MASTER IN PROJECT
MANAGEMENT FINAL MASTER
THESIS
HEALTHCARE CENTER: ALDEA EL ROSARIO
AUTHORS:
Thomas Filippa
Mohamad Mroue
Jisil Rishmawi
Group 12
Tutor:
Prof. Manuel Merchan
Madrid,
Spain June
2019
Abstract
The healthcare system in Honduras is struggling to provide medical assistance to citizens in
rural areas. Therefore, JMT International has developed a construction project to build a
Healthcare Centre in Aldea el Rosario, since this village needs several health treatments.
The clinic will positively impact the lives of approximately 4,200 people, both in El Rosario and
nearby villages such as: Santo Domingo, La Union Otuta and Agua Caliente.
The essence of this project is managing, constructing and delivering the health Centre within the
constraints set. The project will have a duration of 1 year starting from the approval to the
delivery of the healthcare center with a budget cost of $ 1,031,866.
It will be sponsored by USAID, JICA, Government and Rotary International. It will offer
primary medical services such as: general medicine, X-Ray services, obstetric, respiratory
emergency and pharmacy that can be accessed at any time needed
Table of Contents
1. Project Charter: Construction Healthcare Center Aldea El Rosario..........................6
2. Business Case: Construction of a Healthcare Center- Aldea El Rosario...................7
2.1. Purpose, Methodology and Structure of the Business Case Document.........................7
2.1.1 Purpose of the Business Case...............................................................................7
2.1.2 Methodology.........................................................................................................7
2.1.3 Structure...............................................................................................................8
2.2 Description of the Business Context.............................................................................8
2.2.1 Health Sector Analysis.........................................................................................8
2.3 Requester and Project Request...................................................................................10
2.4 Business Needs...........................................................................................................11
2.5 Strategic Context........................................................................................................12
2.6 Values.........................................................................................................................12
2.7 Strategic Objectives....................................................................................................12
2.7.1 Financial Objectives...........................................................................................13
2.7.2 Operational Objectives.......................................................................................13
2.7.3 People / Learning Objectives.............................................................................13
2.8 Identification and Analysis of Main Stakeholders......................................................14
2.9 Diagnosis of the AS-IS model....................................................................................15
2.10 Definition of TO-BE Model.......................................................................................15
2.11 Smart Objectives........................................................................................................16
2.12 High Level Requirements...........................................................................................17
2.13 Multicriteria Comparative Analysis of Options or Alternatives..................................18
2.14 Selection and Description of Optimal Solution...........................................................19
2.15 Master Schedule.........................................................................................................19
2.16 Master Gross Budget..................................................................................................21
2.17 Risk Identification and Assessment............................................................................22
2.18 Definition of Indicators, Measurement Systems, Targets and Control........................26
2.19 Conclusions................................................................................................................28
3. Scope Management Plan..........................................................................................29
3.1 Introduction, Scope and Purpose................................................................................29
3.2 Requirement Traceability Matrix................................................................................30
3.3 Product Scope Description.........................................................................................31
3.4 Work Breakdown Structure........................................................................................35
3.5 WBS Dictionary.........................................................................................................37
3.6 Monitoring and Controlling........................................................................................52
4 Schedule Management Plan.....................................................................................53
4.1 Introduction, Scope and Purpose of the Plan..............................................................53
4.2 Key dates and Milestones...........................................................................................53
4.3 Activity List................................................................................................................54
4.4 Project Schedule.........................................................................................................58
4.5 Control Schedule........................................................................................................63
4.6 Critical Path................................................................................................................64
5 Cost Management Plan............................................................................................68
5.1 Introduction, Objectives and Scope............................................................................68
5.2 Plan Cost Management...............................................................................................69
5.3 Risks Costs Identification...........................................................................................70
5.4 Cost Estimations.........................................................................................................72
5.5 Cost Estimates............................................................................................................72
5.6 Estimate costs: Tools & Techniques...........................................................................73
5.7 Summary of the cost key requirements.......................................................................74
5.8 Project Budget............................................................................................................75
5.9 Control Cost...............................................................................................................83
5.10 Control Costs: Tools and Techniques.........................................................................84
6 Quality Management Plan........................................................................................85
6.1 Introduction, Scope and Purpose of the Quality Management Plan............................85
6.2 Quality Policies..........................................................................................................86
6.4 Quality Responsibilities..............................................................................................88
6.5 Manage Quality..........................................................................................................92
6.6 Quality Control Template...........................................................................................92
6.7 Data Analysis – Decision Making............................................................................94
6.8 Procedures.................................................................................................................95
6.9 Control Quality.........................................................................................................97
6.9.1 Inspection Requests..........................................................................................97
6.9.2 Minutes of Meeting...........................................................................................97
6.10 Safety Permits...........................................................................................................98
6.11 Survey........................................................................................................................99
7 Risk Management Plan........................................................................................101
7.1 Introduction, Scope and Purpose Risk Management Plan..................................101
7.2 Identification of Project Risks...............................................................................102
7.3 Qualitative Risk Analysis.......................................................................................103
7.4 Roles and Responsibilities......................................................................................103
7.5 Probability and Impact Analysis...........................................................................104
7.6 Response To Risks..................................................................................................105
7.7 Monitor Risks.........................................................................................................106
7.8 Risk Matrix.............................................................................................................107
8 Stakeholder Management Plan...........................................................................109
8.1 Introduction, Scope and Purpose of the Plan.......................................................109
8.2 Identify Stakeholders.............................................................................................109
8.3 Plan Stakeholder Engagement...............................................................................115
8.4 Monitor and Control..............................................................................................116
8.5 Incident Register.....................................................................................................119
9 Communication Management Plan....................................................................120
9.1 Intro, objective and scope of the communications plan,......................................120
9.2 Stakeholder Identification and Communication Needs.......................................121
9.3 Communication Matrix..........................................................................................126
9.4 Complaint Flowchart.............................................................................................128
9.5 Communication Process.........................................................................................128
9.6 Monitoring and control..........................................................................................131
10 Procurement Management Plan.....................................................................132
10.1 Introduction, Scope and Purpose of the Plan.......................................................132
10.2 Types of Contract...................................................................................................133
10.3 Make / Buy Analysis...............................................................................................133
10.4 Criteria for Supplier Selection and Evaluation of Offers....................................134
10.4.1 Vendor Selection.............................................................................................134
10.5 Offer / Proposal Assessment Matrix......................................................................136
10.6 Monitoring and Control Audit..............................................................................137
10.6.1 Deliverable template.......................................................................................137
10.6.2 Closure.............................................................................................................138
11 Change Management Plan...............................................................................139
11.1 Intro, Scope and Objectives Change Management Plan......................................139
11.2 Change Management Plan.....................................................................................140
11.3 Change Control Committee organization.............................................................142
11.4 Change Request Flowchart....................................................................................143
11.5 Process of assessing change requests.....................................................................144
12. Conclusions.......................................................................................................145
13. References.........................................................................................................146
Index of Tables
Table 1: High Level Requirements....................................................................................3
Table 2: Project Cost.........................................................................................................4
Table 3: Project Request..................................................................................................10
Table 4: Stakeholder Identification.................................................................................14
Table 5: Smart Objectives...............................................................................................16
Table 6: High Level Requirements..................................................................................17
Table 7: Multicriteria Comparative Analysis of Alternatives.........................................18
Table 8: Master Schedule................................................................................................19
Table 9: Master Gross Budget.........................................................................................21
Table 10: Risk Identification...........................................................................................23
Table 11: Risk Matrix......................................................................................................24
Table 12: Explanation of Risk Ranking..........................................................................25
Table 13: KPI´s Measures...............................................................................................26
Table 14: Requirement Traceability Matrix....................................................................30
Table 15: WBS Dictionary..............................................................................................37
Table 16: Milestones.......................................................................................................54
Table 17: Activity List.....................................................................................................54
Table 18: Risk Cost Identification...................................................................................71
Table 19: Cost Key Requirements...................................................................................74
Table 20: Budget Description..........................................................................................76
Table 21: Sponsors Contribution.....................................................................................77
Table 22: Direct and Indirect Manpower Budget............................................................78
Table 23: Running Costs.................................................................................................80
Table 24: Equipment Costs.............................................................................................81
Table 25: Activity Costs..................................................................................................81
Table 26: Roles and Responsibilities..............................................................................89
Table 28: Stakeholder Register.....................................................................................110
Table 29: Stakeholder Engagement...............................................................................117
Index of Figures
Figure 1: Master Schedule...............................................................................................20
Figure 2: Architectural Design Layout............................................................................32
Figure 3: Work-Breakdown Structire (WBS)..................................................................36
Figure 4: Project Schedule A...........................................................................................59
Figure 5: Project Schedule B...........................................................................................60
Figure 6: Project Schedule C...........................................................................................61
Figure 7: Project Schedule D...........................................................................................62
Figure 8: Critical Path A..................................................................................................65
Figure 9: Critical Path B..................................................................................................66
Figure 10: Critical Path C................................................................................................67
Figure 11: Indirect and Direct Staff.................................................................................79
Figure 12: Histogram Equipment vs Time......................................................................80
Figure 13: Organizational Chart......................................................................................91
Figure 14: Inspection Request.........................................................................................93
Figure 15: Ishikawa Diagram..........................................................................................95
Figure 16: Change Request Flowchart............................................................................96
Figure 17: Minute Meeting..............................................................................................97
Figure 18: Safety Permits................................................................................................99
Figure 19: Survey..........................................................................................................100
Figure 20: Stakeholder Engagement.............................................................................115
Figure 21: Incident Register..........................................................................................119
Figure 22: Complaint Flowchart...................................................................................128
Figure 23: Deliverables Template.................................................................................137
Figure 24: Closure Flowchart........................................................................................138
Figure 25: Change Request Template...........................................................................140
Figure 26: Change Request CCB Approval of Changes...............................................142
Figure 27: Change Request Flowchart..........................................................................143
1. Project Charter: Construction Healthcare Center Aldea El Rosario
Project Title: Construction Healthcare Center Aldea El Rosario
Date: December 12th, 2018
Project Sponsor:
The following were identified for the funding for the project,
USAID - United States Agency for International Development
JICA - Japan International Cooperation Agency
Honduran Government
Rotary International
Project Client:
The project´s clients after completion are going to be the Municipality of Santa Rita de
Copán.
Project Justification:
The objective of the project is to provide health care services to the remote community
of Aldea El Rosario – Honduras. The citizens have experienced health care shortage due
to the absence of public facilities in the rural areas, as it takes up to two hours to reach
the closest clinic/hospital by walking distance, since none of the people in El Rosario
has access to transport.
In the Honduran National Health Plan 2021 (2005) states:
The National Institute of Statistics (INE) of Honduras in a projection estimated
that in 2015 the population would be 7,028,389 inhabitants. Of this population,
it is estimated that the network of services of the Ministry of health covers 60%,
The Social Security Institute covers 18%, a 5% the private sector, and the
remaining 17% or 1,194,826 habitants, has no access to any health service.(p.30)
1
Project Description
The healthcare in Honduras is very deficient as there is no medical healthcare accessible
to all areas of the country. Due to this problem, the decision to build a health center
will help the citizens to have a closer medical assistance whenever they need it. It will
be located in rural community in El Rosario, Santa Rita de Copan that can be accessed
by children, women, men and senior citizens, some of the characteristics that the health
center will include are:
a) Offer an outpatient medical care in which will include:
Diagnosis
Observation
Consultation
Treatment
Intervention
- It will include services of:
General Medicine
Obstetric
Respiratory
Emergency
High Level Requirements:
The high level requirements that will be needed for the project are specified on Table 1.
Table 1: High Level Requirements
Activity Requirements
Construction Permits - Land use license
- INSEP permit
- Environmental standard according to ISO
- ACI Code
Working execution - Comply with Health and Safety regulations
- Safety officer
- Employees’ insurance
Source: The authors
High Level Risks:
- Safety hazards that lead to worker accidents and injuries
- Unknown site conditions
- Labor shortages, as it might be difficult to find good workers in that rural
area
- Damage or theft of equipment and tools – Since 2010, Honduras has had one
of the highest murder rates in the world.
- Natural disasters and weather unpredicted changes
Project Scope:
The deliverables that are going to be presented along the entire project will be:
Engineering report
Proposal
Design drawings
Design documents
Completed product (building)
Technical interpretation
Site investigation report
Design review
New equipment or tools
Service report
Strategic report
Progress report
Medical Clinic
Landscape
Project Cost:
After analyzing all the activities, the proposed budget for the project is shown in table 2.
Table 2: Project Cost
Activity Cost
Ownership of land $ 25,000
Conceptual Design $ 17,000
Construction Preparation $ 10,000
Bldg. Substructure $ 50,000
Concrete Structures $ 30,000
Parking & Landscape $ 50,000
Equipment Process & Systems $ 356,000
Start up $ 10,000
Safety / Environmental $ 20,000
Indirect Staff $ 154,500
Direct Cost $ 143,800
Food $ 13,000
Transportation $ 10,800
Miscellaneous $ 5,000
Travel Expenses $ 15,000
Contingency 10 % $ 93,806
Total Cost $ 1,031,866
Source: The authors
Project Schedule:
Total duration of the project will be of 1 year, and starting from January 1st, 2019.
Table 3: Project Schedule
Activity Description Start Date End Date
Design January 1, 2019 January 31, 2019
Mobilization February 1, 2019 February 21, 2019
Execution February 22, 2019 March 14, 2019
UG Utilities March 15, 2019 April 9, 2019
Raft Foundation April 10, 2019 May 10, 2019
Backfill & Compaction May 11, 2019 May 26, 2019
Slab On Grade May 27, 2019 June 16, 2019
Column June 17, 2019 July 1, 2019
Beams July 2, 2019 July 16, 2019
Roof Slab July 17, 2019 July 31, 2019
Brick wall August 1, 2019 August 21, 2019
Plastering August 22, 2019 September 6, 2019
Painting September 7, 2019 September 27, 2019
Plumbing July 6, 2019 August 5, 2019
Electricity July 26, 2019 August 25, 2019
Tiling October 1, 2019 October 26, 2019
HVAC August 1, 2019 August 26, 2019
False Ceiling August 27, 2019 September 26, 2019
Lighting September 27, 2020 October 7, 2020
Roof Works & Solar November 1, 2019 November 16, 2019
Panel
Equipment Installation November 17, 2019 November 27, 2019
Testing, November 28, 2020 December 18, 2020
Commissioning &
Delivery
Source: The authors
Main stakeholders of the project:
- Medical employees
- People living in Aldea El Rosario
- Health Ministry
- Construction Firm
- Project Sponsors (Government, JICA, USAID and Rotary International)
Approval:
Sponsor Project Manager
2. Business Case: Construction of a Healthcare Center- Aldea El Rosario
2.1. Purpose, Methodology and Structure of the Business Case Document
2.1.1 Purpose of the Business Case
The purpose of this project is to help the locals in Aldea El Rosario in their struggle to
have an accessible medical facility. Currently, there are no available healthcare services
and families have to travel to another town for assistance. The situation was reported
then Health Ministry but due to several problems they could not provide a solution. Our
project is to build a clinic to provide fast and high quality health assistance to all the
residents of the village.
2.1.2 Methodology
The methodology in this project is going to take a Waterfall Methodology, being that
all the planning must be done at the initial part of the project due to the construction, it
follows a sequential guideline to plan, construct, test, and implement and there is no
room for big changes.
It is divided into the phases:
1. Gather Requirements needs and provide a solution
2. The design specifications are created and evaluated on how the final result is
going to look like
3. After the design is approved and, the implementation or construction starts
4. Testing - Once the construction has been finished, the final tests for delivery.
5. Delivery - The product is when the deliverables are made and submitted by the
team
2.1.3 Structure
The structure of this business case will consist in several stages consisting:
a) Definition of the case: First we describe the current situation in the health sector
in Honduras, to analyze the business needs and the project ticket request.
b) Definition of the strategic plan in how the project will operate which will help us
to meet the business needs
c) Identification o and description of stakeholders
d) Definition of the triple constraint, the project cost, schedule and scope are
defined
e) Analysis of alternatives solutions
f) Risks analysis
2.2 Description of the Business Context
2.2.1 Health Sector Analysis
To understand the purpose of the needs of building a healthcare center in Aldea El
Rosario, we are going describe the health system in Honduras and how does that impact
all the citizens around the country.
As described by (Herrera-Ramos, 2016),
The health sector consists of two subsectors. A public sub sector composed by
the Ministry of health (signal) corresponds to which the controller, guiding role
and provision of health services to the entire Honduran population and the
Honduran Institute of Social Security (IHSS) charge collect, manage fiscal
resources and compulsory contributions from workers and employers.
In the Honduran National Health Plan 2021 (2005) states:
The National Institute of Statistics (INE) of Honduras in a projection estimated
that in 2015 the population would be 7,028,389 inhabitants. Of this population,
it is estimated that the network of services of the Ministry of health covers 60%,
The Social Security Institute covers 18%, a 5% the private sector, and the
remaining 17% or 1,194,826 habitants, has no access to any health service.
(p.30)
In rural areas, especially in areas with a high percentage of indigenous population,
there are challenges in the provision of basic health services to residents. Additionally,
it is necessary to improve the percentage of delivery of health services, some of the
most common health problems in the rural areas that are found are “infectious diseases,
diarrhea, adolescent pregnancy, chronic and respiratory diseases are also health
problems in rural areas” (JICA, 2014).
The health system in Honduras is going difficulties on its capacity to provide all citizen
with medication, resources and access to health this problems evidence in different
aspects according to ( Centro National de Information de Ciencias Médicas. Biblioteca
Médica, 2017),
- The fragmentation of the health system, without control over the coverage
and without dimensioning how much of the fundamental efforts are being made
to incorporate the poorest to the Health services,
- The administration of human resources with rigidities that make it difficult to
streamline management to increase their productivity, without defining the different
types and amounts of resources needed to promote the service model, without the ability
to change the methods of recruitment, hiring and remuneration in force and to interlink
the recognition of individual performance with the institutional one and finally
condition the entry into the system to competitions;
- The unequal health financing, since an important part of the expenditure is
contributed by the households and of them, the poorest suffer greater financial risk since
the direct payment to obtain health services comes from their pockets.
2.3 Requester and Project Request
The project request descriptions are shown in table 3.
Table 3: Project Request
Name and Title of Requester Non- Profit Organization -
TMJ International Organization
Description of Request Provide Medical services
Description of Problem In Honduras, there is a deficiency of providing
healthcare in rural areas, which results in a high
percentage of illness in the population. There is
no immediate access to medicines.
Ideas for Solution Construction of Healthcare Center
Medical Brigades
Provide transportation weekly to nearest clinic
Reason of the Request No medical accessibility in Aldea El Rosario
Date Requested 12th December 2018
Source: The authors
2.4 Business Needs
Being Honduras a third world country, it is difficult to the health system to provide
all citizens with medication, resources and access to health, especially in the rural
areas. (Lino Carmenate-Milián, 2016) Explains the coverage on medical attention in
Honduras:
In 2015, there were 10,995 registered doctors. In terms of health personnel, it is
estimated that there are 10.1 doctors per 10,000. Data by departments showed
that Francisco Morazán had 23.8 doctors per 10,000 inhabitants while Lempira
and Santa Barbara each had 2 doctors per 10,000 inhabitants. None of the 18
departments meet the minimum indicator of 25 physicians per 10,000 inhabitants
as indicated by the regional human resources target and in contracting with the
average of the region of the Americas there is an unequal gap (20.8 physicians
Per 10,000).
Aldea El Rosario is located on Santa Rita in the department of Copan with an area of
314 km² and with a population of 31,829 and the families do not have an immediate
access to a healthcare facility: It takes them up to three hours to the next town to have
medical assistance. Moreover, the quality of the medical service is not always
appropriate especially during emergencies that require immediate assistance. Finally,
the closest hospital to Aldea el Rosario does not have adequate equipment for the best
medical assistance or medicines.
2.5 Strategic Context
2.5.1 Mission
To provide to the locals living in Aldea El Rosario access of medical services, resources
and doctors with the construction of a Medical Healthcare Center sponsored by NGO
“TMJ International Organization” and providing the basic medical needs.
2.5.2 Vision
To improve the health condition and reduce the percentage of diseases of all the families
living in nearby villages that does not have access to medical assistance.
2.6 Values
For a successful project, the cores values in which are going to rely are:
1. Integrity: Always present a finished project to what the client is offered
2. Honesty - To have the confidence with all the stakeholders means to be
truthful with them
3. Efficiency: Having the proper metrics in each aspect of the project will help us
determine how effectively and efficiently our team is performing in base of the
schedule and budget.
4. Communication: By having the proper communication with the clients, team
members and stakeholders, it results in a more effective project and can manage
the client expectations.
2.7 Strategic Objectives
The construction of the healthcare center id a Strategic Project due that has long
term goals and once the project closes it is not repeated.
2.7.1 Financial Objectives
In terms of financial objectives during the project, the objectives are:
Financial Efficiency: Implementing strict financial control to terminate the
project on budget.
Ensure financial sustainability: The project will be operating in an uncertain
economic environment, inflation risks will be taken in account to make sure that
our sponsors will provide financial stability.
2.7.2 Operational Objectives
In terms of operational Objectives during the project, the operational objectives are
- Continuous Improvement of Project Management: Implementing the Project
Management Book of Knowledge (PMBOK) guidelines to meet standard of
excellence and improving to reach operational effectiveness
Communication Management: Improve internal communication processes
implementing cultural training with agile methodologies.
Reduce waste by 10% over the project life: Reducing environmental impact
during operations by using recyclable materials will be one of the objectives.
Also, we could reduce energy waste by monitoring and controlling electricity
usage.
Eco Friendly solutions: Implementing the solar panel system to reduce
operational costs.
2.7.3 People / Learning Objectives
Improve and maintain workplace safety: Comply with health and safety
regulations to maintain a zero accident vision.
Ensure compliance with local authorities: Act according to local regulations
and law.
Build high-performing teams: Build a team of professional people who can
work together productively. Cultural and language factors will be taken into
considerations.
Include participation of community: At least 51% of the population will have
an active participation in the project.
2.8 Identification and Analysis of Main Stakeholders
The stakeholders that are going to be involved through the whole project are:
Table 4: Stakeholder Identification
Main Stakeholders Role Needs
USAID Project Sponsors Completing the project on time
JICA and budget
Government
Rotary International
Health Ministry
Municipality Project Client Efficient management of the
clinic
Construction firm To construct the facility Adequate working conditions and
salaries
International NGO To plan, execute and close Funds - licenses - Professional
the project staff
Suppliers Deliver project on time Payments
and budget
Subcontractors Deliver the project on time Payments
and budget
Source: The authors
2.9 Diagnosis of the AS-IS model
The citizens have experienced health care shortage due to the absence of public
facilities in the rural areas, as it takes up to three hours to reach the closest
clinic/hospital. Thus, people in serious conditions are at more risk as there is no
immediate assistance. Moreover, the quality of the closest hospital is not as high as in
other parts of Central America. The medical clinic, in which the families have access,
can only provide medical attention to 1 or 2 persons at the same time, which makes
longer waiting times for the rest of the day.
2.10 Definition of TO-BE Model
The clinic will improve the life of local people in Aldea el Rosario and neighbor
communities. It will provide immediate medical support to patients and will be able to
treat the whole community (estimated to be 4,200 considering the growth factor of 25
years).
The clinic will offer good medical assistance due to the investment being made and it
will consist with 7 exam rooms, 1 minor procedure room and X-ray facilities, in which
will make the waiting period shorter and faster. It will also have a pharmacy which
will have a supplied storage so that there always will have a good medicine inventory
at the moment that is needed.
The clinic will offer the basic medical services such as: of general medicine, X-Ray
services, obstetric and respiratory emergency for everyone in Aldea El Rosario or
nearby communities that will need medical assistance
2.11 Smart Objectives
The Smart Objectives identified for the project are shown in table 5
Table 5: Smart Objectives
Specific Objective Measures Time to reach it
Build a medical clinic in Aldea el Documenting and gathering 1 year and 3
Rosario data during all the phases of months
the project approximately
Provide medical assistance to local Medical records of each patient Ongoing process
people (estimated to be 4,200 in 25
years)
Increase the quality of health Patients’ feedback after Ongoing process
services in Aldea el Rosario treatments / government
reports and inspections
Manage government public funds Reporting the financial Ongoing process
effectively statements directly to the
health ministry
Source: The authors
2.12 High Level Requirements
The high level requirements are presented in order to meet the project, business and
product´s need, these are shown in table 6.
Table 6: High Level Requirements
Project Requirements Business Requirements Products Requirements
Land for construction Operation License Health Standards
Construction License Medical License Medical Equipment
Suppliers Agreement Medical and disposable
Materials
Professional and
experienced Doctors and
Nurses
Table 3: High – Level Requirements
2.13 Multicriteria Comparative Analysis of Options or Alternatives
In this section consists on the evaluation of 4 different options or alternatives to resolve the business need for the lack of medical attention in
Aldea El Rosario, the options and alternatives are describe each one on table 7.
Table 7: Multicriteria Comparative Analysis of Alternatives
Option Financial Factors Environmental Factors Social Factors
Pros Cons Pros Cons Pros Cons
Construction Cost of the The cost of Does not Need of - It will provide medical care - Citizens will get
Healthcare project is construction depend on construction and to approximately 4,200 people molested during the time
Center higher and weather for environmental anytime they need of construction
equipment is the center permits - It will be accessible to
$1,159,253 to Provide other villages around El
once the services Rosario
project is - Offer services of general
done medicine, obstetric, respiratory
emergency and pharmacy at
any time needed
Organizing The cost is Costs on - Don´t In case of storms or - Provide medical care to - Waiting for 2 months
Medical lower per transport, need a natural disasters, the Aldea El Rosario for medical brigades to
Brigades into year housing and specific medical brigades will - It can be medical and reach the village
the Village food of space to have to be cancelled dentistry brigade - Only makes general
every 2 months volunteer Provide or postponed medical examinations
doctors. medical - Will only provide
$4000 per services assistance to El Rosario
year
Hiring Lower Costs on bus In case of storms or - Provide medical care only to - People have to wait
Transports costs transportation natural disasters, the the people in need for weekly for the
weekly from per year. transports will not be assistance transportation to the
the Village to $5200 able to drive through nearest clinic
the nearest the villages
health clinic
18
Source: The authors
18
2.14 Selection and Description of Optimal Solution
After analyzing the alternatives for solutions of the business needs, the Construction of
the healthcare center will have more impact on El Rosario and the nearby villages on
the health situation. Even though is going to have a higher cost at first than the other
options, it will not depend on environmental or transport problems. In the social factors,
with the Health center, the people will receive a more complete medical examination to
approximately 4,200 citizens and comparing with the medical brigades and offering
only the transportation to the nearest clinic, it will only impact around 400 people
2.15 Master Schedule
The total duration of the project will be of 1 year, and starting from January 1st,
2019. The detailed activities of the projects are shown in table 8
Table 8: Master Schedule
Activity Description Start Date End Date
Design January 1, 2019 January 31, 2019
Mobilization February 1, 2019 February 21, 2019
Execution February 22, 2019 March 14, 2019
UG Utilities March 15, 2019 April 9, 2019
Raft Foundation April 10, 2019 May 10, 2019
Backfill & Compaction May 11, 2019 May 26, 2019
Slab On Grade May 27, 2019 June 16, 2019
Column June 17, 2019 July 1, 2019
Beams July 2, 2019 July 16, 2019
Roof Slab July 17, 2019 July 31, 2019
Brick wall August 1, 2019 August 21, 2019
Plastering August 22, 2019 September 6, 2019
19
Painting September 7, 2019 September 27,
2019
Plumbing July 6, 2019 August 5, 2019
Electricity July 26, 2019 August 25, 2019
Tiling October 1, 2019 October 26, 2019
HVAC August 1, 2019 August 26, 2019
False Ceiling August 27, 2019 September 26,
2019
Lighting September 27, October 7, 2020
2020
Roof Works & Solar Panel November 1, 2019 November 16,
2019
Equipment Installation November 17, November 27,
2019 2019
Testing, Commissioning & November 28, December 18, 2020
Delivery 2020
Source: The authors
Figure 1 shows a visual representation of the time-line of the project. It will be further
elaborated in the schedule management plan through the use of MS project.
Figure 1: Master Schedule
Source: The authors
2.16 Master Gross Budget
The estimated budget for the construction of the healthcare center will be $1,135,053,
which includes all the activities involved.
Table 9: Master Gross Budget
Description Cost
Ownership of land $ 25,000
Conceptual Design $ 17,000
Construction Preparation $ 10,000
Bldg. Substructure $ 50,000
Concrete Structures $ 30,000
Parking & Landscape $ 50,000
Equipment Process & Systems $ 356,000
Start up $ 10,000
Safety / Environmental $ 20,000
Indirect Staff $ 154,500
Direct Cost $ 143,800
Food $ 13,000
Transportation $ 10,800
Miscellaneous $ 5,000
Travel Expenses $ 15,000
Contingency 10 % $ 93,806
Total Cost $ 1,031,866
Source: The authors
2.17 Risk Identification and Assessment
There were several risks identified during each phase of the project. According to
Table 10, natural disaster and health and safety issues might represent a high risk.
The risk score was found by combining the impact and the probability on the risk matrix
Below is shown the actions to mitigate these risks. The risks are detailed on the table
11, with the description for each risk on table 12.
Table 10: Risk Identification
Probability
Activities Associated Risk(s) Severity Risk Score Method(s) to Manage the Risk
Construction of the
Health and safety issues – not Strict supervision on site – make sure
clinic Critical Medium High
complying with regulations workers have insurance
Natural Disaster Damage of the equipment –
Catastrophic Low High Checking weather forecasts regularly
Delay in the schedule
Working with local
Cultural misunderstands
people Marginal Medium Medium One week cultural training
Working in a rural All medium – senior positions will be
Labor shortages – low skills workers Critical Low Medium
isolated area filled with high-profile employees.
Working in a very Damage or theft of equipment and
Marginal Low Medium Inventory control
poor area tools
Working in an Pre – investigation of the bearing
Problems during the excavation phase Critical Low Medium
unknown site capacity conditions with an expert.
Establish a contingency budget to
Economic Instability Inflation Rates Critical Medium Medium
mitigate the risk.
Source: The authors
23
Table 11: Risk Matrix
Severity
NEGLIGIBLE MARGINAL CRITICAL CATASTROPHIC
Small/unimportant Minimal importance; Serious/important; Maximum importance;
Not likely to have a Has an effect on the Will affect the operation of the Could result in disaster/death;
major effect on the operation of event but event in a negative way. WILL affect the operation of
operation of the event. will not affect the event the event in a negative way.
outcome.
LOW LOW (1) MEDIUM (4) MEDIUM (6) HIGH (10)
This risk has rarely been a
problem and never occurred
at a college event of this
nature
MEDIUM LOW (2) MEDIUM (5) HIGH (8) EXTREME (11)
This risk will MOST
LIKELY occur at this event
HIGH MEDIUM (3) HIGH (7) HIGH (9) EXTREME (12)
This risk WILL occur at
this event
Source: The authors
Table 12: Explanation of Risk Ranking
If the consequences to this event/activity
are LOW / MEDIUM, your group should
be OK to proceed with this event/activity.
LOW MEDIUM
It is advised that if the activity is
MEDIUM, risk mitigation efforts should
be made.
If the consequences to this event/activity
HIGH are HIGH, it is advised that you seek
additional event planning support.
If the consequences to this event/activity
are EXTREME, it is advised that you do
EXTREME
not hold this event without prior
consultation with Risk Management
Source: The authors
25
2.18 Definition of Indicators, Measurement Systems, Targets and Control
To understand the efficiency and productivity of the project, the following variables are taken
into account. Then to control and monitor these variables, the KPIs that will be implemented are
shown in table 13.
Table 13: KPI´s Measures
Variable to measure KPIs
Productivity of employees Number of hours to complete a task vs. Hourly salary per
employee
Overtime hours spent to complete a task
Costs Actual Cost vs. Budgeted
Cost control methodologies used by a cost engineer
CV, CPI
Verification Funds – Demonstrate how the funds are
being managed
Time Schedule plan vs. actual time plan to complete tasks –
Refer to the master schedule
Fix some milestones to understand whether there is a delay
SPI, SV
Quality Number of accidents on site
Number of complaints from workers
Number of complaints from local people
Number of change orders (percentage of
approved/unapproved orders)
Fatalities
QA&QC
Risk Refer to the risk matrix
Project Success Number of patients treated
How long patients wait to get medical treatment
How long does it take them to get to the clinic
Number of patients cured
Government saving in health expenditure
Source; The authors
2.19 Conclusions
The health system in Honduras is struggling to provide healthcare in all the country due
to poor management of resources and unequal financing on the health sector by the
Government. This results in insufficient medical care in the rural areas where the locals
do not have access for medical attention and medicines, which oblige them to walk a 3-
hour distance to nearest clinic.
After analyzing the solutions through multi-criteria and the relative risks of the project,
the optimal solution is to build a healthcare center In Aldea el Rosario. This will
positively impact the lives of approximately 4,200 people, both in El Rosario and the
neighbor villages such as: Santo Domingo, La Union Otuta and Agua Caliente.
The project will have duration of 1 year starting from the approval to the delivery of the
healthcare center with a budget cost of $ 1,031,866. It will be sponsored by USAID,
JICA, Government and Rotary International. It will offer primary medical services such
as: general medicine, X-Ray services, obstetric, respiratory emergency and pharmacy that
can be accessed at any time needed
3. Scope Management Plan
3.1 Introduction, Scope and Purpose
The Scope Management Plan presented on this document shows how the project and
Product scope will be defined, validated, and controlled. For the Scope Management to be
completed was needed to:
1. Define High Level Requirements: This was used in order to complete the
Requirement Traceability Matrix with the project, business and product objectives
during the whole project
2. Define Scope Statement: To have a detailed project it is needed to define the
framework in which the project work will be performed and includes all the
deliverables, assumptions and constraints of the project
3. Create WBS: The Work- Breakdown Structure was created which helps to a
better monitoring and controlling the project with its detailed work packages for
cost and scheduling every activity.
4. Creating WBS Dictionary: This will help us to have detailed information of
each deliverable and activity for each component for the WBS.
3.2 Requirement Traceability Matrix
The implementation of a requirements traceability matrix helps ensure that each requirement adds business value by linking it to the
business and project objectives. (Project Management Institute, 2017). The requirements Matrix are described in table 14.
Table 14: Requirement Traceability Matrix
Requirement Information Relationship Traceability
ID Requirement Priority Type Stakeholder Business Objective Acceptance Criteria
1. Operation License High Business Health Obtain a operation license to operate Permit Approval
Ministry, NGO
2. Land for construction High Project NGO, Sign Agreement with government with land Signed approval
Municipality territory
3 Construction License High Project NGO, Obtain construction permit to start Construction permit
Municipality construction
4 Medical License High Business NGO Obtain a medical license for the clinic Medical Permit
5 Construction Team Medium Project NGO Hire a contractor company Signed agreement
6. Health Standards High Product NGO Operate with all health requirements Health Ministry
inside the clinic approval
7. Equipment Medium Product NGO Operate will all the necessary equipment
8. Medical Materials Medium Business NGO Have all graduated and experienced personal Signed Agreement
9 Suppliers Medium Business NGO Identify medical and disposable materials Signed Agreement
10 Professional Medics Medium Business NGO Have all graduated and experienced personal Signed Agreement
and nurses
Source: The authors
30
3.3 Product Scope Description
The clinic will offer medical services to the citizens of Aldea el Rosario and neighbor villages. These
people have difficulties in getting medical treatment, as the closest medical center is located 3 hours
away. The clinic will offer diagnosis, medical consultation and treatments of disease, illness, injury and
other physical and mental impairments of patients.
The main services that we offer vary from primary care, obstetric services and emergency treatment
with immediate intervention on spot. It will consist of:
Total area Clinic : 432 m2
(2) Doctor Office
(1) X-ray facilitates
(7) Exam rooms
(1) Pharmacy
(2) Drug Supply rooms
(1) Staff Break room / Kitchen
(1) Waiting Area
(1) Business Office
(1) Laboratory
(1) Minor Procedures Rooms
(4) Bathrooms
Design Layout :
The figure 2 below represents the architectural design layout for the health care that will be executed
accordingly, based on this design we were able to quantity survey and derive the resources,
durations and estimated cost for the project further in the document.
31
Figure 2: Architectural Design Layout
Source: The Authors
Project Deliverables
The main project deliverables can be categorized in:
Project Management Documents:
Project Charter
Business Case
Scope Management Plan
Schedule Management Plan
Cost Management Plan
Quality Management Plan
Resource Management Plan
Communication Management Plan
Risk Management Plan
Procurement Management Plan
Stakeholder Engagement Plan
Design Tender
Final Design Reviewed
Final Civil Design
Final Architectural Design
Final MEP Design
Human Resources
HRMS
ISO QMS
Construction
Mobilization
Site Preparation
Soil Reports
Offices and Utilities
Excavation
Demobilize
Project Controls
Deliverables Check
Reports & Documents
Approvals
Safety
Safety Plan
Safety Documents
Inspection & Approval
Startup & Commissioning
Project Exclusions
Initially, the clinic only provide the basic medical care for the citizens, which will exclude secondary,
tertiary or quarterly medical care. However, negotiations are open for another project to expand the
clinic and include services such as surgery, psychiatrists and dietitians
Project Constraints
1. The location might represent a challenge for the mobilization.
2. Weather conditions might be adverse.
3. Time: 1 year limit
4. Cost: Max 1.200.000 dollars
Project Assumptions
1. Sponsors will deliver the funds 2 months before the beginning of the project. This will allow us
to start ordering materials and equipment as well as closing the contract with the construction
company.
2. We have the full support of the government and the municipality.
3. We meet the requirements to start a construction projects according to national regulations.
4. Approximately 4200 people per year will benefit from the project.
5. Availability of 20% of management reserve to deal with unforeseen risks.
6. Availability of 5% for contingency risks.
3.4 Work Breakdown Structure
The WBS is defined by the (Project Management Institute, 2017) as it follows:
The WBS is a hierarchical decomposition of the total scope of work to be carried out by the
project team to accomplish the project objectives and create the required deliverables. The WBS
organizes and defines the total scope of the project and represents the work specified in the
current approved project scope statement.
The Work- Breakdown Structure (WBS) is shown in figure 3, which shows a limited version, to view
the entire structure; it has been created on www.wbstool.com. In order to consult it, enter the following
credential:
Email: [email protected]
Password: 123456789
Figure 3: Work-Breakdown Structire (WBS)
Source: The authors (created in ww.wbstool.com)
36
3.5 WBS Dictionary
To understand the Work – Breakdown Structure of the project, the WBS dictionary has
been made as well, in which it “describes each component of the WBS with milestones,
deliverables, activities, scope, and sometimes dates, resources, costs, quality” (Casagrande,
2018). The WBS Dictionary can be shown in table 15
Table 15: WBS Dictionary
1 Clinic Project Description: Title - El Rosario Health Care
Duration: 360
Acceptance Criteria:
Resources: Broken down in below deliverables
1.1 Project Management Office Description: Managing project life cycle
Duration: 360
Acceptance Criteria: Performance Requirements
Resources: PMO, stakeholders
1.1.1 Initiation Description: First Process
Duration: 30 days
Acceptance Criteria: Below Deliverables
Resources: PMO, Stakeholders
1.1.1.1 Project Charter Description: The project charter is defined as a
document issued by the project sponsor that formally
authorizes the existence of a project and provides the
project manager with the authority to apply
organizational resources to project activities.
Duration: 14 days
Acceptance Criteria: Client - sponsor
Resources: Stalk holders; Project Manager
1.1.1.2 Business Case Description: Documented economic feasibility study
used to establish the validity of the benefits of a selected
component lacking sufficient definition and that is used
as a basis for the authorization of further project
management activities.
Duration: 14
Acceptance Criteria: KPIS
Resources: Business Analyst
1.1.1.3 Benefit Management Plan Description: Provide some type of benefit as a result of
delivering the products of the project.
37
Duration: 7
Acceptance Criteria: Metrics
Resources: Business Analyst; Project Manager
1.1.2 Scope Management Plan Description: Establishes how the scope will be defined,
developed, monitored, controlled, and validated.
Duration: 5
Acceptance Criteria: Deliverables
Resources: Project Manager; Contracts Manager
1.1.3 Schedule Management Plan Description: Establishes the criteria and the activities
for developing, monitoring, and controlling the
schedule.
Duration: 5
Acceptance Criteria: SPI
Resources: Project Manager; Planning Engineer
1.1.4 Cost Management Plan Description: Establishes how the costs will be planned,
structured, and controlled.
Duration: 5
Acceptance Criteria: CPI
Resources: Project Manager; Cost Engineer; Planning
Engineer
1.1.5 Quality Management Plan Description: Establishes how an organization´s quality
policies, methodologies, and standards will be
implemented in the project.
Duration: 5
Acceptance Criteria: QUALITY METRICS &
MEASURE
Resources: Project Manager; Quality Engineer
1.1.6 Resource Management Plan Description: Provides guidance on how project
resources should be categorized, allocated, managed,
and released.
Duration: 5
Acceptance Criteria: Fulfills Requirements and
Specifications
Resources: Project Manager; Procurement Engineer;
Cost Engineer; Planning Engineer
1.1.7 Communication Management Description: Establishes how, when, and by whom
Plan information about the project will be administered and
disseminated.
Duration: 5
Acceptance Criteria: Network Channels
Resources: Project Manager
1.1.8 Risk Management Plan Description: Establishes how the risk management
activities will be structured and performed.
Duration: 5
Acceptance Criteria: Significance of risk
Resources: Project Manager; Planning Engineer; Cost
Engineer
1.1.9 Procurement Management Plan Description: Establishes how the project team will
acquire goods and services from outside of the
performing organization.
Duration: 5
Acceptance Criteria: Fulfills Requirements and
Specifications
Resources: Project Manager; Procurement Engineer;
Cost Engineer; Planning Engineer
1.1.10 Stakeholder Engagement Plan Description: Establishes how stakeholders will be
engaged in project decisions and execution, according
to their needs, interests, and impact.
Duration: 5
Acceptance Criteria:
Resources: Project Manager; Stalk holders
1.1.11 Close Out Description: Those processes performed to formally
complete or close the project, phase, or contract.
Duration: 5
Resources: Project Manager, Administrator
1.1.11.1 Final Report Description: Stating all documents for initiation.
Duration: 3
Acceptance Criteria:
Resources: Project Manager
1.1.11.2 Project Document Update Description: • Assumption log • Requirements
documentation • Requirements traceability matrix •
Stakeholder register
Duration: 10
Resources: Administrator
1.1.11.3 OPA Update Description: Project or phase closure guidelines or
requirements, and Configuration management
knowledge base containing the versions and baselines of
all official organizational standards, policies,
procedures, and any project documents.
Duration: 3
Resources: Administrator
1.2 Design Tender Description: Project Design Drawings & Bill of
Quantity
Duration: 21
Acceptance Criteria:
Resources: Structural Engineer; Architectural
Engineer; Electrical Engineer; Estimator; Mechanical
Engineer
1.2.1 Soil Investigation Description: Bearing Capacity Report
Duration: 2
Acceptance Criteria: Bearing Capacity Allowable
Resources: Third Party
1.2.2 Conceptual Design Description: First Revision of Design
Duration: 7
Acceptance Criteria: ACI Code, Building Laws
Resources: Structural Engineer, Architect, Electrical
Engineer, Mechanical Engineer
1.2.2.1 Architectural Design Description: Architectural Design Rev.00
Duration: 7
Acceptance Criteria: Building Laws
Resources: Architect
1.2.2.2 Civil Design Description: Structural Design Rev.00
Duration: 7
Acceptance Criteria: ACI Code
Resources: Structural Engineer
1.2.2.3 MEP Design Description: Electrical, Mechanical, HVAC Designs
Rev.00
Duration: 7
Acceptance Criteria: ACI Code
Resources: Mechanical Engineer; Electrical Engineer;
Architect
1.2.3 Preliminary Design Description: Rev.01 of Designs
Duration: 7
Acceptance Criteria: ACI Code, Building Codes
Resources: Structural Engineer, Architect, Electrical
Engineer, Mechanical Engineer
1.2.3.1 Architectural Preliminary Description: Architect
Design Duration: 3
Acceptance Criteria: Building Laws
Resources: Architect
1.2.3.2 Civil Preliminary Design Description: Rev.01 of Structural Design
Duration: 3
Acceptance Criteria: ACI Code
Resources: Structural Engineer
1.2.3.3 MEP Preliminary Design Description: Rev.01 of MEP Design
Duration: 3
Acceptance Criteria:
Resources: Mechanical Engineer; Electrical Engineer;
Architect
1.2.4 Final Design Reviewed Description: Final Designs
Duration: 4
Acceptance Criteria: ACI Code, Building Laws
Resources: Structural Engineer, Architect, Electrical
Engineer, Mechanical Engineer
1.2.4.1 Final Architectural Design Description: Final Architectural Design
Duration: 4
Acceptance Criteria: Building Laws
Resources: Architectural Engineer
1.2.4.2 Final Civil Design Description: Final Structural Design
Duration: 4
Acceptance Criteria: ACI Code
Resources: Structural Engineer
1.2.4.3 Final MEP Design Description: Final MEP Design
Duration: 4
Acceptance Criteria:
Resources: Electrical Engineer; Mechanical Engineer;
Architectural Engineer
1.2.5 B.O.Q Description: Bill of Quantity
Duration: 5
Acceptance Criteria: Price Comparison
Resources: Procurement Engineer; Cost Engineer
1.3 Human Resources Description: Recruiting Different Crews
Duration: 10
Acceptance Criteria: HRMS, ISO QMS
Resources: Human Resource Officer, Project Manager
1.3.1 HRMS Description: A Human Resources Management System
(HRMS) is a type of information system (IS) that is
designed to manage an organization's computerized
and automated human resource (HR) processes. It is a
combination of hardware and software resources that
hosts and provides most, if not all, of a HR
department's business logic.
Duration: 10
Acceptance Criteria:
Resources: Human Resource Officer, Project Manager
1.3.2 ISO QMS Description: Quality Management System
Duration: 10
Acceptance Criteria: general
Quality Management System requirements
Resources: Human Resources, Administrator, Project
Manager
1.4 Construction Description: All phases including construction
Duration:
Acceptance Criteria: Consultant, Specifications,
Resources: Construction Team, Project Manager
1.4.1 Mobilization Description: Includes Site preparation, Soil
investigation and Office implementation.
Duration: 10
Acceptance Criteria: Required specifications and
Requirements
Resources: Third Party
1.4.1.1 Site Preparation Description: Fencing and warehouse execution
Duration: 6
Acceptance Criteria: Temporary Landscape Plan
Resources: Labor; Foreman
1.4.1.1.1 Ground Compaction Description: Preparation of Ground for Foundation
setup
Duration: 3
Acceptance Criteria: Proctor compaction test
Resources: Site Engineer, Foreman, Labor
1.4.1.1.2 Fencing Description: Temporary Fencing around the Project
Duration: 6
Acceptance Criteria: Layout Design and Plans
Resources: Site Engineer, Foreman, Labor
1.4.1.1.3 Warehouse Description: Storing Project's Material, Equipment and
Tools
Duration: 15
Acceptance Criteria: Temporary Design, Design Plans
Resources: Third Party, Site Engineer, Foreman, Labor
1.4.1.1.3.1 Inventory Description: complete list of items such as property,
goods in stock, or the contents of a building.
Duration: 1
Acceptance Criteria: Auditing
Resources: Warehouse Supervisor
1.4.1.1.3.2 Purchases Description: The process after procurement and site
mobilization
Duration: 1
Acceptance Criteria: Inventory
Resources: Warehouse Supervisor
1.4.1.1.3.3 Receiving Description: Receiving Material from site after usage
Duration: 1
Acceptance Criteria: Inventory
Resources: Warehouse Supervisor, Labor
1.4.1.1.4 Temporary Parking Description: Temporary parking for Crew
Duration: 6
Acceptance Criteria: Layout Plan Design
Resources: Site Engineer, Foreman, Labor
1.4.1.2 Offices and Utilities Description: Porta-cabin fixation with their respects
utilities
Duration: 7
Acceptance Criteria: Consultant specifications
Resources: Third Party Service
1.4.1.2.1 Office Mobilization Description: : Porta-cabin fixation
Duration: 7
Acceptance Criteria: Design layout, Specifications
Resources: Third party, Foreman
1.4.1.2.1.1 MEP Work Description: Preparing all MEP works required
Duration: 3
Acceptance Criteria: Temporary Design
Resources: Third party
1.4.1.2.1.2 Interior Works Description: Allocating Offices, Chairs and acc.
Duration: 2
Acceptance Criteria: Consultant Specifications
Resources: Third Party, Foreman, Labor
1.4.1.2.2 Utilities Mobilization Description: Porta cabin Restrooms and Cafeteria
Duration: 5
Acceptance Criteria: Consultant Specifications, Health
Standards
Resources: Third Party, Foreman, Labor
1.4.1.2.2.1 Restrooms Description: Temporary restroom
Duration: 2
Acceptance Criteria: Health Standards
Resources: Third Party, Foreman, Labor
1.4.1.2.2.2 Cafeteria Description: Temporary Cafeteria
Duration: 3
Acceptance Criteria: Health Standards
Resources: Third Party, Foreman, Labor
1.4.2 Excavation Description:
Duration: 1
Acceptance Criteria:
Resources: Site Engineer, Foreman, Labor, Rigger,
Flagman;
1.4.2.1 Clinic Area Description: Excavation and transport of debris
Duration: 7
Acceptance Criteria: Acceptable Level given by
surveyor
Resources: Surveyor; Rigger; Flagman; Excavator;
Dump Truck
1.4.2.1.1 Excavation Description: Excavate Clinic and Water Tank Areas
Duration: 6
Acceptance Criteria: Accepted Level by Surveyor
Resources: Site Engineer, Foreman, Labor, Rigger,
Flagman
1.4.2.1.2 Dumping Area Description: Area to dump excavated soil
Duration: 8
Acceptance Criteria: Building Laws
Resources: Foreman, Labor, Rigger; Flagman;
1.4.2.1.3 Compaction Description: Compacting underground to start
foundation laying
Duration: 4
Acceptance Criteria: Procter Compaction Test
Resources: Site Engineer, Foreman, Labor
1.4.2.2 Water Tank Area Description: Water Tank Excavation
Duration: 5
Acceptance Criteria: Level Set by Surveyor
Resources: Surveyor; Rigger; Flagman;
1.4.2.2.1 Excavation Description: Excavating Water Tank Area
Duration: 6
Acceptance Criteria: Accepted Level by Surveyor
Resources: Site Engineer, Foreman, Labor, Rigger,
Flagman
1.4.2.2.2 Dumping Area Description: Area to be dump excavated soil
Duration: 6
Acceptance Criteria: Building Laws
Resources: Site Engineer, Foreman, Labor, Rigger,
Flagman
1.4.2.2.3 Compaction Description: Compacting ground for preparation
Duration: 2
Acceptance Criteria: Procter Compaction Test
Resources: Site Engineer, Foreman, Labor, Rigger,
Flagman
1.4.3 Sub-Structure Description: Substructure execution including
underground utilities, Water tank and foundation
columns.
Duration: 18
Acceptance Criteria: As per Drawings designed
Resources: Site Engineer; Supervisor; Steel Fixers;
Carpenters; Surveyor; Carpenters; Carpenters; Labor
1.4.3.1 Foundations 1.5 ( - ) Description: Pouring the foundation of the clinic
Duration: 10
Acceptance Criteria: Consultant
Resources: Site Engineer; Supervisor; Steel Fixers;
Carpenters; Surveyor; Carpenters; Carpenters; Labor
1.4.3.1.1 Formwork Description: Preparing formwork for steel placement
Duration: 5
Acceptance Criteria: Consultant
Resources: Carpenters, Labors, Foreman
1.4.3.1.2 Steel Work Description: Steel works as per Drawings
Duration: 4
Acceptance Criteria: Consultant
Resources: Foreman, Steel fixer, Labor
1.4.3.1.3 Pouring Description: Poring and Curing of Foundation
Duration: 1
Acceptance Criteria: Quality Specification , Consultant
Resources: Site Engineer, Foreman, Labor, Carpenters
1.4.3.2 Foundation Columns Description: Execution of Foundation Columns
Duration: 4
Acceptance Criteria: Consultant
Resources: Site Engineer, Foreman, Steel Fixer,
Carpenter, Labor
1.4.3.2.1 Formwork Description: Formwork Erection
Duration: 2
Acceptance Criteria: Consultant
Resources: Foreman, Carpenter, Labor
1.4.3.2.2 MEP Work Description: Electrical, Mechanical, Plumbing
Duration: 7
Acceptance Criteria: MEP Design Plans
Resources: Electrical Engineer, Mechanical Engineer,
Foreman, Labor
1.4.3.2.3 Steel Work Description: Steel erection of columns
Duration: 2
Acceptance Criteria: Consultant
Resources: Site Engineer, Foreman, Steel Fixers,
Labors
1.4.3.2.4 Pouring Description: Casting and Curing Columns
Duration: 1
Acceptance Criteria: Consultant
Resources: Foreman, Labor
1.4.4 Structures Description: Structure Package above Ground
Duration:
Acceptance Criteria: Specifications, Requirements,
Consultant, ACI Code
Resources: Site Engineer, Electrical Engineer,
Mechanical Engineer, Architect, Foreman, Labor,
Carpenters, Steel Fixers.
1.4.4.1 Concrete Package Description: Structure Package above Ground
Duration: 1
Acceptance Criteria: Specifications, Requirements,
Consultant, ACI Code
Resources: Site Engineer, Electrical Engineer,
Mechanical Engineer, Architect, Foreman, Labor,
Carpenters, Steel Fixers.
1.4.4.1.1 Ground Slab 0.0 ( + ) Description: Slab on Grade Execution
Duration: 18
Acceptance Criteria: Consultant,
Resources: Site Engineer, Electrical Engineer,
Mechanical Engineer, Architect, Foreman, Labor,
Carpenters, Steel Fixers.
1.4.4.1.1.1 Formwork Description: Formwork Erection
Duration: 7
Acceptance Criteria: Design Drawings
Resources: Site Engineer, Foreman , Carpenters,
Labors
1.4.4.1.1.2 MEP Work Description: MEP Works for Slab on Grade
Duration: 3
Acceptance Criteria: MEP Design Drawings
Resources: Electrical Engineer, Mechanical Engineer,
Foreman, Labors
1.4.4.1.1.3 Steel Work Description: Steel Erection for Slab on Grade
Duration: 7
Acceptance Criteria: Structural Design Drawings,
Consultant
Resources: Site Engineer, Foreman, Labors
1.4.4.1.1.4 Pouring Description: Casting and Curing Slab on Grade
Duration: 7
Acceptance Criteria: Design Drawings , Consultant
Resources: Site Engineer, Foreman, Labors ,
Carpenters
1.4.4.1.2 Vertical Elements Description: All Vertical elements executed in the
project
Duration: 8
Acceptance Criteria: Design Drawings, Consultant
Resources: Site Engineer, Electrical Engineer,
Mechanical Engineer, Foreman, Labor, Carpenters,
Steel Fixers.
1.4.4.1.2.1 Formwork Description: Formwork Erection
Duration: 15
Acceptance Criteria: Design Drawings, Consultant
Resources: Site Engineer, Foreman, Carpenters,
Labors
1.4.4.1.2.2 MEP Work Description: Check for MEP Works
Duration: 1
Acceptance Criteria: MEP Drawings, Consultant
Resources: Mechanical Engineer, Electrical Engineer,
Foreman, Labors
1.4.4.1.2.3 Steel Work Description: Steel Erection
Duration: 10
Acceptance Criteria: Structural Design, Consultant
Resources: Site Engineer, Foreman, Steel Fixers,
Labors
1.4.4.1.2.4 Pouring Description: Casting and Curing
Duration: 7
Acceptance Criteria: Structural Design, Consultant
Resources: Site Engineer, Foreman, Carpenters,
Labors
1.4.4.1.3 Slab 3.0 ( + ) Description: Roof Slab Execution
Duration: 23
Acceptance Criteria: Design Drawings, Consultant,
Specifications, Requirements
Resources: Site Engineer, Electrical Engineer,
Mechanical Engineer, Architect, Foreman, Labor,
Carpenters, Steel Fixers.
1.4.4.1.3.1 Formwork Description: Scaffolding and Formwork erection
Duration: 12
Acceptance Criteria: Design Drawings, Consultant
Resources: Site Engineer, Foreman, Carpenters,
Scaffolders, Labors
1.4.4.1.3.2 MEP Work Description: Electrical, Plumbing and Mechanical
Works along
Duration: 5
Acceptance Criteria: Design Drawings, Consultant
Resources: Mechanical Engineer, Electrical Engineer,
Foreman, Labors
1.4.4.1.3.3 Steel Work Description: Steel Erection
Duration: 8
Acceptance Criteria: Structural Drawings, Consultant
Resources: Site Engineer, Foreman, Steel Fixer, Labors
1.4.4.1.3.4 Pouring Description: Slab Casting and Curing
Duration: 7
Acceptance Criteria: Design Drawings, Consultant
Resources: Site Engineer, Foreman, Labors
1.4.4.1.4 Steel Package Description: Structural Steel Erection on Roof
Duration: 10
Acceptance Criteria: Design Drawings, Consultant
Resources: Third Party
1.4.4.2 MEP Works Description: Interior works for MEP
Duration: 25
Acceptance Criteria: Design Drawings, Consultant
Resources: Mechanical Engineer, Electrical Engineer,
Foreman, Labors
1.4.4.2.1 Electrical Works Description: All Interior Electrical works
Duration: 10
Acceptance Criteria: MEP Drawings, Consultant
Resources: Electrical Engineer, Foreman, Labors
1.4.4.2.2 Plumbing Works Description: Interior Plumbing Works
Duration: 10
Acceptance Criteria: MEP Drawings, Consultant
Resources: Mechanical Engineer, Forman, Labors
1.4.4.2.3 HVAC Description: HVAC VRV System
Duration: 20
Acceptance Criteria: MEP Drawings, Consultant
Resources: Mechanical Engineer, Foreman, Labors
1.4.4.2.4 Fire Protection Work Description: Fire Protection System implementation
Duration: 15
Acceptance Criteria: Health Ministry, MEP Drawings,
Consultant
Resources: Mechanical Engineer, Foreman, Labors
1.4.4.3 Interior Package Description: Interior Design Works
Duration: 30
Acceptance Criteria: Consultant, Stakeholders,
Architectural Design
Resources: Architect, Site Engineer, Foreman, Labors
1.4.4.3.1 Masonry Description: Lay Down Masonry
Duration: 25
Acceptance Criteria: Consultant, Architectural
Drawings
Resources: Site Engineer, Foreman, Labors
1.4.4.3.2 Cementations Work Description: Wall Plastering Works
Duration: 21
Acceptance Criteria: Consultant, Architectural
Drawings
Resources: Site Engineer, Forman, Labors
1.4.4.3.3 Paint Work Description: Paint works for walls
Duration: 21
Acceptance Criteria: Consultant, Architectural
Drawings
Resources: Site Engineer, Foreman, Labors
1.4.4.3.4 Tiling Work Description: Tiling works for interiors
Duration: 21
Acceptance Criteria: Consultant, Architectural
Drawings
Resources: Site Engineer, Foreman, Labors
1.4.4.3.5 Gypsum board Work Description: Install Gypsum board for interior works
Duration: 15
Acceptance Criteria: Consultant, Architectural
Drawings
Resources: Architect, Site Engineer, Foreman, Labors
1.4.4.3.6 Lighting Description: Interior & Exterior Lighting
Duration: 10
Acceptance Criteria: Consultant, Architectural
Drawings
Resources: Architect, Site Engineer, Foreman, Labors
1.4.4.3.7 Security Cameras Description: Security Cameras Implementation
Duration: 7
Acceptance Criteria: Testing and Commissioning
Resources: Third Party
1.4.4.4 Equipment Installation Description: Installing Equipment for Offices
Duration: 10
Acceptance Criteria: Architectural Layout
Resources: Third Party, Site Engineer, Foreman,
Labors
1.4.4.4.1 Offices Description: Offices allocation
Duration: 5
Acceptance Criteria: Architectural Layout
Resources: Third Party, Site Engineer, Foreman,
Labors
1.4.4.4.2 Medical Equipment Description:
Duration: 1
Acceptance Criteria: Architectural Layout, Healthcare
requirements
Resources: Third Party, Site Engineer, Foreman,
Labors
1.4.5 Solar Panels Description: Solar Panel Installation
Duration: 10
Acceptance Criteria: Specifications and Location
Layout
Resources: Third Party, Site Engineer, Foreman,
Labors
1.4.6 Parking & Landscape Description: Execution of Parking, Landscape and
Security Check office.
Duration: 15
Acceptance Criteria: Design Layout, Architectural
Design, Consultant
Resources: Site Engineer, Foreman, Labors, Electrical
Engineer, Mechanical Engineer
1.4.7 Demobilize Description: Demobilize temporary offices and utilities
Duration: 7
Acceptance Criteria: Clear Obstruction and Site
Cleaning
Resources: Foreman, Labors
1.5 Project Controls Description: Controlling and Monitoring Project
Performance
Duration: 150
Acceptance Criteria: KPIS
Resources: Project Manager, Planning Engineer, Cost
Engineer, Procurement Engineer, Contracts Engineer.
1.5.1 Deliverables Check Description: Checking Projects Deliverables
Duration: 150
Acceptance Criteria: Scope Management Plan
Resources: Project Manager, Planning Engineer, Cost
Engineer, Procurement Engineer, Contracts Engineer.
1.5.1.1 Scope Control Description: Controlling Deliverables of the project
Duration: 150
Acceptance Criteria: Scope Management Plan
Resources: Project Manager, Planning Engineer, Cost
Engineer, Procurement Engineer, Contracts Engineer.
1.5.1.2 Schedule Control Description: Controlling Schedule
Duration: 150
Acceptance Criteria: SPI
Resources: Project Manager, Planning Engineer, Cost
Engineer
1.5.1.3 Cost Control Description: Controlling Cost
Duration: 150
Acceptance Criteria: CPI
Resources: Project Manager, Planning Engineer, Cost
Engineer
1.5.1.4 Quality Control Description: Quality Control And Quality Assurance
Duration: 150
Acceptance Criteria: Quality Management Plan
Resources: Project Manager, Procurement Engineer,
Contracts Engineer.
1.5.1.5 Resource Control Description: Controlling Projects resources
Duration: 150
Acceptance Criteria: HRMS
Resources: Project Manager, Planning Engineer, Cost
Engineer, Procurement Engineer, Contracts Engineer,
Human resources.
1.5.1.6 Procurement Control Description: Controlling Procurement
Duration: 150
Acceptance Criteria: Procurement Management Plan
Resources: Project Manager, Planning Engineer, Cost
Engineer, Procurement Engineer, Contracts Engineer.
1.5.1.7 Monitor Risk Description: Risk Control
Duration: 150
Acceptance Criteria: Opportunities and Exposure for
omission
Resources: Project Manager, Planning Engineer, Cost
Engineer, Procurement Engineer, Contracts Engineer.
1.5.2 Safety Description: Safety of Site Crew
Duration: 150
Acceptance Criteria: Safety permits,
Resources: Safety Team
1.5.2.1 Safety Plan Description: Safety of Site Crew
Duration: 150
Acceptance Criteria: Safety permits,
Resources: Safety Team
1.5.2.2 Safety Documents Description: Safety of Site Crew
Duration: 150
Acceptance Criteria: Safety permits,
Resources: Safety Team
1.5.2.3 Inspection & Approval Description: Final Inspections
Duration: 20
Acceptance Criteria: Manuals
Resources: Quality Control, Project Management
1.5.3 Approvals Description: Deliverable approvals
Duration: 20
Acceptance Criteria: Benefit realization Plan
Resources: Project Manager, Administrator
1.5.4 Change Control Description: How to handle Change
Duration: 150
Acceptance Criteria: Change Management Plan
Resources: Project Manager, Planning Engineer, Cost
Engineer, Procurement Engineer, Contracts Engineer.
1.6 Startup & Commissioning Description: Testing of all equipment and buildings
Duration: 15
Acceptance Criteria: Manuals
Resources: Project Manager, Planning Engineer, Cost
Engineer, Procurement Engineer, Contracts Engineer.
1.6.1 Test Preparation Description: Testing of all equipment and buildings
Duration: 15
Acceptance Criteria: Manuals
Resources: Project Manager, Planning Engineer, Cost
Engineer, Procurement Engineer, Contracts Engineer.
1.6.2 Test Performance Description: Testing of all equipment and buildings
Duration: 15
Acceptance Criteria: Manuals
Resources: Project Manager, Planning Engineer, Cost
Engineer, Procurement Engineer, Contracts Engineer.
1.6.3 Manuals Description: Testing of all equipment and buildings
Duration: 15
Acceptance Criteria: Manuals
Resources: Project Manager, Planning Engineer, Cost
Engineer, Procurement Engineer, Contracts Engineer.
Source: The authors
3.6 Monitoring and Controlling
The construction of the Health Clinic in El Rosario will take a year, being this is a long
project it is necessary to be monitoring and controlling the entire project since the initiation
until closure.
With the information provided, the scope will be monitored throughout the whole project
by using variance analysis which will be used to compare the baseline to the actual results
of the project and to consider if making a corrective or preventive decision.
The results will also include “the number of change requests received, the number of
requests accepted, and the number of deliverables verified, validated, and completed”
(Project Management Institute, 2017)
4 Schedule Management Plan
4.1 Introduction, Scope and Purpose of the Plan
The schedule management plan is created to establish all the criteria’s for developing,
monitoring and controlling all the activities on the construction for the Healthcare Center in
el Rosario.
The Schedule Management plan is created to establish all the criteria’s for developing,
monitor and control all the activities for the construction of the Healthcare Center in El
Rosario. (Project Management Institute, 2017) Defines Schedule Management Plan as:
The process of establishing the policies, procedures, documentation for
planning, developing, managing, executing and controlling the project schedule.
The tool used to determine the schedule plan is Project Management Software Project (MS
Project) , which is “a tool for project managers that helps develop a schedule, assign
resources to tasks, track the progress, manage the budget and analyze workloads for an
ongoing project” (Tutorials Point).
4.2 Key dates and Milestones
A milestone list is created by the Project Manager of this project and its team where it
represents a time where the team has achieved an important event of the project. . To have a
better understanding, a milestone is a “significant point or event in a project. A milestone
list identifies all project milestones and indicates whether the milestone is mandatory, such
as those required by contract, or optional, such as those based on historical information”
(Project Management Institute, 2017).
The milestone list for the Clinic construction presented on Table 16
Table 16: Milestones
Task Name Milestone Date
Project Kick Off Thu 2/1/20
Construction Phase Tue 18/2/20
Under Ground Phase Tue 5/5/20
Above Ground Phase Tue 29/9/20
Project Completion Thu 28/1/21
Source: The authors
4.3 Activity List
The activity list includes the schedule activities required on the project. This list provides
as many details as possible to make it easier to for the project management team to access
though the schedule during the whole project duration. The activity list for the whole
project is presented on Table 17.
Table 17: Activity List
Task ID Task Name Duration Start Finish
1 Clinic Project 264 days Thu 2/1/20 Thu 28/1/21
1.1 Project Management Office 34 days Thu 2/1/20 Wed 19/2/20
1.1.1 Initiation 11 days Thu 2/1/20 Thu 16/1/20
1.1.1.1 Business Case 8 days Thu 2/1/20 Mon 13/1/20
1.1.1.2 Project Charter 3 days Tue 14/1/20 Thu 16/1/20
1.1.1.3 Benefit Management Plan 3 days Tue 14/1/20 Thu 16/1/20
1.1.2 Scope Management Plan 5 days Fri 17/1/20 Thu 23/1/20
1.1.3 Schedule Management Plan 5 days Fri 24/1/20 Thu 30/1/20
1.1.4 Cost Management Plan 5 days Wed 29/1/20 Wed 5/2/20
1.1.5 Quality Management Plan 5 days Thu 30/1/20 Thu 6/2/20
1.1.6 Resource Management Plan 5 days Fri 24/1/20 Thu 30/1/20
1.1.7 Communication Management Plan 5 days Tue 4/2/20 Mon 10/2/20
1.1.8 Risk Management Plan 5 days Wed 5/2/20 Tue 11/2/20
1.1.9 Procurement Management Plan 5 days Thu 6/2/20 Wed 12/2/20
1.1.10 Stakeholder Engagement Plan 5 days Fri 7/2/20 Thu 13/2/20
1.1.11 Close Out 4 days Fri 14/2/20 Wed 19/2/20
1.1.11.1 Final Report 2 days Fri 14/2/20 Mon 17/2/20
1.1.11.2 Project Document Update 1 day Tue 18/2/20 Tue 18/2/20
1.1.11.3 OPA Update 1 day Wed 19/2/20 Wed 19/2/20
1.2 Design Tender 19 days Thu 2/1/20 Tue 28/1/20
1.2.1 Soil Investigation 4 days Thu 2/1/20 Tue 7/1/20
1.2.2 Soil Report 1 day Wed 8/1/20 Wed 8/1/20
1.2.3 Conceptual Design 6 days Wed 8/1/20 Wed 15/1/20
1.2.3.1 Architectural Design 3 days Wed 8/1/20 Fri 10/1/20
1.2.3.2 Civil Design 3 days Mon 13/1/20 Wed 15/1/20
1.2.3.3 MEP Design 3 days Mon 13/1/20 Wed 15/1/20
1.2.4 Preliminary Design 2 days Thu 16/1/20 Fri 17/1/20
1.2.4.1 Architectural Preliminary Design 2 days Thu 16/1/20 Fri 17/1/20
1.2.4.2 Civil Preliminary Design 2 days Thu 16/1/20 Fri 17/1/20
1.2.4.3 MEP Preliminary Design 2 days Thu 16/1/20 Fri 17/1/20
1.2.5 Final Design Reviewed 2 days Mon 20/1/20 Tue 21/1/20
1.2.5.1 Final Architectural Design 2 days Mon 20/1/20 Tue 21/1/20
1.2.5.2 Final Civil Design 2 days Mon 20/1/20 Tue 21/1/20
1.2.5.3 Final MEP Design 2 days Mon 20/1/20 Tue 21/1/20
1.2.6 B.O.Q 5 days Wed 22/1/20 Tue 28/1/20
1.3 Human Resources 25 days Mon 13/1/20 Tue 18/2/20
1.3.1 HRMS 20 days Mon 13/1/20 Mon 10/2/20
1.3.2 ISO QMS 20 days Mon 13/1/20 Mon 10/2/20
2 Construction 232 days Tue 18/2/20 Thu 28/1/21
2.1 Mobilization 17 days Tue 18/2/20 Wed 11/3/20
2.1.1 Site Preparation 17 days Tue 18/2/20 Wed 11/3/20
2.1.1.1 Site Clearance 1 day Tue 18/2/20 Tue 18/2/20
2.1.1.2 Ground Compaction 3 days Wed 19/2/20 Fri 21/2/20
2.1.1.3 Fencing 10 days Wed 19/2/20 Tue 3/3/20
2.1.1.4 Warehouse 13 days Mon 24/2/20 Wed 11/3/20
2.1.1.4.1 Warehouse Implementation 7 days Mon 24/2/20 Tue 3/3/20
2.1.1.4.2 Inventory 2 days Wed 4/3/20 Thu 5/3/20
2.1.1.4.3 Purchases 2 days Fri 6/3/20 Mon 9/3/20
2.1.1.4.4 Receiving 2 days Tue 10/3/20 Wed 11/3/20
2.1.1.5 Temporary Parking 6 days Mon 24/2/20 Mon 2/3/20
2.1.1 Offices and Utilities 12 days Mon 24/2/20 Tue 10/3/20
2.1.1.1 Office Mobilization 12 days Mon 24/2/20 Tue 10/3/20
2.1.1.1.1 Office Allocation 6 days Mon 24/2/20 Mon 2/3/20
2.1.1.1.2 MEP Work 3 days Tue 3/3/20 Thu 5/3/20
2.1.1.1.3 Interior Works 3 days Fri 6/3/20 Tue 10/3/20
2.1.1.2 Utilities Mobilization 3 days Tue 3/3/20 Thu 5/3/20
2.1.1.2.1 Restrooms 3 days Tue 3/3/20 Thu 5/3/20
2.1.1.2.2 Cafeteria 3 days Tue 3/3/20 Thu 5/3/20
2.2 Excavation 7 days Wed 11/3/20 Fri 20/3/20
2.2.1 Clinic Area 7 days Wed 11/3/20 Fri 20/3/20
2.2.1.1 Excavation 5 days Wed 11/3/20 Tue 17/3/20
2.2.1.2 Dumping Area 5 days Wed 11/3/20 Tue 17/3/20
2.2.1.3 Compaction 2 days Wed 18/3/20 Fri 20/3/20
2.2.2 Water Tank Area 5 days Wed 11/3/20 Tue 17/3/20
2.2.2.1 Excavation 3 days Wed 11/3/20 Fri 13/3/20
2.2.2.2 Dumping Area 3 days Wed 11/3/20 Fri 13/3/20
2.2.2.3 Compaction 2 days Mon 16/3/20 Tue 17/3/20
2.3 Sub-Structure 27 days Mon 23/3/20 Tue 5/5/20
2.3.1 Foundations 1.5 ( - ) 21 days Mon 23/3/20 Fri 24/4/20
2.3.1.1 Formwork 8 days Mon 23/3/20 Wed 1/4/20
2.3.1.2 Steel Work 6 days Thu 2/4/20 Wed 15/4/20
2.3.1.3 Pouring & Curing 7 days Thu 16/4/20 Fri 24/4/20
2.3.1.4 DE shuttering & Cleaning 1 day Fri 17/4/20 Fri 17/4/20
2.3.1.5 Backfill & Compaction 2 days Mon 20/4/20 Tue 21/4/20
2.3.2 Foundation Columns 12 days Fri 17/4/20 Tue 5/5/20
2.3.2.1 Formwork 5 days Fri 17/4/20 Thu 23/4/20
2.3.2.2 MEP Work 2 days Fri 17/4/20 Mon 20/4/20
2.3.2.3 Steel Work 2 days Tue 21/4/20 Wed 22/4/20
2.3.2.4 Pouring & Curing 7 days Thu 23/4/20 Mon 4/5/20
2.3.2.5 DE shuttering & Cleaning 1 day Fri 24/4/20 Fri 24/4/20
2.3.2.6 Backfill & Compaction 6 days Mon 27/4/20 Tue 5/5/20
2.4 Structures 172 days Wed 6/5/20 Thu 14/1/21
2.4.1 Concrete Package 56 days Wed 6/5/20 Thu 23/7/20
2.4.1.1 Ground Slab 0.0 ( + ) 17 days Wed 6/5/20 Thu 28/5/20
2.4.1.1.1 Formwork 12 days Wed 6/5/20 Thu 21/5/20
2.4.1.1.2 MEP Work 3 days Wed 6/5/20 Fri 8/5/20
2.4.1.1.3 Steel Work 10 days Wed 6/5/20 Tue 19/5/20
2.4.1.1.4 Pouring 7 days Wed 20/5/20 Thu 28/5/20
2.4.1.2 Vertical Elements 17 days Mon 25/5/20 Wed 17/6/20
2.4.1.2.1 Scaffolding 5 days Mon 25/5/20 Fri 29/5/20
2.4.1.2.2 Formwork 7 days Thu 28/5/20 Fri 5/6/20
2.4.1.2.3 MEP Work 2 days Thu 28/5/20 Fri 29/5/20
2.4.1.2.4 Steel Work 5 days Mon 1/6/20 Fri 5/6/20
2.4.1.2.5 Pouring & Curing 7 days Mon 8/6/20 Wed 17/6/20
2.4.1.2.6 DE shuttering & Cleaning 2 days Tue 9/6/20 Wed 10/6/20
2.4.1.2 Slab 3.0 ( + ) 30 days Fri 12/6/20 Thu 23/7/20
2.4.1.2.1 Scaffolding 7 days Fri 12/6/20 Mon 22/6/20
2.4.1.2.2 Formwork 10 days Tue 23/6/20 Mon 6/7/20
2.4.1.2.3 MEP Work 3 days Tue 23/6/20 Thu 25/6/20
2.4.1.2.4 Steel Work 7 days Wed 24/6/20 Thu 2/7/20
2.4.1.2.5 Pouring & Curing 7 days Fri 3/7/20 Mon 13/7/20
2.4.1.2.6 DE shuttering Scaffolding & Cleaning 14 days Mon 6/7/20 Thu 23/7/20
2.4.2 Exterior Package 44 days Fri 24/7/20 Tue 29/9/20
2.4.2.1 Alco bond 29 days Fri 24/7/20 Wed 2/9/20
2.4.2.1.1 Formwork 4 days Fri 24/7/20 Wed 29/7/20
2.4.2.1.2 Steel Work & Anchor Bolt Allocation 3 days Thu 30/7/20 Mon 3/8/20
2.4.2.1.3 Pouring & Curing 1 day Tue 4/8/20 Tue 4/8/20
2.4.2.1.4 Alco bond Steel Rails Fixation 7 days Wed 5/8/20 Thu 13/8/20
2.4.2.1.5 Alco bond Panels Fixation 14 days Fri 14/8/20 Wed 2/9/20
2.4.2.2 Solar Panel Fixation 15 days Thu 3/9/20 Tue 29/9/20
2.4.3 Interior Package 106 days Fri 24/7/20 Wed 30/12/20
2.4.3.1 Masonry 21 days Fri 24/7/20 Fri 21/8/20
2.4.3.2 Cementious Work 21 days Mon 24/8/20 Fri 25/9/20
2.4.3.3 Paint Work 14 days Mon 28/9/20 Fri 16/10/20
2.4.3.4 Tiling Work 21 days Tue 20/10/20 Wed 18/11/20
2.4.3.5 Gypsum board Work 15 days Thu 19/11/20 Wed 9/12/20
2.4.3.6 Lighting 8 days Thu 10/12/20 Tue 22/12/20
2.4.4 MEP Works 36 days Mon 24/8/20 Mon 19/10/20
2.4.4.1 Electrical Works 15 days Mon 24/8/20 Mon 14/9/20
2.4.4.2 Plumbing Works 15 days Mon 24/8/20 Mon 14/9/20
2.4.4.3 HVAC 21 days Mon 31/8/20 Fri 2/10/20
2.4.4.4 Fire Protection Work 15 days Mon 28/9/20 Mon 19/10/20
2.4.4 Equipment Installation 10 days Fri 1/1/21 Thu 14/1/21
2.4.4.1 Offices 10 days Fri 1/1/21 Thu 14/1/21
2.4.4.2 Medical Equipment 10 days Fri 1/1/21 Thu 14/1/21
2.4.5 Parking & Landscape 30 days Thu 16/7/20 Wed 26/8/20
2.4.6 Demobilize & Site Clearance 10 days Fri 15/1/21 Thu 28/1/21
3 Project Controls 263 days Thu 2/1/20 Thu 28/1/21
3.1 Deliverables Check 233 days Fri 14/2/20 Thu 28/1/21
3.1.1 Scope Control 233 days Fri 14/2/20 Thu 28/1/21
3.1.2 Schedule Control 233 days Fri 14/2/20 Thu 28/1/21
3.1.3 Cost Control 233 days Fri 14/2/20 Thu 28/1/21
3.1.4 Quality Control 233 days Fri 14/2/20 Thu 28/1/21
3.1.5 Resource Control 233 days Fri 14/2/20 Thu 28/1/21
3.1.6 Procurement Control 233 days Fri 14/2/20 Thu 28/1/21
3.1.7 Risk Control 233 days Fri 14/2/20 Thu 28/1/21
3.2 Safety 263 days Thu 2/1/20 Thu 28/1/21
3.2.1 Safety Plan 2 days Thu 2/1/20 Fri 3/1/20
3.2.2 Safety Documents 2 days Fri 24/1/20 Tue 28/1/20
3.2.3 Inspection & Approval 234 days Thu 13/2/20 Thu 28/1/21
3.3 Approvals 234 days Thu 13/2/20 Thu 28/1/21
3.4 Change Control 234 days Thu 6/2/20 Thu 21/1/21
4 Startup & Commissioning 10 days Fri 15/1/21 Thu 28/1/21
4.1 Test Preparation 3 days Fri 15/1/21 Tue 19/1/21
4.2 Test Performance 5 days Wed 20/1/21 Tue 26/1/21
4.3 Manuals 2 days Wed 27/1/21 Thu 28/1/21
5 Project Completion 0 days Thu 28/1/21 Thu 28/1/21
Source: The authors
4.4 Project Schedule
According to (Project Insight), project schedule is defined as:
Is the tool that communicates what work needs to be performed, which resources of the
organization will perform the work and the timeframes in which that work needs to be
performed. The project schedule should reflect all of the work associated with
delivering the project on time. (Slate, 2018)
The project complete schedule of the project is shown on the figures 4, 5, 6 and 7 which
were created by using MS Project as a PMIS tool in order to manage correspondences
logically, due to the difficulty of presentation the schedule below will be divided on
different pages showing all activities (Task Name), durations, start and finish dates, in
addition to the critical path and milestones highlighted in yellow under the (Task
Name).
Figure 4: Project Schedule A
Source: The authors. (Elaborated in MS Project)
59
Figure 5: Project Schedule B
Source: The authors (Elaborated in MS Project)
Figure 6: Project Schedule C
Source: The authors (elaborated in MS Project)
Figure 7: Project Schedule D
Source: The authors (elaborated in MS Project)
4.5 Control Schedule
Controlling the schedule involves to monitor the status of the project activities and to update the
project progress throughout the entire schedule, the result of this process is that the schedule baseline
is maintained.
4.5.1 Variance Analysis
To keep control of the schedule performance during the project, the schedule variance and cost
variance analysis will be used:
Schedule Variance
Schedule variance (SV) is a measure of schedule performance expressed as the difference
between the planned values. It is the amount by which the project is ahead or behind the
planned delivery date, at a given point in time. It is a measure of schedule performance on
a project (Project Management Institute, 2017)
Cost Variance
Cost variance (CV) is the amount of budget deficit or surplus at a given point in time,
expressed as the difference between earned value and the actual cost. It is a measure of cost
performance on a project. (Project Management Institute, 2017)
63
4.6 Critical Path
The Critical Path is a method that controls the calculated start or finish date of the project. The
Critical path is used to:
“Estimate the minimum project duration and determine the amount of schedule flexibility on the
logical network paths within the schedule model. This schedule network analysis technique
calculates the early start, early finish, late start, and late finish dates for all” (Project Management
Institute, 2017)
Figure 8, 9 and 10 shows the critical path for the project which presents all the activities on the MS
Project that cannot be delayed to maintain the project schedule. Any delay affecting he activities
highlighted in red will be managed by the project manager according to the change management plan
stated further below.
Figure 8: Critical Path A
Source: The authors (Elaborated in MS Project)
65
Figure 9: Critical Path B
Source: The authors (Elaborated in MS Project)
Figure 10: Critical Path C
Source: The authors (Elaborated in MS Project)
5 Cost Management Plan
5.1 Introduction, Objectives and Scope
Project cost management includes the processes involved in planning, estimating,
budgeting, financing, funding, managing, and controlling costs so that the project can be
completed within the approved budget.
According to the PMBOK (2017), the Project Cost Management processes are:
1. Plan Cost Management
2. Estimating Costs
3. Determine Budget
4. Control Costs
For example, limiting the number of design reviews can reduce the cost of the project but
could increase the resulting product’s operating costs.
Another aspect of cost management is recognizing that different stakeholders measure
project costs in different ways and at different times.
For example, the cost of an acquired item may be measured when the acquisition decision
is made or committed, the order is placed, the item is delivered, or when the actual cost is
incurred or recorded for project accounting purposes.
68
5.2 Plan Cost Management
To plan the Cost Management plan, will be needed the following inputs:
a) Project Charter:
This will be helpful to assess the scope of the project and the total gross budget. The wider
the scope, the less accurate the cost estimates. Thus, we have developed a specific and
narrow scope to minimize uncertainty. In fact, our project charter includes information such
as project description & justification, high level requirements, risk analysis, gross budget
and project schedule.
Another important input to develop an accurate plan cost management is the analysis of the
project management plan.
b) Schedule Management Plan.
The schedule management plan establishes the criteria and the activities for developing,
monitoring, and controlling the schedule. The schedule management plan provides
processes and controls that will impact cost estimation and management (PMBOK, 2017).
Refer to our schedule management plan for more details.
c) Risk management plan.
The risk management plan provides the approach for identifying, analyzing, and monitoring
risks. Therefore, it can positively contribute to the identification of the processes to control
cost estimations. Refer to the risk management document to see the full risk matrix.
5.3 Risks Costs Identification
The Risk Cost Identification shows the most important risks of the project. The costs to
manage these risks can be calculated by identifying the salary per hour of the person in
charge of managing these risks and the total hours needed to do so.
The total risk cost identification will be $10, 032.50, which is illustrated in Table 18
- The Salary per hour taken by dividing the annual salary with 52 weeks of
work.
- The time needed are the hours worked per week
- Total is the product of the salary per hour and the total hours.
Table 18: Risk Cost Identification
Risk Salary per Time
Risk Item Mitigation Plan Who Total
Category hour needed
Sponsors keep changing requirements Mitigation: Ongoing communication with the
Stakeholders of the project during the execution sponsor before starting the executing phase of PM $ 18.75 40 $ 750.00
phase of the project the project & Provide a Change Order Plan
Prevention: Make material and equipment
Material and equipment delays on
Stakeholders orders weeks before needed to arrive on PM $ 18.75 35 $ 656.25
construction site
time.
Mitigation Plan:
Mitigation: Proper Planning considering
Bad Weather will delay construction
Environmental weather forecasts - getting the right PM $ 18.75 35 $ 656.25
works
equipment to work in rainy and muddy
conditions
Workers can go on a strike, delaying
Political Prevention - Tool Box Meetings Supervisor $ 8.00 55 $ 440.00
the construction
External Prevention: Maintenance for all equipment
Equipment / Machinery breaks down Supervisor $ 8.00 40 $ 320.00
Factors and machinery ( Small Workshop on site)
Project
Prevention: Daily monitoring and abiding by Safety
Management Health and Safety issues - Site injury $ 9.95 80 $ 796.00
safety permits for permission of execution. Department
Risk
Labor shortage/low skills workers. As Mitigate -Outsource part of the construction HR department
Economic $ 22.05 130 $ 2,866.50
we operate in a very isolated area phase - running a strict recruitment process (2 people)
Government changes regulations on Mitigation: Have multiple meetings with all
Political PM $ 18.75 110 $ 2,062.50
how NGOs work in Honduras stakeholders if a change is necessary
Damage or theft of equipment due to Prevention Separate Warehouse provided
Social Supervisor $ 8.00 45 $ 360.00
high level of poverty in the local area while mobilization
Project Architectural - Civil - MEP design Prevention: Early design phase and multiple
Consultants $ 15.00 75 $ 1,125.00
Management defaults revisions with external consultants
Source: The authors
71
5.4 Cost Estimations
The cost estimates will be reviewed and refined during the project to reflect additional
detail as it becomes available and assumptions are tested. The accuracy of a project
estimate will increase as the project progresses through the project life cycle. The project in
its initiation phase may have a rough order of magnitude (ROM) estimate in the range of
−25% to +75%. Later in the project, as more information is known, definitive estimates
could narrow the range of accuracy to −5% to +10%.
5.5 Cost Estimates
The first input would be the Plan Cost Management described in the previous sections. This
is because the unit of measures, the level of accuracy and precision are essential to
estimates costs.
Another important input is the Quality Management Plan. In this document, we have
identified quality requirements and/or standards for the project and its deliverables. We also
documented how the project will demonstrate compliance with quality requirements and
how we manage and control quality. Examples include ACI code for construction
specifications, ISO for the PMO quality standards and ISO for accessibility. Regarding
managing and controlling quality, we are going to use tools such as inspection checklists,
performance surveys and Ishikawa Diagrams.
Therefore, the Quality Management Plan is an essential input to estimate costs, as these
activities involve various expenses.
Finally, another vital management plan to use for cost estimates is the Scope Baseline. This
72
is because the wider the scope, the higher the costs. Therefore, we have developed a
specific project scope statement and a detailed WBS with approximately 150 deliverables.
Each deliverable is associated with specific resources. In this way, it would be easier to
estimates costs. Moreover, we have also developed a WBS dictionary in which we describe
the work to do in each WBS component. This will provide additional details to develop a
precise and accurate estimation of costs.
5.6 Estimate costs: Tools & Techniques
Analogous cost estimating. Since the team has had experiences in the construction
industry, analogous estimating is one of the most appropriate methodologies for our
project. It uses values and attributes of a previous project that are similar to the current
one. Values and attributes of the projects may include but are not limited to: scope, cost,
budget, duration, and measures of scale. Comparison of the values of the previous project
becomes the basis for estimating the same parameter or measurement for the current
project.
In the project will be using the parametric estimating to identify a relationship between
relevant data and other variables to calculate a cost estimate for project work.
Also, a reserve analysis is made to estimate the contingency reserves to account for cost
uncertainty. Contingency reserves are the budget within the cost baseline that is allocated
for identified risks. Given the results of the nature of the project and the risk matrix, the
contingency reserve has been allowed to a 20%.
5.7 Summary of the cost key requirements
The cost key requirements that have been identified are shown on Table 19.
Table 19: Cost Key Requirements
Units of measures They depend on the activity measured: they
can be in M - M2 – M3 – Lump Sum – total
units.
Level of precision The estimated costs are rounded to the
closest decimal unit.
Level of accuracy The range is +/- 10%
Cost Baseline Control Limit The range is +/- 10% of CPI/SPI
Cost Baseline Specification Limit The range is +/- 10% of CPI/SPI
(Sponsor approval)
Estimation methods Analogous Estimation
Parametric Estimation
Contingency Reserves +10% wastage on material
+10% on direct and indirect labor
Source: The authors
5.8 Project Budget
To determine the budget is the process of aggregating the estimated costs of individual
activities or work packages to establish an authorized cost baseline. The key benefit of this
process is that it determines the cost baseline against which project performance can be
monitored and controlled. This process is performed once or at predefined points in the
project.
A project budget includes all the funds authorized to execute the project. The cost baseline
is the approved version of the time-phased project budget that includes contingency
reserves, but excludes management reserves.
The budget items have been divided according to the following description:
1) Material
2) Subcontractors/Suppliers
3) Equipment/Vehicles
4) Running costs
5) Mobilization and site off costs
6) Indirect staff
7) Direct staff
8) Contingency
Table 20 presents a budget description for each item which will be used throughout the
project.
Table 20: Budget Description
Budget Item Description To-Complete
Structural Fill - Gatch $ 372
Aggregate & Asphalt For Road Works $ 14,400
Conc. Forming, Scaffolding & Acc. $ 28,808
Reinforcement Steel & Wire Mesh $ 19,200
Concrete, Grouting & Acc. $ 5,000
Plastering Material $ 3,000
Materials Painting Material $ 14,000
Masonry $ 5,175
Tiles $ 13,300
False Ceiling $ 7,200
Aluminum Louvers $ 576
Bituminous Sheet Waterproofing $ 12,600
Sub - Total Materials $ 123,631
MEP Works 0
HVAC System VRV $ 25,000
Electrical Works $ 30,000
Subcontractors / Suppliers
Solar Panel $ 15,000
Medical Equipment Installation $ 250,000
Fire System $ 15,000
Sub - Total Subcontractors $ 335,000
Rented Equipment / O.T $ 66,000
Equipment / Vehicles
Fixed Assets ( Generators ) $ 8,000
Sub - Total Equipment / Vehicles $ 74,000
Consumables $ 2,500
Running Costs Tools $ 4,500
Safety $ 3,000
Sub - Total Consumables $ 10,000
Mobilization & Site Off. Running Cost $ 6,500
Running Cost Mobilize, Demobilize & Utilities $ 15,600
Sub - Total Mobilization & Site Off. Running Cost $ 22,100
Eng. / Lab / Consultant Lab, Testing, Consultant $ 12,000
Salaries / O.T $ 221,300
Indirect Staff
Tickets / Others $ 15,000
Sub - Total Indirect Staff $ 236,300
Salaries / O.T $ 183,100
Food $ 15,150
Direct Staff Transport $ 12,625
Housing $ 14,760
Sub - Total Direct $ 225,635
Total Production Cost $ 1,038,666
Contingency $ 22,609
Head Office Allocation 0
Total Cost $ 1,061,275
Source: The authors
a) Sponsors Contribution
The Sponsors contribution for the project according to the budget is shown on table 21.
Table 21: Sponsors Contribution
Budget Item USAID JICA Governme Rotary
nt International
Sub - Total Materials $ 50,000 $ 50,000 $ 23,631 0
Sub - Total Subcontractors $ 25,000 $ 50,000 $ 10,000 $ 250,000
Sub - Total Equipment / Vehicles $ 35,000 $ 35,000 $ 4,000
Sub - Total Consumables 0 0 $ 10,000 0
Sub - Total Mobilization & Site $ 10,000 $ 12,100 0 0
Off. Running Cost
Sub - Total Eng. / Lab / $ 6,000 $ 6,000 0 0
Consultant
Sub - Total Indirect Staff $ 100,000 $ 65,000 $ 71,300
Sub - Total Direct $ 65,000 $ 100,000 $ 60,635 0
Total Production Cost $ 291,000 $ 318,100 $ 179,566 $ 250,000
Contingency $ 11,000 $ 11,609 0 0
Total Cost $ 302,000 $ 329,709 $ 179,566 $ 250,000
Sponsor Contribution % 28.46% 31.07% 16.92% 23.56%
Source: The authors
This table has been created thanks to the analysis of 3 important variables of our
construction project:
1) Mobilization Plan: Containing the costs of both direct and indirect staff divided
monthly
2) Equipment Costs: Containing all the costs of the machines used during the project
divided monthly
3) Material Costs: Containing specific material items and the relative unit of measure,
quantity, unit rate and total costs.
b) Direct and Indirect Manpower Budget
The direct and indirect manpower budget is shown in table 22
Table 22: Direct and Indirect Manpower Budget
Description Estimated Costs for Project
Duration
Indirect Manpower
Project Manager $ 39,000
Site Engineer $ 14,400
Planning Engineer $ 18,200
Cost Control Engineer $ 18,200
Quality Engineer $ 18,200
Electrical Engineer $ 18,200
Mechanical Engineer $ 18,200
QA/QC Engineer $ 15,600
HSE Dep. $ 20,700
HR Dep. $ 23,000
Warehouse Staff $ 17,600
Direct Manpower
Supervisor $ 12,000
Foreman $ 9,600
Labors $ 36,400
Carpenters $ 28,500
Steel Fixers $ 21,000
Scaffolders $ 15,000
Electricians $ 14,400
Riggers $ 15,600
Surveyors $ 16,200
Plumbers $ 14,400
Source: The authors
Direct and Indirect costs were estimated according to the histogram in Figure 11 based on
the mobilization/de-mobilization plan that will be executed.
Figure 11: Indirect and Direct Staff
40
35
30
25
20
Indirect Staff
15 Direct Staff
10
Source: The authors
c) Running Costs Breakdown
The running costs of the project are shown in table 23 based on the histogram on Figure 12
of the mobilization and demobilization of manpower and equipment of the whole project.
Table 23 estimates the Running costs breakdown for the project.
Table 23: Running Costs
Description Estimated Costs for
Project Duration
Running Costs
Food $ 15,150
Transportation $ 12,625
Housing $ 14,760
Miscellaneous $ 5,000
Travel Expenses $ 15,000
Manpower 5% $ 22,609
Contingencies
Source: The authors
Figure 12: Histogram Equipment vs Time
8
No. of Equipments
7
6
5
4
3
Equipments
2
1
0
Date
Source: The authors
d) Equipment Costs Breakdown
Table 24: Equipment Costs
Description Estimated Costs for
Project Duration
Equipment Cost
Bob Cat $ 10,800
Excavator $ 6,000
Dump Truck $ 2,400
Mobile Crane 30 Ton $ 30,000
Compressor $ 6,000
Grader $ 6,000
Roller Compactor $ 4,800
Source: The authors
e) B.O.Q
By using the architectural design layout and the Activity list of Table 17, the estimations
for the activities were made and are shown on Table 25
Table 25: Bill of Quantities
Item/Activities Unit of Quantity Unit Rate Tot. Amount (Nu)
measure
Mobilization
Cabin Total Unit 2 $ 2,310 $ 4,620
Toilette Total Unit 1 $ 450 $ 450
Offices Total Unit 1 $ 1,500 $ 1,500
Warehouse Total Unit 1 $ 5,000 $ 5,000
Temporary Fancies L.M 146 $5 $ 730
Temporary L.S 1 $ 2,500 $ 2,500
parking
Small cafeteria Total Unit 1 $ 800 $ 800
Earth works - Gatch M3 120 $3 $ 372
Fill
Concrete works M3 0
Foundations M3 55 $ 104 $ 5,720
Columns M3 9 $ 104 $ 936
Beams M3 33 $ 104 $ 3,432
Slabs M3 180 $ 104 $ 18,720
Concrete Grouting L.S 1 $ 5,000 $ 5,000
& Acc.
Reinforcement steel Tons 30 $ 640 $ 19,200
Masonry Total Unit 11,500 0 $ 5,175
Plastering works M2 1,000 $3 $ 3,000
Painting works M2 1,000 $ 14 $ 14,000
Tiling Works M2 380 $ 35 $ 13,300
HVAC VRV System Total Unit 1 $ 25,000 $ 25,000
Electrical works LS 1 $ 30,000 $ 30,000
Plumbing works LS 1 $ 10,000 $ 10,000
False Ceiling M2 360 $ 20 $ 7,200
Waterproofing M2 360 $ 35 $ 12,600
works
Solar panels Total Unit 1 $ 15,000 $ 15,000
Medical Equipment Total Unit 1 $ 250,000 $ 250,000
Aluminum louvers Total Unit 32 $ 18 $ 576
Wooden doors Total Unit 25 $ 60 $ 1,500
Fire System LS 1 $ 15,000 $ 15,000
Alco bond M2 250 $ 12 $ 3,000
Generators Total Unit 1 $ 8,000 $ 8,000
Parking and M2 400 $ 36 $ 14,400
landscape
Ambulance Total Unit 1 $ 40,000 $ 40,000
Porta Cabin Offices Total Unit 15 $ 2,000 $ 30,000
Consumables L.S 1 $ 2,500 $ 2,500
Tools L.S 1 $ 4500 $ 4,500
Safety Tools L.S 1 $ 3000 $ 3,000
Running Cost L.S 1 $ 6500 $ 6,500
Lab Testing & Third L.S 1 $ 12000 $ 12000
Parties
Source: The authors
Note: M: Meters, M2: Meters Squared, M3: Meters Cube, L.S: Lump sum
5.9 Control Cost
Control Costs is the process of monitoring the status of the project to update the project
costs and managing changes to the cost baseline. The key benefit of this process is that the
cost baseline is maintained throughout the project (PMBOK, 2017).
The following activities will be executed during the cost control process:
- Identifying the factors that create changes to the authorized cost baseline;
- Ensuring that all change requests are acted on in a timely manner;
- Ensuring that cost expenditures do not exceed the authorized funding by period, by
WBS component, by activity, and in total for the project;
- Monitoring cost performance to isolate and understand variances from the approved
cost baseline;
- Monitoring work performance against funds expended;
- Preventing unapproved changes from being included in the reported cost or resource
usage;
- Informing appropriate stakeholders of all approved changes and associated cost; and
- Bringing expected cost overruns within acceptable limits.
5.10 Control Costs: Tools and Techniques
One of the analysis selected to control cost is the earned value analysis. It compares the
performance measurement baseline to the actual schedule and cost performance. Earned
value management (EVM) integrates the scope baseline with the cost baseline and schedule
baseline to form the performance measurement baseline.
Finally, two important metrics to control costs are the schedule performance index (SPI)
and the Cost performance index (CPI).
The work performance information covers the project’s past performance and any
information that could impact the project in the future EACs are typically based on the
actual costs incurred for work completed, plus an estimate to complete (ETC) the remaining
work (PMBOK, 2017).
6 Quality Management Plan
6.1 Introduction, Scope and Purpose of the Quality Management Plan
A construction project in a remote area such as Aldea el Rosario can face many challenges
due to the uncertainty of factors such as local regulations, cultural differences, labor
shortages and unknown site conditions. The levels of responsibilities are high in each part
of the project, in which the opportunity to increase social value and improve the wellbeing
of many people. Therefore, the purpose of this quality management plan is to minimize
risks and increase the chance of success of the project.
The Project Quality Management processes that are going to be presented in this document
according to the (Project Management Institute, 2017) are:
a) Plan Quality Management Identifying quality requirements and/or standards for
the project and its deliverables, and documenting how the project will demonstrate
compliance with quality requirements and/ or standards Assessing roles and
responsibilities
b) Manage Quality: The process of translating the quality management plan into
executable quality activities that incorporate the organization’s quality policies into
the project.
c) Control Quality: The process of monitoring and recording the results of executing
the quality management activities to assess performance and ensure the project
outputs are complete, correct, and meet customer expectations
6.2 Quality Policies
For quality improvement in the project, the following actions are going to be implemented
to comply with specified Policies and Standards:
Compliance:
Identify what quality standards and processes we are going to use and in
what parts of the project.
Establish standards to achieve the desired level of performance for the
activities and the project.
Identify the desired levels of performance for the product and its
components.
Strictly complies with laws, regulations and standards defined in the
following report.
Defects:
Deliver a product with zero defects to the end user.
Maintenance of product in case of any defects.
Communication:
Hold meetings, report incidents and take measurements
Ask the client for his definition of quality.
Identify at what level the NGO is going to control the project.
Environment:
Identify a HRMS for the HR department for employees to avoid risks and
maintain a positive environment.
Make sure teams members know what quality is expected from their work.
Meet CSR requirements as defined in Business case.
Testing:
Define testing requirements according to American standards of
construction for material.
Define method statements for construction implementation and reporting.
Closing:
Collect lessons learned and update current plans for coming projects.
6.3 Reference Standards
a) ACI 318-14 code for construction specification:
The American Concrete Institute (ACI) promulgates ACI 318-83, "Building Code
Requirements for Reinforced Concrete, “the aim of building codes is to provide the
minimum public safety criteria, and this is the principle followed in the preparation of the
ACI Building Code. The code sets out appropriate techniques to design and construct
reinforced concrete houses” (Concrete Construction Staff)
b) ISO 9001 for the quality management system (QMS).
According to (Standards Stores), ISO 9001 “is the Quality Management System (QMS)
global standard. It is intended to assist businesses at many levels, including focusing on
client demands, enhancing business management, finding methods to enhance
continuously”
c) ISO/IEC Guide 71:2014 Standards and regulations.
The (International Organisation for Standadization) describes the ISO / IEC JTC 1 as “a
joint technical committee of the International Organization for Standardization (ISO) and
the IEC. Its aim is to create, preserve and encourage IT and Information and
Communications Technology (ICT) norms”
d) IEC 60364-5-51
The rules set by (International Electrotechnical Commission, 2005) are “intended to
provide for the safety of persons, livestock and property against dangers and damage which
may arise in the reasonable use of electrical installations and to provide for the proper
functioning of those installations”.
6.4 Quality Responsibilities
During projects, making sure that people are on the same page and understanding how they can
contribute becomes increasingly important. The lines of communications, expectations, and
alignment on achieving the vision of the project are critical to ensure success (Kovacevic, 2018)
The following table describes the role and responsibilities of the stakeholders involved in the
project. Moreover, the table reveals the frequency of each activity and who is charge of approving
it.
Table 26: Roles and Responsibilities
Name Role Responsibility Frequency Acceptance criteria
X Quality - Determine Quality Management Plan. - Once Client Approval
Department - Quality Metrics
- Supervision of Quality Assurance and control on site. - Once Quality Assurance Manager
- Every 7 days Approval
W Project Manager - Develop of Quality Management Plan - Once Sponsor and Client approval
- Project documents updates (Lessons learned register, - Every two weeks - Quality Assurance
Requirements traceability matrix, Risk register, - Every two weeks - Quality Assurance Manager
Stakeholder register). Approval
- Change request - As Needed - Client
- Quality Task Review, deliverables and process - As Needed - Quality Assurance Manager
Approval
89
Name Role - Responsibility - Frequency Acceptance criteria
M Technical Supervision of Quality Control at the design - During the design none
Department - Phase phase
N Sponsors Review and approval of documents - Once none
L Construction Communicating quality specs with site team - Ongoing none
Manager
Q Safety Engineer - Monitor the respect of safety rules on site, so you must - Ongoing Quality Assurance Manager
ensure that the quality of the project is compatible
with safety regulations. Informing the Project Manager
of any problems that occur in search of a better quality
that affect the safety of the project.
L Lab Technician Material Quality Assurance Once none
Source: The authors
Organizational Chart of the projects structure:
The Organizational Chart on Figure 13 shows the hierarchical structure of the NGO, which illustrates the relationships between the
departments and employees.
Figure 13: Organizational Chart
Source: The authors
6.5 Manage Quality
Once the Plan Quality Management phase is completed, it is vital to understand how to manage
quality during the project. The main inputs during this phase are:
1) Project Management Plan
2) Project Documents
3) Organizational process assets (PMBOK (2016).
6.6 Quality Control Template
During the project in data gathering, checklists will be used in every step, which is a “structured
tool, usually component-specific, used to verify that a set of required steps has been performed or to
check if a list of requirements has been satisfied” (Project Management Institute, 2017)
Based on the project’s requirements and practices, the checklist that is going to be implemented in
our project will be used during the inspections requests for information regarding site work (civil,
mechanical & electrical), material and safety, which is presented on Figure 14.
92
Figure 14: Inspection Request
Date:
El Rosario Health Clinic Time
IR No:
INSPECTION REQUEST FOR SITE WORK
Item description:
Coordination
Technical
Survey Electrical Mechanical
Construction Drawings No:
Item ready for On Next Event Start On / /
inspection At ………………………………. At :
Name Date Time Signature
Name Date Time Signature
IR received
Comments
Inspection Result
QC / Approved
Consultant
Approve
d as noted
Civil Electrical Mechanical
Name
Signature Disapproved.
Date
Source: The authors