Refractory Removal and Installation Schedule

The document outlines a project plan to remove and reinstall refractory lining over 20 days from January 15th to February 3rd. It involves mobilizing equipment, erecting scaffolding, demolishing the existing lining over 4 days, removing and welding anchors over 2 days, installing new refractory in two layers over 12 days, and a final inspection before removing scaffolding.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
68 views1 page

Refractory Removal and Installation Schedule

The document outlines a project plan to remove and reinstall refractory lining over 20 days from January 15th to February 3rd. It involves mobilizing equipment, erecting scaffolding, demolishing the existing lining over 4 days, removing and welding anchors over 2 days, installing new refractory in two layers over 12 days, and a final inspection before removing scaffolding.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

S.P. Mechanical Engineering Co.

,Ltd
ID Task Task Name Duration Start Finish February 2022
Mode 13 15 17 19 21 23 25 27 29 31 02 04 06 08
1 20 days 15‐01‐22 03‐02‐22
4600‐U1‐F1 Remove and Reintall Refractory

2 Mobilization of tool, equipment      
3 Election scaffolding 1 day 15‐01‐22 15‐01‐22
4 Demolishing existing refractory lining  4 days 16‐01‐22 19‐01‐22
5 Remove existing and Welding new anchor 2 days 20‐01‐22 21‐01‐22
6 1 st layer Installation of new refractory (Gunning) 2 days 22‐01‐22 23‐01‐22
7 2 nd layer Installation of new refractory (Casting) 10 days 24‐01‐22 02‐02‐22
8 Finalinspection and remove  scaffolding 1 day 03‐02‐22 03‐02‐22

Task Inactive Task Manual Summary Rollup External Milestone

Split Inactive Milestone Manual Summary Deadline


Project: Schedule work.
Milestone Inactive Summary Start-only Progress
Date: 13-09-21
Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Page 1