COMMISSIONING PROCESS
1. DESCRIPTION
This Document describes the overall commissioning process of the K2S back up power project installations.
Commissioning requires the participation of all members of a Commissioning Team as described in this
Document. The goal of Commissioning is to ensure that all systems are operating in a manner consistent with
the Contract Documents. Each contractor designated as responsible for a commissioned system shall be familiar
with all parts of this Document and the responsibilities that are required of each contractor as relates to all other
Commissioning Team members. Each contractor shall be responsible for following the Commissioning Plan
prepared by the commissioning team and shall execute all Commissioning responsibilities assigned to them in
this and all other related Contract Documents.
A. Project Engineers (PEs): The prime consultant (PEs) and sub-consultants who comprise the design
team, generally the Project Mechanical designer/engineer and the Electrical designer/engineer.
B. Commissioning Lead (CL): The CL directs and coordinates the commissioning activities. The CL
does not take an oversight role. The CL is part of the project management team.
C. Commissioning Plan (CP): An overall plan that provides the structure, schedule and coordination
planning for the commissioning process.
D. Commissioning Team (CT): The members of the commissioning team consist of the Commissioning
Lead, the Project Manager, the Commissioning Team Contractor Staffs, Subcontractor’s(staffs),
equipment Vendors and the Facility owner. The owner and the plant operator/engineer also may be
members of the commissioning team.
E. Commissioning Vendors (CV): (Team Contractor) Contractors responsible for providing the systems
specified for Commissioning, General Commissioning Requirements for their installed packages, of
their respective contracts. The vendors are totally responsible for their various Subcontractors.
F. Project Manager (PM): The Person in Charge of the Construction project, acting on behalf of
MORPOL.
G. Commissioning Mechanical Engineer (CME): CME is responsible for all Commissioning activities
associated with the Mechanical contract, and all those of the subcontractors and Mechanical equipment
vendors MANTRAC for Commissioned equipment supplied under the Mechanical contract 2 x 2.5MVA
Gas Generators, including all piping installation.
H. Commissioning Electrical & Instrumentation Engineer (CEIE): CEIE is responsible for all
Commissioning activities associated with the Electrical & instrumentation contract, and all those of
J. Subcontractors (Subs): The contractors to the vendors who manufactured and provided the installed
components and systems.
L. Functional Performance Test (FT): Test of the dynamic function and operation of equipment and
systems using manual (direct observation) or monitoring methods. Functional testing is the dynamic
testing of systems (rather than just components) under full operation. Systems are tested under various
modes, such as during low cooling or heating loads, high loads, component failures, unoccupied, varying
outside air temperatures, fire alarm, power failure, etc. The CL develops the functional test procedures
in sequential written form. The CL coordinates, oversees and documents the actual testing. The
Contractor performs the functional tests. FTs are performed after pre-commissioning checklists and
startups are complete.
M. Pre-commissioning Checklist (PC): A list of items to inspect and component tests to conduct to verify
proper installation of equipment. (Covered by A check sheet)
N. Commissioning Testing (CT): Functional test procedures approved by the CL and PM to be performed
after Functional Completion and post Substantial Completion of the project. All discrepancies will be
approved for correction at a later date by the PM.
O. Commissioning Completion (CC): Final written approval by the Commissioning Lead that all
Commissioning work is complete.
1.2 SUMMARY
1. Verify that applicable equipment and systems are installed according to the manufacturer’s
recommendations and to industry accepted minimum standards and that they receive adequate
operational checkout by installing contractors.
2. Verify and document proper performance of (selected) equipment and systems.
3. Verify that O&M documentation left on site is complete.
4. Verify that the Owner’s operating personnel are adequately trained.
A. Management:
1. The CL is hired by, and works for, the Project Manager and/or Owner. The CL directs and
coordinates the commissioning activities. All Commissioning Team members work together to fulfill
their contracted responsibilities and to meet the objectives of the Contract Documents.
2. It is noted that the services for the PM and Commissioning Authority are not provided for in this
contract. That is, the Commissioning Team contractors are not responsible for providing the CL’s or
PM services. Their responsibilities and tasks are listed in this Document to clarify the commissioning
process.
B. Commissioning Process:
The following narrative provides a brief overview of the typical commissioning tasks during
construction and the general order in which they occur.
1. Commissioning begins prior to construction with a scoping meeting planned, scheduled and
conducted by the CL where the commissioning process is reviewed with the commissioning team
members. The CL will provide the initial schedule of primary commissioning events at the
commissioning scoping meeting. Meeting minutes will be distributed to all parties by the CL.
2. The CL will develop a commissioning plan to provide guidance in the execution of the
commissioning process. A draft copy of the plan will be presented at the scoping meeting for
discussion.
3. The CL will work with the Commissioning Team contractors according to established protocols to list
and schedule the commissioning activities, using his initial listing of events from the draft
Commissioning Plan as a basis. The CL will integrate all commissioning activities into the
Construction Progress or Master Schedule.
4. Additional meetings will be required throughout construction, scheduled by the CL with necessary
Commissioning Team members attending, to plan, scope, coordinate, schedule future activities and
resolve deficiencies. These meetings will be held monthly or bi-weekly during initial construction
and can increase in frequency to as often as one per week in the final months or critical periods of
each phase of construction.
5. After the initial commissioning scoping meeting the CL will update the plan which is then considered
the “final” plan, though it may be revised as the project progresses. The Contract Specifications will
take precedence over the Commissioning Plan.
6. Equipment documentation, including O&M manuals are submitted to the CL during the submittal
process, including detailed start-up procedures. The CL reviews the O&M documentation for
completeness.
7. The CL works with the Commissioning Team contractors and their subcontractors to develop startup
plans and startup documentation formats for commissioned equipment and systems. This includes
providing pre-commissioning checklists to be completed, during the startup process.
8. The CL develops specific equipment and system functional performance test procedures. The
Commissioning Team contractors and Subs review the procedures and submit suggestions or
comments. Procedures are finalized by the CL.
9. The Commissioning Team contractors and their subcontractors, under their own direction, execute
and document the pre-commissioning checklists and perform startup and initial checkout for all
1. The CL is not responsible for design concept, design criteria, compliance with codes, design or
construction scheduling, cost estimating, or construction management. The CL may assist with
problem-solving, non-conformance or deficiencies, but ultimately that responsibility resides with
the Project Manager, the Commissioning Team contractors and the PE. The primary role of the
CL is to develop and coordinate the execution of a testing plan and to observe and document that
systems are functioning in accordance with the documented design intent, in accordance with the
Contract Documents. The Contractors will provide all tools or the use of tools to start, check-out
and functionally test equipment and systems, except for specified testing with portable data-
loggers, which shall be supplied and installed by the CL.
3. Warranty Period:
a. Coordinate and supervise required seasonal or functional testing.
b. Remain on the site during the 90-Days Reliability Run and review with facility staff the
current operation and the condition of outstanding issues related to the original and seasonal
D. Project Manager:
2. Warranty Period:
a. Assist the CL as necessary in the seasonal or functional testing.
2. Warranty Period
a. Execute seasonal or functional performance testing, witnessed by the CL, according to the
specifications.
b. Ensure that Commissioning Team contractors correct deficiencies and make necessary
adjustments to O&M manuals and as-built drawings for applicable issues identified in any
seasonal testing.
F. Vendors:
1. Provide all requested submittal data, including detailed start-up procedures and specific
responsibilities for the Owner to keep warranties in force.
A. All Commissioning must be complete prior to Functional Completion, unless approved in writing by the
PM. Exceptions to this are planned system training performed after handover and any required seasonal
or approved functional testing. This includes for all systems, but is not limited to:
1. Completed and signed start-up and pre-commissioning checklist documentation.
2. Requested trend log data
3. Submission of final approved systems report.
4. Completion of all required controls work.
5. Completion of all functional testing.
6. Required training of O&M personnel completed and approved.
7. Submission of the approved O&M manuals.
8. All identified deficiencies have been corrected or are approved as exceptions to this
milestone by the PM.
B. The PM will determine the date of Functional Completion after reviewing the Commissioning
Company’s recommendation for Commissioning Completion.
2. EXECUTION
2.1 REPORTING
A. The CL will provide regular reports to the PM with increasing frequency as construction and
commissioning progresses. Standard forms will be provided and/or referenced in the Commissioning
Plan.
B. The CL will regularly communicate with all members of the commissioning team, keeping them
apprised of commissioning progress and scheduling changes through memos, progress reports, etc.
C. Testing or review approvals and non-conformance and deficiency reports are made regularly.
D. A final summary report by the CL will be provided to the PM, focusing on evaluating commissioning
process issues and identifying areas where the process could be improved. All acquired documentation,
logs, minutes, reports, deficiency lists, communications, findings, unresolved issues, etc., will be
compiled in appendices and provided with the summary report. Pre-commissioning checklists,
2.2 SUBMITTALS
A. The CL will provide appropriate contractors with a specific request for the type of submittal
documentation the CL requires facilitating the commissioning work. These requests will be integrated
into the normal submittal process and protocol of the construction team. At minimum, the request will
include the manufacturer and model number, the manufacturer’s printed installation and detailed start-up
procedures, full sequences of operation, O&M data, performance data, any performance test procedures,
control drawings, wiring diagrams and details of factory tests. In addition, the installation and checkout
materials that are shipped inside the equipment and the field checkout sheet forms to be used by the
factory or field technicians shall be submitted to the Commissioning Lead. All documentation requested
by the CL will be included by the Commissioning Team contractors in their O&M manual contributions.
B. The CL may request additional design narrative from the PE and the Commissioning Team Contractors,
depending on the completeness of the design intent documentation and sequences provided with the
Specifications.
C. The Commissioning Lead will review and approve submittals related to the commissioned equipment for
conformance to the Contract Documents as it relates to the commissioning process, to the functional
performance of the equipment and adequacy for developing test procedures. This review is intended
primarily to aid in the development of functional testing procedures and only secondarily to verify
compliance with equipment specifications. The Commissioning Lead will notify the PM of items
missing or areas that are not in conformance with Contract Documents which may affect the
commissioning and which require resubmission.
D. Submittals to the CL do not constitute compliance for O&M manual documentation. The compilation
and submission of O&M manuals is the responsibility of the Contractor. The CL will review and
approve individual O&M documents.
B. The project will require startup and initial checkout to be executed in phases. This phasing will be
planned and scheduled in a coordination meeting of the CL, PM and the Commissioning Team
contractors. Results will be added to the Construction Progress Schedule and Commissioning Plan.
C. General. Pre-commissioning checklists are important to ensure that the equipment and systems are
installed and operational. It ensures that functional performance testing (in-depth system checkout) may
proceed without unnecessary delays. The pre-commissioning testing for a given system must be
successfully completed prior to formal functional performance testing of equipment or subsystems of the
given system.
D. Start-up and Initial Checkout Plan. The CL shall assist the Commissioning Team contractors
responsible for startup of any equipment in developing detailed start-up plans. The primary role of the
CL in this process is to ensure that there is written documentation that each of the manufacturer-
recommended procedures have been completed.
G. Functional testing is intended to begin upon completion of a system. Functional testing may proceed
prior to the completion of systems or sub-systems at the discretion of the CL and PM. Beginning system
testing before full completion does not relieve the Contractor from fully completing the system,
including all pre-commissioning checklists as soon as possible.
H. The Commissioning Team contractors have start-up, pre-commissioning and functional testing
responsibility and are required to complete systems and sub-systems so they are fully functional,
meeting the design objectives of the Contract Documents. The commissioning procedures and
functional testing do not relieve or lessen this responsibility or shift that responsibility partially to the
Commissioning Company or PM.
A. This article applies to all commissioning functional testing for all divisions.
C. Test Methods.
1. Functional performance testing and verification may be achieved by manual testing (persons
manipulate the equipment and observe performance). When a control system is part of the project,
functional performance testing may use the controls to monitor the performance and analyze the
results using the control system’s trend log Capabilities or by stand-alone data loggers. The CL may
substitute specified methods or require an additional method to be executed, other than what was
specified, with the approval of the PM. The CL will determine which method is most appropriate for
tests that do not have a method specified.
2. Setup. Each function and test shall be performed under conditions that simulate actual conditions as
close as is practically possible. The Contractor executing the test shall provide all necessary
materials, system modifications, etc. to produce the necessary flows, pressures, temperatures, etc.
necessary to execute the test according to the specified conditions. At completion of the test, the
Contractor shall return all affected equipment and systems, due to these temporary modifications, to
their pre-test condition.
3. Simulated Conditions. Simulating conditions (not by an overwritten value) shall be allowed, though
timing the testing to experience actual conditions is encouraged wherever practical.
4. Overwritten Values. Overwriting sensor values to simulate a condition, such as overwriting the
outside air temperature reading in a control system to be something other than it really is, shall be
D. Problem Solving. The CL will recommend solutions to testing problems; however the burden of
responsibility to solve, correct and retest problems is with the Commissioning Team contractors,
subcontractors and PE.
A. Documentation.
1. The CL shall witness and document the results of all functional performance tests using the specific
procedural forms developed for that purpose. Prior to testing, these forms are provided to the PM for
review and approval and to the Commissioning Team contractors for review. The CL will include the
filled out forms in the Final Commissioning Report.
B. Non-Conformance.
1. The CL will record the results of the functional test on the procedure or test form. All deficiencies or
non-conformance issues shall be noted and reported to the PM.
2. Corrections of minor deficiencies identified may be made during the tests at the discretion of the CL.
In such Cases the deficiency and resolution will be documented on the procedure form.
3. Every effort will be made to expedite the testing process and minimize unnecessary delays, while not
compromising the integrity of the procedures.
4. As tests progress and a deficiency is identified, the CL discusses the issue with the executing
contractor.
a. When there is no dispute on the deficiency and the Contractor accepts responsibility to correct it:
1) The CL documents the deficiency and the Contractor’s response and intentions and they go on to
another test or sequence. The CL submits the non-compliance reports to the PM for signature, if
required. A copy is provided to the Commissioning Team contractors and CL. The
Commissioning Team contractors correct the deficiency, sign the statement of correction at the
bottom of the non-compliance form certifying that the equipment is ready to be retested and send
it back to the CL.
2) The CL reschedules the test and the test is repeated.
b. If there is a dispute about a deficiency, regarding whether it is a deficiency or who is responsible:
1) The deficiency shall be documented on the non-compliance form with the Commissioning Team
contractor’s response and a copy given to the PM and to the Commissioning Team contractor.
D. Approval:
1. The CL notes each satisfactorily demonstrated function on the test form. Formal approval of the
functional test is made later after review by the CL and by the PM, if necessary. The CL
A. The Commissioning Team contractors and CL shall be responsible for training coordination, scheduling
and ultimately for ensuring that training is completed.
B. The CL shall be responsible for reviewing and approving the content and adequacy of the training of
Owners personnel for commissioned equipment.
1. Hands-on training shall include start-up, operation in all modes possible, including manual, shut-
down and any emergency procedures and preventative maintenance for all pieces of equipment.
2. Training shall occur after functional testing is complete, unless approved otherwise by the PM.
3. Duration of Training: The Commissioning Team contractor shall provide training on each piece of
equipment according to the durations in individual equipment specifications.
A. The commissioning process generates a number of written work products described in various Sections
of the Specifications. The Commissioning Plan lists all the formal written work products, describes
briefly their contents, who is responsible to create them, their due dates, who receives and approves them
and the location of the specification to create them. In summary, the written products are:
1. Product Developed By:
a. Final Commissioning Plan: CL.
b. Commissioning Meeting Minutes: CL.
c. Commissioning Schedules: CL with Commissioning Team contractors and PM.
d. Equipment Documentation Submittals: Commissioning Team contractors.
e. Sequence Clarifications: Commissioning Team contractors and PE as needed.
f. Pre-commissioning Checklists: CL.
g. Startup and Initial Checkout Plan: Commissioning Team contractors and CL (compilation of
documents).
h. Startup and Initial Checkout Forms Filled Out: Commissioning Team contractors.
END OF SECTION