1 See M7.1_S1
fighting equipment
may be rendered
unavailable or
inaccessible as a result
of a fire or accident.
Sufficient redundancy
is provided to ensure
that a minimum
provision is always
available.
M7_V1 Review any changes made to the asset which could M7 - All
affect the firewater water systems since the last
operational verification visit.
73
OPERATIONAL VERIFICATION VSEL 3
M7_V2 Confirm that all standard work text instructions have M7 - All
scheduled within the maintenance management
system have been completed as scheduled.
M7_V4 Witness function test (dry tests) of deluge This will support
skids. Functionality Items
M7.1_F1, M7.1_F2,
M7.1_F3, M7.1_F4,
M7.1_F5, M7.1_F6
M7_V5 Visual examination and witness function test of This will support
monitors. Functionality Items
M7.2_F1, M7.2_F2.
M7_V6 Visual examination and witness function test of This will support
sprinklers. Functionality Items
M7.3_F1, M7.3_F2.
M7_V7 Visual examination and witness function test of This will support
hydrants. Functionality Items
M7.4_F1, M7.4_F2
M7_V8 Visual examination and witness function test of This will support
hosereels. Functionality Items
74
OPERATIONAL VERIFICATION VSEL 3
M7.5_F1, M7.5_F2
M7_V9 Witness function test of Helideck monitors and This will support
confirm remote operation when all power is Functionality Item M7.2_F3.
lost.
Table 1 – Minimum Acceptable Flow Rates and Pressures for the Deluge and Fixed Monitor Systems.
Location / Protected Equipment Minimum Flow Rate [litres Minimum Pressure [bar] (Measured P&ID No.
per minute] downstream of deluge valve)
Deluge Valves
HOLD – Asset specific details to be incorporated. HOLD – Asset specific details HOLD – Asset specific details to be HOLD – Asset specific details
All modules with the deluge system should be listed here and to be incorporated. incorporated. to be incorporated.
the corresponding minimum flow rates and pressures. [##] <##> [P & ID Reference]
HOLD – Asset specific details to be incorporated. HOLD – Asset specific details HOLD – Asset specific details to be HOLD – Asset specific details
to be incorporated. incorporated. to be incorporated.
Fire Monitors
HOLD – Asset specific details to be incorporated. HOLD – Asset specific details HOLD – Asset specific details to be HOLD – Asset specific details
to be incorporated. incorporated. to be incorporated.
HOLD – Asset specific details to be incorporated. HOLD – Asset specific details HOLD – Asset specific details to be HOLD – Asset specific details
to be incorporated. incorporated. to be incorporated.
75
Table 2: Sprinkler Application rates
Location Discharge Density Minimum Flow Rate Minimum Pressure [bar] P&ID No.
[mm/min] [litres per minute] (Measured downstream of
deluge valve)
Sprinklers
HOLD – Asset specific details to be incorporated. HOLD – Asset specific HOLD – Asset specific HOLD – Asset specific details to HOLD – Asset specific
All modules with the deluge system should be details to be details to be be incorporated. details to be
listed here and the corresponding minimum flow incorporated. incorporated. <##> incorporated.
rates and pressures. [##] [P & ID Reference]
HOLD – Asset specific details to be incorporated. HOLD – Asset specific HOLD – Asset specific HOLD – Asset specific details to HOLD – Asset specific
details to be details to be be incorporated. details to be
incorporated. incorporated. incorporated.
76
SECE Number: M8 SECE System: Foam Systems Revision: Rev B3 Date: 24/10/2016
Goal:
To provide a reliable and secure supply of foam for firefighting at the required pressures and flows for all foam dependent systems on the installation.
Scope / Equipment
Scope:
Foam storage tanks, pumps, proportioner including all associated valves, pipework & control instrumentation.
Note 1
Foam type likely to include variations of normal Aqueous Film Forming Foam (AFFF), Alcohol Resistant Aqueous Film Forming Foam (AR-AFFF), Low/Medium/High
expansion etc.
Note 1
77
‘Flow control method’ is the means of foam proportioning used such as a flow control valve, proportioner.
E4 Helideck
M7 Firewater Systems
M8.1_F1 The Helideck is Provide reference Reasonably foreseeable fires Provide reference Operational assurance is Provide reference
provided with HOLD – to: are detailed and assessed to: provided by routine inspection to:
Insert number within the asset fire and and function checks, carried out
CAA -CAP CAA -CAP 437. GS EP EXP
automatically explosion risk assessment. in accordance with relevant
437 GS EP SAF 322 311 Plant
controlled water/AFFF work instruction at frequencies
NPFA 11 - The asset fire protection Fixed Integrity
monitors. Each scheduled in as scheduled in
Standard for philosophy details how fire Firewater Minimum
monitor has a capacity the asset maintenance
Low, fighting systems are to be used Systems Inspection
of [HOLD – Insert management system.
Medium, to mitigate fire hazards, FERA. Requirement
flowrate] L/min in of
High including the type and required Asset fire Changes to the system are in s
with [HOLD – Insert
Expansion duration of foam application. protection accordance with the Total GSP EP EXP
pressure] barg inlet
Foam. philosophy. change control procedure. 213
pressure. The fire system basis of design
Active Fire enacts the fire protection Fire system Minimum
78
SECE Sub System:
Procurement and QA
procedures ensure original
equipment and components
comply with the relevant design
codes, company standards and
statutory regulations.
79
SECE Sub System:
M8.1_F2 Helideck foam tanks See M8.1_F1 See M8.1_F1 See M8.1_F1 See M8.1_F1 See M8.1_F1
are filled with
minimum of:
[HOLD – Insert
tank description,
tag number and
volume m3.
M8.1_F3 The Helideck High See M8.1_F1 See M8.1_F1 See M8.1_F1 See M8.1_F1 See M8.1_F1
Capacity Hose reels
deliver [HOLD – Insert
percentage] % AFFFAR
foam at a minimum
rate of [HOLD – Insert
flowrate] lpm, fed from
the foam concentrate
ring main. The hose
reel pressure is
regulated to [HOLD –
Insert pressure] barg,
which is sufficient to
ensure uniform
application to all parts
of the safe landing
area, irrespective of
wind strength or
condition, in
accordance with the
80
SECE Sub System:
requirements of CAA
CAP437.
M8.1_F4 On actuation of the See M8.1_F1 See M8.1_F1 See M8.1_F1 See M8.1_F1 See M8.1_F1
manual air release
valves, foam reach the
Helideck in less than
[HOLD – Inert no of
Second] seconds.
M8.1_F5 Foam Monitors See M8.1_F1 Procurement and QA Provide reference See M8.1_F1 See M8.1_F1
including those that procedures ensure original to:
service the helideck equipment and components
Affiliate / Asset
are on actuation comply with the relevant design
Procurement
oscillate smoothly and codes, company standards and
and QA
fully in the horizontal statutory regulations.
Procedure.
plane (this is applicable
for both manual and
automatic monitors).
M8.1_F6 Foam Monitors in See M8.1_F1 See M8.1_F1 See M8.1_F1 See M8.1_F1 See M8.1_F1
conjunction with their
Foam Induction Units
produce Finished Foam
of the correct
concentration.
81
SECE Sub System:
function for a
minimum of [HOLD –
Insert minutes] on loss
of Instrument Air
Supply
Sufficient foam concentrate at the correct storage conditions are stored on the asset.
M8.3_F1 Foam tanks are filled See M8.1_F1 See M8.1_F1 See M8.1_F1 See M8.1_F1 See M8.1_F1
with minimum of:
[HOLD – Insert
tank description,
tag number and
volume m3.
[HOLD – Insert
tank description,
tag number and
volume] m3.
M8.3_F2 The quality of the Provide reference See M8.1_F1 See M8.1_F1 See M8.1_F1 See M8.1_F1
stored Foam to:
Concentrate is to be
NPFA 11 -
within the following
Standard for
specification:
Low,
[HOLD – Insert Medium,
tank description, High
tag number [HOLD Expansion
– Insert
82
SECE Sub System:
percentage] % Foam.
AFFF. GS SAF 334
[HOLD – Insert Foam Fire
tank description, Extinguishing
tag number and Systems.
[HOLD – Insert
percentage] %
AFFF.
M8.5_F1 [HOLD – Insert flow See M8.1_F1 See M8.1_F1 See M8.1_F1 See M8.1_F1 See M8.1_F1
control method]
maintain foam
injection at a rate
between [HOLD –
Insert minimum
percentage of
flowrate] and [HOLD –
Insert maximum
percentage of
flowrate] of the
required firewater
deluge demand.
[HOLD – Depending on
the number of
proportioners, this
information may
83
SECE Sub System:
require to be outlined
within a table at the
back of this document.
M8.5_F2 Deluge systems Provide reference Documented confirmation by Provide reference One-time Approval Process – One-time
protecting areas which to: suitably competent technical to: See means of design assurance. Approval Process
present a credible pool authority that foam system – See means of
NPFA 11 - TA report
fire risk are provided design (including foam storage design assurance.
Standard for confirming
with dual water / foam tanks), specification and
Low, compliance
capability in manufacture complies with the
Medium, with codes,
accordance with NFPA relevant design codes, company
High standards and
11. standards, statutory regulations
Expansion statutory
and enacts the asset fire
Foam. regulations
protection philosophy.
GS SAF 334 Affiliate / Asset
Confirmation based on review
Foam Fire Procurement
of firewater calculations and
Extinguishing and QA
other design and manufacture
Systems. Procedure.
documentation.
Procurement and QA
procedures ensure original
equipment and components
comply with the relevant design
codes, company standards and
statutory regulations.
M8.5_F3 The foam system for See M8.5_F2 See M8.5_F2 See M8.5_F2 One-time Approval Process – One-time
the Methanol storage Approval Process
84
SECE Sub System:
M8.6_F1 Mobile foam units - - Provide reference Monthly visual inspection Provide reference
are provided as to the Safety to asset
additional means to concept and to inspection
either protect safety equipment program
layout
specific equipment
or provide additional
capabilities to the
emergency response
team
M8.6_F2 Mobile Foam - - Provide reference Monthly visual inspection Provide reference
Trolleys shall be to the Safety to asset
provided with a concept. inspection
[hold, tank insert program
capacity] storage
tank.
M8.6_F3 Foam concentrate - - Provide reference Monthly visual inspection and Provide reference
shall be [hold, to the Safety annual functional test if to manufacturer
insert foam type concept. possible using for instance out maintenance
and concentration] of date foam supply documentation
and minimum
85
SECE Sub System:
Safely contain foam within the pipework connecting the foam storage tanks to the inductor on the deluge skid as per design requirements
M8.9_F1 Foam is contained Provide reference Documented confirmation by Provide reference See M8.1_F1 See M8.1_F1
within the pipework to: suitably competent technical to:
connecting the foam authority that process
GS SAF 334 GS EP PVV
storage tanks to the
Foam Fire equipment design, specification 111 Piping
inductor on the deluge
Extinguishing and manufacture complies with Valves Vessels
skid (via the foam
Systems. the relevant design codes, General
pump/s) for conditions
within the design company standards and Specification
operating envelope. statutory regulations. catalogue
Confirmation based on review TA report
confirming
of process/structural
compliance
calculations, material selection with codes,
reports and other design and standards and
manufacture documentation. statutory
86
SECE Sub System:
M8.10_F1 Foam pumps achieve See M8.1_F1 See M8.1_F1 See M8.1_F1 See M8.1_F1 See M8.1_F1
the following on
activation:
[HOLD – Insert
foam pump
description,
equipment tag
deliver [HOLD
insert flow rate
m3/hr and
pressure barg].
[HOLD – Insert
87
SECE Sub System:
foam pump
description,
equipment tag
deliver [HOLD
insert flow rate
m3/hr and
pressure barg].
[HOLD – Depending on
the number of pumps,
this information may
require to be outlined
within a table at the
back of this document.
M8_A1 Helideck foam Provide reference Documented confirmation by Provide references Foam system availability is Provide
monitors are 100% to: suitably competent technical to: assured through adherence to reference to:
available during flying authority that the, specification standards and procedures,
GS SAF 334 TA report Total
operations. and manufacture of helideck regular inspection and function
Foam Fire confirming Change
fire fighting systems complies testing and reporting,
Foam monitors work Extinguishing compliance Control
88
SECE Sub System:
on demand. In the Systems. with the relevant design codes, with codes, monitoring and completion of Procedure.
event of critical CAA -CAP company standards and standards and corrective work orders (as per Asset safety
unavailability of the 437 statutory regulations. statutory priority assignment). case /
Helideck fire systems. regulations. COMAH
Design reviews, approvals and Temporary changes to the
Affiliate / Asset Report.
Helideck operations the associated QA/QC system are in accordance with
Procurement Relevant
may only continue in processes completed during the the Total change control
and QA supporting
controlled conditions, engineering phase of the Asset procedure
Procedure safety
where a risk EPC provide the primary
Ongoing suitability is addressed studies e.g.
assessment has been assurance activity that the
within the scope of the risk EERA, FEA,
completed and firewater delivery systems are
assessment in support of the QRA.
accepted by senior fit for purpose.
Safety Case / COMAH Report Asset ISSOW
management; and
and updates of supporting procedure.
when suitable
studies.
temporary provisions
are in place. Changes to the system are in
accordance with the Total
Any failure of a safety
change control procedure.
critical element to
function on demand is
treated as
unacceptable and the
root cause identified
and rectified.
Planned outages are
subject to appropriate
risk assessment and
may require
alternative fire-fighting
89
SECE Sub System:
systems to be put in
place during the period
of the outage.
M8_A2 Deluge delivered foam Provide reference See M8_A1 See M8_A1 See M8_A1 See M8_A1
systems are available to:
at all times, unless
NPFA 11 -
down for maintenance
Standard for
or inspection which
Low,
should be subject to an
Medium,
appropriate risk
High
assessment.
Expansion
Foam.
GS SAF 334
Foam Fire
Extinguishing
Systems.
90
SECE Sub System:
M8_S1 Helideck foam Provide reference Various safety studies assess Provide references Ongoing suitability is addressed Provide
monitors to be to: the potential impairment of the to the: within the scope of the risk reference to:
protected from effects foam system and its elements assessment in support of the
NPFA 11 - MAH analysis Total
of aircraft collision and during MAHs and makes Safety Case / COMAH Report
Standard for documentation Change
effects of fire on recommendations with respect and updates of supporting
Low, Control
Helideck by location to protection strategy including studies.
Medium, Procedure
and provision of achievement of this through
High Changes to the system are in Asset safety
multiple units. design, location and
Expansion accordance with the Total case /
redundancy.
Foam. change control procedure. COMAH
GS SAF 334 Design reviews, approvals and Report.
Foam Fire the associated QA/QC Relevant
Extinguishing processes completed during the supporting
Systems. engineering phase of the Asset safety
CAA -CAP EPCI provide the primary studies e.g.
437 assurance activity that the foam EERA, FEA,
Active Fire systems are fit for purpose. QRA.
Protection
philosophy
M8_S2 Deluge foam supplies See M8_S1 See M8_S1 See M8_S1 See M8_S1 See M8_S1
to be protected by
location and
redundancy from
effects of fire and
explosion in the
protected area.
91
SECE Sub System:
92
OPERATIONAL VERIFICATION VSEL 3
M8_V1 Review any changes made to the asset which affect M8 - All
the foam system since the last operational
verification visit.
M8_V2 Confirm that all standard work text instructions have M8 - All
scheduled within the maintenance management
system have been completed as scheduled.
M8_V3 Visual examination and witness function test of Test will support
helideck fixed foam monitors. Functionality Items
M8.1_F1, M8.1_F4,
M8.1_F5
M8_V5 Witness function test of helideck High Capacity Test will support
Hose reels. Functionality Items
M8.1_F3
M8_V6 Analyse samples from foam storage and from Test will support
dispensed foam. Functionality Items
M8.1_F6, M8.3_F2,
93
OPERATIONAL VERIFICATION VSEL 3
M8.5_F1.
M8_V7 Visual examination and witness function test of Test will support
foam pumps. Functionality Items
M8.10_F1.
94
SECE Number: M9 SECE System: Liquid & Gaseous Extinguishing Revision: Rev B2 Date: 01/10/2013
Systems
Goal:
To extinguish fires within enclosures or spaces that could lead to a MAH.
Scope / Equipment
Scope:
All gaseous extinguishant systems [HOLD – Insert type e.g. Inergen, CO2 etc] including storage, distribution piping, valves, nozzles and all
associated instrumentation and control systems (See Note 1).
[HOLD – Inset Extinguishant agent system i] which protects areas:
Area [HOLD – Insert area description].
Area [HOLD – Insert area description].
[HOLD – Inset Extinguishant agent system ii] which protects areas:
95
Area [HOLD – Insert area description].
Area [HOLD – Insert area description].
HOLD - List any other agent systems used on the Facility with their location.
Exclusions:
Water-based self-contained systems which are covered under M7 – Firewater Systems.
Enclosure fire dampers operating on Non-Hazardous Ventilation Systems which are covered under P8 – Process Area Ventilation.
Note 1
Not all gaseous extinguishant systems will necessarily be SECE. They are primarily provided for equipment protection to prevent escalation, should a fire event occur.
Refer to GS EP EXP 407 for guidance on the Selection of Safety and Environmentally Critical Elements.
Engagement with the Facility Engineer(s) and Mechanical Technical Authority is also recommended to ensure all aspects of the facility are covered.
M9.1_F1 Extinguisher system Provide reference Reasonably foreseeable fires Provide reference Operational assurance is Provide reference
(CO2, FM200, Inergen, to: are detailed and assessed to: provided by routine inspection to:
M9.2_F1
Water Mist / Fog within the asset fire and and function checks, carried out
Asset FERA. Asset FERA. GS EP EXP
M9.4_F1 Systems) distribute explosion risk assessment. in accordance with relevant
Asset fire
96
M9 SECE Sub System: Liquid & Gaseous Extinguishing Systems
M9.5_F1 sufficient protection The asset fire protection work instruction at frequencies 311
extinguishment to philosophy. philosophy details how fire Asset fire scheduled in as scheduled in GSP EP EXP
extinguish fire with Fire and Gas fighting systems are to be used protection the asset maintenance 213
sufficient after flow to Layout to mitigate fire hazards, philosophy. management system. Asset
compensate for Drawings including the type and required Fire system Inspection
Changes to the system must be
enclosure leakage. Fire and Gas duration of extinguishant. BOD. and
in accordance with the Total
System requirements Logigrams TA report Maintenance
The fire system basis of design change control procedure.
are presented in Table P&ID for CO2 confirming Management
enacts the fire protection
1. Skids. compliance System
philosophy.
NFPA 12: with codes, Total Change
Standard for Documented confirmation by standards and Control
Carbon suitably competent technical statutory Procedure.
Dioxide authority that the extinguishant regulations
Extinguishing system design, specification and Asset HAZID
Systems manufacture complies with the study.
TOTAL relevant design codes, company Asset HAZOP
General standards, statutory regulations study.
Specification: and enacts the asset fire Affiliate / Asset
Safety –GS protection philosophy. Procurement
EP 331 – Confirmation based on review and QA
Carbon of firewater calculations and Procedure
dioxide fire other design and manufacture
extinguishing documentation.
system The process design has been
subject to HAZID / HAZOP
studies to ensure appropriate
protection from design
97
M9 SECE Sub System: Liquid & Gaseous Extinguishing Systems
deviations is provided.
Procurement and QA
procedures ensure original
equipment and components
comply with the relevant design
codes, company standards and
statutory regulations and are fit
for purpose.
M9.1_F2 Units to have 100% See M9.1_F1 Documented confirmation by Provide reference See M9.1_F1 See M9.1_F1
back up supply of CO2 suitably competent technical to:
M9.2_F2
and FM200 i.e. dual authority that the extinguishant
TA report
M9.4_F2 shot capability. system design, specification and
confirming
manufacture complies with the
M9.5_F2 compliance
relevant design codes, company
with codes,
standards, statutory regulations
standards and
and enacts the asset fire
statutory
protection philosophy.
regulations.
Confirmation based on review
Affiliate / Asset
of firewater calculations and
Procurement
other design and manufacture
and QA
documentation.
Procedure.
Procurement and QA
procedures ensure original
equipment and components
98
M9 SECE Sub System: Liquid & Gaseous Extinguishing Systems
M9.1_F4 Systems to be provided See M9.1_F1 See M9.1_F2 See M9.1_F2 See M9.1_F1 See M9.1_F1
with a manual release.
M9.2_F4
M9.4_F4
M9.5_F4
M9.1_F5 System status and See M9.1_F1 See M9.1_F2 See M9.1_F2 See M9.1_F1 See M9.1_F1
alarm signals to be
M9.2_F5
provided in the CCR.
M9.4_F5
M9.5_F5
M9.1_F6 CO2 and FM200 See M9.1_F1 See M9.1_F2 See M9.1_F2 See M9.1_F1 See M9.1_F1
systems to be provided
99
M9 SECE Sub System: Liquid & Gaseous Extinguishing Systems
M9.1_F7 CO2 or FM200 See M9.1_F1 See M9.1_F2 See M9.1_F2 See M9.1_F1 See M9.1_F1
protected areas to be
M9.2_F7
clearly marked with
M9.4_F7 warning signs.
M9.5_F7
M9.1_F8 Executive action upon See M9.1_F1 See M9.1_F2 See M9.1_F2 See M9.1_F1 See M9.1_F1
confirmed fire
M9.2_F8
detection as per F&G
M9.4_F8 logograms.
M9.5_F8
100
M9 SECE Sub System: Liquid & Gaseous Extinguishing Systems
M9.1_F9 Area fire dampers See M9.1_F1 See M9.1_F2 See M9.1_F2 See M9.1_F1 See M9.1_F1
close upon F&G signals
M9.2_F9
in accordance with
M9.4_F9 F&G Cause and Effect
diagrams.
M9.5_F9
M9.3_F1 Galley Hood Fire Provide reference Documented confirmation by Provide reference See M9.1_F1 See M9.1_F1
Suppression to: suitably competent technical to:
Extinguishing System authority that the extinguishant
Asset fire TA report
to be capable of system design, specification and
protection confirming
delivering manufacture complies with the
philosophy. compliance
extinguishing agent relevant design codes, company
NFPA 17A: with codes,
(HOLD – Insert name of standards, statutory regulations
Standard for standards and
suppressant) over all and enacts the asset fire
Wet statutory
areas of cooking protection philosophy.
Chemical regulations.
surfaces were cooking Confirmation based on review
Extinguishing Affiliate / Asset
oil or fat fire may of firewater calculations and
Systems Procurement
occur. other design and manufacture
and QA
documentation.
Procedure.
Procurement and QA
procedures ensure original
equipment and components
comply with the relevant design
codes, company standards and
statutory regulations and are fit
for purpose.
M9.3_F2 Manual system See M9.3_F1 See M9.3_F1 See M9.3_F1 See M9.3_F1 See M9.3_F1
101
M9 SECE Sub System: Liquid & Gaseous Extinguishing Systems
operation is achieved
by the activation of a
cable pulley system
located at the galley
exit which opens a
valve on the nitrogen
cylinder.
Automatic system
operation is initiated
by fusible link
detectors rated at
[HOLD – Insert
temperature] and
located within the
extract hood.
The system is
interfaced with the
F&G System for shut
down of the fire
dampers and stopping
of the fans. The
activation is from the
F&G System.
102
SECE Sub System: Liquid & Gaseous Extinguishing Systems
M9.1_A1 Liquid and gaseous See M9.3_F1 See M9.3_F1 See M9.3_F1 System reliability / availability is Provide
extinguishing systems assured through adherence to reference to:
M9.2_A1
to be available at all standards and procedures,
Total
M9.4_A1 times unless regular inspections and
Change
alternative reporting, monitoring and
Control
arrangements are in completion of corrective work
Procedure –
place. orders (as per priority
Asset safety
assignment).
case /
Temporary / permanent COMAH
changes to the system are in Report.
accordance with the Total Relevant
change control procedure. supporting
safety
Ongoing suitability is addressed
studies e.g.
within the scope of the risk
EERA, FEA,
assessment in support of the
QRA.
Safety Case / COMAH Report
and updates of supporting
studies.
Changes to the system are in
accordance with the Total
change control procedure.
103
SECE Sub System: Liquid & Gaseous Extinguishing Systems
M9.1_S1 System to be Provide reference Various safety studies assess Provide reference Ongoing suitability is addressed Provide
unimpaired in a MAH to: the potential impairment of to: within the scope of the risk reference to:
M9.2_S1
for which it is meant to safety systems during MAHs assessment in support of the
Asset fire MAH analysis Total
M9.4_S1 provide protection. and makes recommendations Safety Case / COMAH and
protection documentation Change
with respect to protection updates of supporting studies.
philosophy. Communicatio Control
strategy including achievement
n systems Basis Changes to the system are in Procedure
of this through design location,
of Design. accordance with the Total Asset safety
redundancy and diversity in
EER change control procedure. case /
equipment.
philosophy. COMAH
The requirement for field Asset Safety Report.
equipment (including antennas) Philosophy. Relevant
to survive MAH events has been supporting
incorporated into the safety
communication system basis of studies e.g.
design. EERA, FEA,
The location of field equipment QRA.
(including antennae) has been
reviewed. The review has
confirmed that the equipment
is, so far as is reasonably
practicable, positioned and/or
protected to survive MAHs.
104
OPERATIONAL VERIFICATION VSEL 3
M9_V1 Review any changes made to the asset which affect M9 - All
the suppressant system since the last operational
verification visit.
M9_V2 Confirm that all standard work text instructions have M9 - All
scheduled within the maintenance management
system have been completed as scheduled.
M9_V3 Visual examination and witness function test of Test will support all
fire suppressant systems to confirm the functionality requirements
following: associated with 9.1, 9.2, 9.3
and 9.4.
All piping and equipment within skid
enclosures are undamaged, securely fitted
and functioning.
Control gas container pressure is kept as
per [HOLD – Insert relevant P&ID
reference].
Normally open/ car seal open valves are as
per [HOLD – Insert relevant P&ID
reference].
Gas bottles are within certification.
Each gaseous extinguishant system control
and instrumentation is functioning in
accordance with the asset F&G Cause and
105
OPERATIONAL VERIFICATION VSEL 3
Effect diagrams.
Fire dampers close upon F&G signal in
accordance with F&G Cause and Effects.
Visual conformation of fire damper blade
full travel and closure.
Relevant audible and visual alarms activate
as per the Cause and Effect Charts.
M9_V4 Visual examination and witness function test of Test will support
Galley Hood Fire Suppression Extinguishing Functionality Items
System to confirm the following: M9.3_F1 and M9.3_F2.
106
SECE Number: M10 SECE:- Portable Fire Extinguishers Revision: Rev B2 Date: 18/03/2014
Goal:
To fight small fires in process areas, living quarters, technical rooms, helideck etc, to prevent escalation.
Scope / Equipment
Scope
The scope of this performance standard includes:
Portable fire extinguishers (All types including large capacity wheeled and trolley mounted extinguishers)
107
SECE Sub System:
M10.1_F1 Portable fire fighting Provide reference Safety studies making Provide reference Operational assurance is Provide reference
equipment meets to: recommendations with respect to: provided by routine inspection to:
applicable standards to required number, type and and function checks, carried out
Fire and Safety GS EP EXP
and is located as per location of extinguishers have in accordance with relevant
Explosion Equipment 311
Table 1. been reviewed. These reviews work instruction at frequencies
Risk Analysis Layout GSP EP EXP
have been used to specify the scheduled in as scheduled in
Note: (FERA) Drawings. 213
design, number and location of the asset maintenance
Specification Fire and Asset
Applicable standards extinguishers which are management system.
for Explosion Risk Inspection
each extinguisher must presented in Table 1.
Miscellaneou Analysis (FERA) Changes to the system are in and
conform to is
s Safety A review of the asset Safety Specification accordance with the Total Maintenance
presented in Table 1.
Equipment. Equipment Layout Drawings for change control procedure. Management
Unless an alternative CAP 437: and has been undertaken to Miscellaneous System
standard or regulation Offshore ensure the location and number Safety Total Change
can be justified, fire Helicopter of extinguishers detailed in Equipment. Control
extinguishers meet the Landing Table 1 are suitable. CAP 437: Procedure.
requirements of BS Areas – Offshore
Documented confirmation by
5306 and CAP 437 Guidance on Helicopter
(where applicable). suitably competent technical
Standards. Landing Areas
BS 5306 authority that extinguisher – Guidance on
specification and manufacture Standards.
complies with the relevant BS 5306.
design codes, company TA report
standards and statutory confirming
regulations. compliance
with codes,
Procurement and QA standards and
procedures ensure original statutory
equipment and components regulations.
108
SECE Sub System:
M10_A1 Multiple independent Provide reference Initial assurance is provided by Provide reference Ongoing suitability is addressed Provide
units and diverse to: means of specification, design, to: within the scope of the risk reference to:
locations supported by construction and assessment in support of the
Active Fire TA report Total
appropriate commissioning in compliance Safety Case / COMAH and
Protection confirming Change
maintenance strategy with the relevant international updates of supporting studies.
philosophy compliance Control
should be provided to design codes, company general
109
SECE Sub System:
ensure that sufficient specifications and statutory with codes, Changes to the system are in Procedure –
extinguishers are regulations. standards and accordance with the Total Asset safety
available at all times statutory change control procedure. case /
Portable Extinguishers are sited
and function on regulations. COMAH
at locations as shown in Safety
demand. Affiliate / Asset Report.
Equipment layout drawings,
Procurement Relevant
which are agreed with the
and QA supporting
necessary TAs
Procedure. safety
Design reviews, approvals and studies e.g.
the associated QA/QC EERA, FEA,
processes completed during the and QRA.
engineering phase of the Asset
EPC provide the primary
assurance activity that the type
selection, number and location
of portable extinguishers is fit
for purpose.
110
SECE Sub System:
M10.1_S1 Protection from all - Various safety studies assess Provide references Ongoing suitability is addressed Provide
major accidents the potential impairment of to the: within the scope of the risk reference to:
provided by location safety equipment during MAHs assessment in support of the
MAH analysis Total
and provision of and make recommendations Safety Case / COMAH and
documentation Change
multiple independent with respect to protection updates of supporting studies.
Asset Safety Control
units. strategy including achievement
Philosophy. Changes to the system are in Procedure
of this through design location,
accordance with the Total Asset safety
redundancy and diversity in
change control procedure. case /
equipment.
COMAH.
The location of extinguishers Relevant
has been reviewed. The review supporting
has confirmed that the safety
equipment is, so far as is studies e.g.
reasonably practicable, EERA, FEA,
positioned and/or protected to and QRA.
survive MAHs.
M10_V1 Review any changes made to the asset which could M10 - All
affect the type, number or location of fire
extinguishers since the last operational verification
visit.
111
OPERATIONAL VERIFICATION VSEL 3
M10_V2 Confirm that all standard work text instructions have M10 - All
scheduled within the maintenance management
system have been completed as scheduled.
112
Table 1 – Extinguisher Details
HOLD – Asset specific HOLD – Asset specific HOLD – Asset specific HOLD – Asset specific HOLD – Asset specific HOLD – Asset specific
details to be details to be incorporated. details to be details to be details to be details to be
incorporated. incorporated. incorporated. incorporated. incorporated.
e.g. Portable Fire
e.g. Dry powder Extinguishers. e.g. 50 e.g. Weather deck e.g. 2 e.g. BS 5306
HOLD – Asset specific HOLD – Asset specific HOLD – Asset specific HOLD – Asset specific HOLD – Asset specific HOLD – Asset specific
details to be details to be incorporated. details to be details to be details to be details to be
incorporated. incorporated. incorporated. incorporated. incorporated.
e.g. Portable Fire
e.g. water Extinguishers. e.g. 100 e.g. Mezzanine deck e.g. 1 e.g. BS 5306
HOLD – Asset specific HOLD – Asset specific HOLD – Asset specific HOLD – Asset specific HOLD – Asset specific HOLD – Asset specific
details to be details to be incorporated. details to be details to be details to be details to be
incorporated. incorporated. incorporated. incorporated. incorporated.
e.g. Trolley Mounted
e.g. CO2 Extinguishers. e.g. 50 e.g. Cellar deck e.g. 1 e.g. BS 5306
HOLD – Asset specific HOLD – Asset specific HOLD – Asset specific HOLD – Asset specific HOLD – Asset specific HOLD – Asset specific
details to be details to be incorporated. details to be details to be details to be details to be
incorporated. incorporated. incorporated. incorporated. incorporated.
e.g. Large Capacity
e.g. Foam Wheeled Extinguishers. e.g. 200 e.g. Helideck e.g. 1 e.g. CAP 437 / BS 5306
HOLD – Asset specific HOLD – Asset specific HOLD – Asset specific HOLD – Asset specific HOLD – Asset specific HOLD – Asset specific
details to be details to be incorporated. details to be details to be details to be details to be
incorporated. incorporated. incorporated. incorporated. incorporated.
113
SECE Number: M11 SECE: - Collision Mitigation Revision: Draft Rev B1 Date: 15/06/2017
Goal:
Minimize structure damage in the event of a collision
Scope / Equipment
M11.1 Fenders
Scope
Collision protection structures (HOLD – Insert collision protection structures for asset e.g. Berthing Aids, Kinetic Energy Impact Protection)
Notes
P1 Structural Integrity
C5 Riser ESDVs
114
M11.1 SECE Sub System: Collision Avoidance Systems
M.11.1 F1 Physical barriers are - Reasonably foreseeable kinetic Provide reference Operational assurance is Provide reference
provided in specified energy impacts with MAH to: provided by routine to:
locations to prevent MAH potential are identified during inspections, carried out in
Project HAZID. GS EP EXP
incidents caused by kinetic the asset HAZID assessments. accordance with relevant work
Physical
energy impacts. instruction at frequencies 311 Plant
The physical barrier basis of barrier basis of
scheduled in as scheduled in Integrity
design have been reviewed design.
the asset maintenance Minimum
and compared with the Plot plan/s
management system. Inspection
reasonable foreseeable showing the
vehicular incident kinetic location of Requirement
energies. physical s
The review confirmed that the barriers. GSP EP EXP
physical barriers are suitable
213
and sufficient to mitigate the
effects of kinetic impacts. Minimum
Maintenance
Requirement
s
Asset
Inspection
and
Maintenance
Managemen
t System
Total Change
Control
Procedure.
115
M11.1 SECE Sub System:
116
OPERATIONAL VERIFICATION VSEL 3
117