Telecom Site Construction Progress Report

The document appears to be a status report for telecommunications tower projects in the Southwestern region (SWR). It includes project details like site IDs, locations, tower details, and status updates on phases of the projects such as excavation, foundation work, tower erection and electrical work. The status is reported against timelines/baselines with actual completion dates for each phase.

Uploaded by

Yeshitila
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
56 views25 pages

Telecom Site Construction Progress Report

The document appears to be a status report for telecommunications tower projects in the Southwestern region (SWR). It includes project details like site IDs, locations, tower details, and status updates on phases of the projects such as excavation, foundation work, tower erection and electrical work. The status is reported against timelines/baselines with actual completion dates for each phase.

Uploaded by

Yeshitila
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

Tower Actual

Site ID Site ID Batch Region City Tower Designed Longtitud Actual DG Type
Height Type e Latitude

244008 244008 SWR

244017 244017 SWR

244009 244009 SWR

244006 244006 SWR

244015 244015 SWR

233527 233527 SWR

233532 233532 SWR

244285 244285 SWR

244175 244175 SWR

244042 244042 SWR

244256 244256 SWR

233539 233539 SWR

233698 233698 SWR

244010 244010 SWR

233697 233697 SWR

233699 233699 SWR

244174 244174 SWR

244178 244178 SWR

244185 244185 SWR

244172 244172 SWR

244203 244203 SWR

244149 244149 SWR

244280 244280 SWR


244268 244268 SWR

244286 244286 SWR


Final Total
Tower Telecom Config
Availabilit Shipment Availabilit PO BTS Type Solar Type E/// SE E/// SE E/// SE ID
y y Number Name Cell Phone
Final Total
Config
CW SBC Tower Tower 1.2.1 E/// Approve LLD
CW SBC CW SBC TL Cell Tower SBC TL SBC TL
Name TL Name Phone SBC Name Name Cell Phone
baseline plan actual remark
1.2.2 LLD Submit to ET 1.2.4 ET Approve CW DD 2.1.0 Site Handover to ET Sub-con

baseline plan actual remark baseline plan actual remark baseline plan
Site Handover to ET Sub-con 2.1.1 Kick off Meeting with ET Sub-con 2.1.2 Excavation Start

actual remark baseline plan actual remark baseline plan actual remark
2.1.5 Column Formwork, Template and H
2.1.3 Excavation Finish 2.1.4 Pad formwork and rebar installation installation

baseline plan actual remark baseline plan actual remark baseline plan
mn Formwork, Template and HDB
installation 2.1.6 Tower Foundation Concrete Casting 2.1.7 Tower Column Concrete Casting Done

actual remark baseline plan actual remark baseline plan actual remark
9.2.4 Bolts & Washer Handover to pro/s
2.1.8 Tower Foundation Curing 2.1.9 Hammer Test Passed CON

baseline plan actual remark baseline plan actual remark baseline plan
s & Washer Handover to pro/sub 2.2.0 Lader shoes done(vertical and
CON horizental) 2.2.1 Backfilling

actual remark baseline plan actual remark baseline plan actual remark
2.2.2. Site Handover for tower erection done 2.2.2 Generator Foundation Finish 2.2.3 BTS Foundation

baseline plan actual remark plan baseline plan actual remark baseline
2.2.3 BTS Foundation Finish 2.2.4 PVC Pipe Ready 2.2.9 Solar Foundation Finish

plan actual remark baseline plan actual remark baseline plan actual
undation Finish 9.1.1 Tower Inspection at Site done 9.1.2 Tower Outbound done

remark baseline plan actual remark baseline plan actual remark

10/08/15 9/8/2015
10/08/15 9/8/2015
CIT tower
09/08/15 09/08/15
09/08/15 09/08/15
01/09/15 30/08/15
27/08/15 26/08/15
9/8/2015
15/08/15 13/08/15
14/08/15 13/08/15
10/08/15 9/8/2015
07/09/15 05/09/15
25/08/15 25/08/15
CIT tower

13/10/15 11/10/15
14/10/15 11/10/15
25/10/15 11/10/15
09/11/15 07/11/15
08/10/15 06/10/15
10/10/15 09/10/15
9.1.3 Tower MoS done 3.1.4 Earthing Material MoS done 3.1.4 Earthing System

baseline plan actual remark baseline plan actual remark baseline

10/08/15 10/08/15
10/08/15 10/08/15

09/08/15
09/08/15
01/09/15
27/08/15

15/08/15 28/10/15
14/08/15
10/08/15 10/08/15
07/09/15 07/09/15
25/08/15 25/08/15

13/10/15 13/10/15
13/10/15 13/10/15
25/10/15 25/10/15
09/11/15 11/11/2015
08/10/15 6/11/2015
10/10/15
3.1.4 Earthing System Finish 9.1.2 securty guarde 3.1.0 Tower Erection Start

plan actual remark baseline plan actual remark baseline plan

31/10/15 05/08/15
29/10/15
20/09/15

28/10/15
29/10/15
31/10/15
12/11/15 06/11/15 9/11/2015
08/11/15
2.2.6 Ladder and Cable Tray Foundation
3.1.0 Tower Erection Start 3.1.1 Tower Erection Complete Done

actual remark baseline plan actual remark baseline plan actual

11/08/15 14/08/15
15/08/15 20/08/15

09/08/15 11/08/15
09/08/15 12/08/15
01/09/15 04/09/15
27/08/15 31/08/15

15/08/15 20/10/15
14/08/15 18/08/15
10/08/15 12/08/15
07/09/15 10/11/15
25/08/15 29/08/15

13/10/15 17/10/15
14/10/15 20/10/15
25/10/15 28/10/15
11/11/15
09/10/15 13/10/15
10/10/15 13/10/15
able Tray Foundation
one 2.2.7 Site Fence Done 2.2.8 Site Leveling Done 3.2.0 CW Done

remark baseline plan actual remark baseline plan actual remark baseline
3.2.0 CW Done 3.1.2 Tower Erection Self Check by Sub-con 3.1.3 Tower Erection Self Check by SUB CON

plan actual remark baseline plan actual remark baseline plan actual
Self Check by SUB CON 8.1.0 Tower ICR 8.2.0 Tower PAT

remark baseline plan actual remark baseline plan actual remark

11/10/15 11/10/15
11/10/15 11/10/15

12/10/15 12/10/15
12/10/15

08/10/15 08/10/15
29/10/15 29/10/15

08/10/15 08/10/15

28/10/15 28/10/15

10/11/15
09/11/15
08/11/15
12/11/15

10/11/2015 10/11/2015
bus bar installed (DG and Equipment ) 1.3.2 Transformer Installation 1.3.3 Power meter Installa

baseline plan actual remark baseline plan

23/9/15
23/9/15
23/9/15
23/9/15
23/9/15
21/9/15
24/9/15
16/9/15
07/10/15
01/11/15
17/9/15
21/10/15
22/10/15
09/10/15
23/10/15
24/10/15
28/9/15
28/9/15
28/9/15
16/9/15
22/10/15
24/10/15
24/10/15
24/10/15
24/10/15 8/11/2015
1.3.3 Power meter Installation 1.3.4 Cabling 1.3.5 Power E2E

actual remark baseline plan actual remark baseline plan

09/10/15
07/10/15
08/10/15
08/10/15
08/10/15
22/10/15
21/10/15
22/9/15
07/10/15
29/10/15
17/9/15
21/10/15
23/10/15
09/10/15
24/10/15
25/10/15
02/10/15
02/10/15
02/10/15
07/10/15
23/10/15
24/10/15
24/10/15

24/10/15
1.3.5 Power E2E 3.2.1 Sign RFI Checklist 3

actual remark baseline plan actual remark baseline plan

09/10/15 20/10/15
07/10/15 20/10/15
08/10/15
08/10/15 20/10/15
08/10/15
22/10/15
21/10/15
22/09/15
07/10/15
29/10/15 20/10/15
17/9/15
21/10/15
23/10/15
09/10/15
24/10/15
25/10/15
02/10/15
02/10/15
02/10/15
07/10/15
23/10/15
24/10/15
24/10/15

24/10/15
3.2.2 RFI

actual remark

The tower type is CIT so there is no plan to outbound

Some tower membere damage need replacement

The tower type is CIT so there is no plan to outbound

PO not initiated
PO not initiated
PO not initiated