S.P. Mechanical Engineering Co.
,Ltd
ID Task Task Name Duration Start Finish February 2022
Mode 13 15 17 19 21 23 25 27 29 31 02 04 06 08
1 20 days 15‐01‐22 03‐02‐22
4600‐U1‐F1 Remove and Reintall Refractory
2 Mobilization of tool, equipment
3 Election scaffolding 1 day 15‐01‐22 15‐01‐22
4 Demolishing existing refractory lining 4 days 16‐01‐22 19‐01‐22
5 Remove existing and Welding new anchor 2 days 20‐01‐22 21‐01‐22
6 1 st layer Installation of new refractory (Gunning) 2 days 22‐01‐22 23‐01‐22
7 2 nd layer Installation of new refractory (Casting) 10 days 24‐01‐22 02‐02‐22
8 Finalinspection and remove scaffolding 1 day 03‐02‐22 03‐02‐22
Task Inactive Task Manual Summary Rollup External Milestone
Split Inactive Milestone Manual Summary Deadline
Project: Schedule work.
Milestone Inactive Summary Start-only Progress
Date: 13-09-21
Summary Manual Task Finish-only Manual Progress
Project Summary Duration-only External Tasks
Page 1