Io List

This document provides a list of instruments and their associated input/output signals for the fuel gas and water distribution systems of a 104.717 MW power plant project in Jambi, Indonesia. It includes 12 instruments such as pressure transmitters, flow transmitters, temperature transmitters, level switches, and pressure switches. For each instrument, it specifies the process and drawing, I/O signal type and range, alarm set points if any, engineering units, and other details.

Uploaded by

sswahyudi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
1K views4 pages

Io List

This document provides a list of instruments and their associated input/output signals for the fuel gas and water distribution systems of a 104.717 MW power plant project in Jambi, Indonesia. It includes 12 instruments such as pressure transmitters, flow transmitters, temperature transmitters, level switches, and pressure switches. For each instrument, it specifies the process and drawing, I/O signal type and range, alarm set points if any, engineering units, and other details.

Uploaded by

sswahyudi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

INSTRUMENT I/O LIST FUEL GAS SYSTEM, WATER

DISTRIBUTION SYSTEM

PT. PLN (PERSERO)


PEMBANGKITAN SUMBAGSEL

PROYEK PLTMG SEI GELAM


104.717 MW JAMBI

CONTRACT NO. : 055.PJ/610/GM-KITSBS/2012


001/KONTRAK/PLTMGJAMBI/PP-IFE/2012

PLN’s DOC. NO. : -

PURPOSE :

FOR APPROVAL

2 Re Issued for Construction 20/11/12 ATR NS/MH HYT / AI


1 Issued for Construction 31/07/12 KDR NS/MH HYT / AI
0 Issued for Approval 17/04/12 KDR NS/MH HYT / AI

Rev. Description Date Prepared Checked Approved

CONTRACTOR:
Doc. No.:

SG-E-00-J0-IX-102B

REV
Page No:
Konsorsium PP 2
1 of 4
SHEET 2 OF 4

REV
DOC. NO. :
SG-E-00-J0-IX-102B 2
INSTRUMENT I/O LIST FUEL
GAS SYSTEM, WATER
DATE BY CHKD APVD
Konsorsium PP DISTRIBUTION SYSTEM
20/11/12 ATR NS/MH HYT/AI

REVISION HISTORICAL SHEET

Rev No Date Description


0 17/04/12 Issued for Approval
1 31/07/12 Issued for Construction

2 20/11/12 Re Issued for Construction


PAGE 3 OF 4

LEGEND I/O LIST

No SERVICE ALARM & SET POINT


Serial Number Reference Process in the Project Alarm and Set Point on System
LL : Low Low Alarm
L : Low Alarm
SP : Set Point
H : High Alarm
TAG Number INPUT / OUTPUT (I/O) SIGNAL HH : High High Alarm
- Field/Outer Instrument TAG Number Engineering Signal Input/Output
AI : Analog Input
AO : Analog Output
DI : Digital Input
DO : Digital Output Eng. Unit
P&ID DRAWING Engineering Unit of Project
Description of Field Instrument or System 220VAC : Wet Contact 220VAC
24VDC : Wet Contact 24VDC
DRY : Dry Contact

LOCATION FROM / TO
Location of Signal Coming from / Going to
DCS : Process Control System Range L & H
MCC : Motor Control Center For Analog I/O Signal
FIELD : In the Field L : Low range (0%)
H : High range (100%)
PAGE 4 OF 4

INSTRUMENT I/O LIST


FUEL GAS SYSTEM AND WATER DISTRIBUTION SYSTEM

Konsorsium PP REV 2
PROJECT : PROYEK PLTMG SEI GELAM 104.717 MW JAMBI DATE 20-Nov-12
DOC NO. : SG-E-00-J0-IX-102B BY ATR
JOB NO. : - CHK NS/MH
CLIENT : PT. PLN (PERSERO) PEMBANGKIT SUMBAGSEL APV HYT/AI

Location I/O Range Alarm and Set Point


P&ID NO.
NO. TAG NUMBER INSTRUMENT DESCRPTION Eng. Unit Remark
DRAWING NO. From To SERVICE Signal Type L H LL L SP H HH

FUEL GAS SYSTEM


1 PT- 03 SG-E-01-P1-EF-001A Pressure Transmitter Field DCS Fuel Gas From CNG/Gas Filter to Gas regulator AI 4-20 mA - - - - - - - Kg/cm2 Metering System
2 FT-01 SG-E-01-P1-EF-001A Flow Transmiter Field DCS Fuel Gas From CNG/Gas Filter to Gas regulator AI 4-20 mA - - - - - - - M3/hr Metering System
3 TT-01 SG-E-01-P1-EF-001A Temperature Transmitter Field DCS Fuel Gas From CNG/Gas Filter to Gas regulator AI 4-20 mA - - - - - - - Deg C Metering System
4 PT-08 SG-E-01-P1-EF-001A Pressure Transmitter Field DCS Fuel Gas From CNG/Gas Filter to Gas regulator AI 4-20 mA 0 10 - - - - - Kg/cm2
5 PT-02 SG-E-01-P1-EF-001A Pressure Transmitter Field DCS Fuel Gas From CNG/Gas Filter to Gas regulator AI 4-20 mA 0 10 - - 7.03 - - Kg/cm2
6 PY-02 SG-E-01-P1-EF-001A I/P Converter DCS Field Fuel Gas From CNG/Gas Filter to Gas regulator A0 4-20 mA - - - - - - -
WATER DISTRIBUTION SYSTEM
7 LS-03 SG-E-01-P1-EF-003 Level switch High/Low Field DCS Level at Tank Fresh Water Tank at SG-T-001 DI DRY - - - 500 - 2000 -
8 PSHH-03A SG-E-01-P1-EF-003 Pressure Switch High High Field DCS Pressure discharge SG-P-01A DI DRY - - - - - - 4.3 Kg/cm2
9 PSHH-03B SG-E-01-P1-EF-003 Pressure Switch High High Field DCS Pressure discharge SG-P-01B DI DRY - - - - - - 4.3 Kg/cm2
10 LSHH-XXX SG-E-01-P1-EF-004 Level Switch High High Field DCS Level at Fire Water Tank DI DRY - - - - - - - by Wartsila
11 LSL-XXX SG-E-01-P1-EF-004 Level Switch Low Field DCS Level at Fire Water Tank DI DRY - - - - - - - by Wartsila
12 LSL-04 SG-E-01-P1-EF-004 Level Switch Low Field DCS Level at deep well pump DI DRY - - - - - - -

PCS
Analog Input 5
Analog Output 1
Digital Input 6
Digital Output 0