Bungo II Bridge Cone Test Report

This document summarizes the results of dynamic cone penetrometer tests conducted at multiple locations along a road construction project in Bungo Regency, Indonesia. The tests were performed to evaluate the soil strength and structural properties at depths of 0 to 50 cm below the surface. Test results included penetration resistance values, soil types, and cumulative blow counts at each test location. The document was signed by the site inspector, lab technician, and quality control contractor to approve the test results.

Uploaded by

Setiawan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
86 views12 pages

Bungo II Bridge Cone Test Report

This document summarizes the results of dynamic cone penetrometer tests conducted at multiple locations along a road construction project in Bungo Regency, Indonesia. The tests were performed to evaluate the soil strength and structural properties at depths of 0 to 50 cm below the surface. Test results included penetration resistance values, soil types, and cumulative blow counts at each test location. The document was signed by the site inspector, lab technician, and quality control contractor to approve the test results.

Uploaded by

Setiawan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd

REPUBLIK INDONESIA

DEPARTEMANT PEKERJAAN UMUM


DIREKTORAT JENDERAL BINA MARGA
KEGIATAN PEMBANGUNAN JALAN DAN JEMBATAN KABUPATEN BUNGO
PAKET : JEMBATAN BUNGO II

SCALA DYNAMIC CONE PENETROMETER TEST

Link Name : Date of testing : / /2019


Type of Work :
Location :

KM. 134+150 (kiri) KM. 134+200 (kanan) KM. 134+250 (kiri)


RIGID PAVEMENT RIGID PAVEMENT RIGID PAVEMENT RIGID PAVEMENT
axt axt axt axt
TYPE t (cm) a TYPE t (cm) a TYPE t (cm) a TYPE t (cm) a
2.54 2.54 2.54 2.54
38.00 41.00 39.00

STRUCTURAL NO. STRUCTURAL NO. STRUCTURAL NO. STRUCTURAL NO.


R D DD SPP R D DD SPP R D DD SPP R D DD SPP
0 0.00 0 0.00 0 0.00 0
5 13.00 5 9.80 5 14.20 5
10 28.40 10 27.10 10 25.50 10
15 43.40 15 39.40 15 42.20 15
20 58.50 20 59.40 20 59.30 20
25 73.60 25 74.50 25 77.60 25
30 30 30 30

CUMULATIVE NO OF BLOW CUMULATIVE NO OF BLOW CUMULATIVE NO OF BLOW


0 5 10 15 20 25 30 35 40 45 50 0 5 10 15 20 25 30 35 40 45 50 0 5 10 15 20 25 30 35 40 45 50
0 1 0 1 0 1

10 10 10

20 20 20

30 30 30

40 40 40

50 50 50

60 60 60

70 70 70

80 80 80

90 90 90
CUMULATIVE NO OF BLOW CUMULATIVE NO OF BLOW
0 5 10 15 20 25 30 35 40 45 50 0 5 10 15 20 25 30 35 40 45 50 CUMULATIVE NO OF BLOW
0 0

10 10

20 20

30 30

40 40

50 50

60 60

70 70

80 80

90 90

Disetujui oleh, Diperiksa oleh, Dikerjakan oleh,


PELAKSANA KEGIATAN KONSULTAN KONTRAKTOR

( Ade Kurnia, ST. ) ( Sugiyanto ) ( Al Azhar Chan )


Site Inspector Lab Teknisi Quality Control

[Link]
REPUBLIK INDONESIA
DEPARTEMANT PEKERJAAN UMUM
DIREKTORAT JENDERAL BINA MARGA
KEGIATAN PEMBANGUNAN JALAN DAN JEMBATAN KABUPATEN BUNGO
PAKET : JEMBATAN BUNGO II

SCALA DYNAMIC CONE PENETROMETER TEST

Link No. : Date of testing : / /2019


Link Name :
Type of Work :

KM. 129+050 (kiri) KM. 129+100 (kanan) KM. 129+150 (kiri) KM. 129+200 (kanan)
OVERLYING PAVEMENT OVERLYING PAVEMENT OVERLYING PAVEMENT OVERLYING PAVEMENT
axt axt axt axt
TYPE t (cm) a TYPE t (cm) a TYPE t (cm) a TYPE t (cm) a
2.54 2.54 2.54 2.54
43.00 41.00 39.00 42.00

STRUCTURAL NO. STRUCTURAL NO. STRUCTURAL NO. STRUCTURAL NO.


R D DD SPP R D DD SPP R D DD SPP R D DD SPP
0 0.00 0 0.00 0 0.00 0 0.00
5 9.10 5 12.70 5 11.50 5 10.50
10 22.40 10 28.30 10 25.60 10 17.30
15 40.60 15 38.40 15 40.10 15 36.80
20 58.70 20 55.30 20 59.40 20 55.80
25 76.80 25 63.30 25 78.20 25 74.90
30 30 84.20 30 30

CUMULATIVE NO OF BLOW CUMULATIVE NO OF BLOW CUMULATIVE NO OF BLOW


0 5 10 15 20 25 30 35 40 45 50 0 5 10 15 20 25 30 35 40 45 50 0 5 10 15 20 25 30 35 40 45 50
0 1 0 1 0 1

10 10 10

20 20 20

30 30 30

40 40 40

50 50 50

60 60 60

70 70 70

80 80 80

90 90 90
CUMULATIVE NO OF BLOW CUMULATIVE NO OF BLOW
0 5 10 15 20 25 30 35 40 45 50 0 5 10 15 20 25 30 35 40 45 50
CUMULATIVE NO OF BLOW
0 1 0

10 10

20 20

30 30

40 40

50 50

60 60

70 70

80 80

90 90

Disetujui oleh, Diperiksa oleh, Dikerjakan oleh,


PELAKSANA KEGIATAN KONSULTAN KONTRAKTOR

( Ade Kurnia, ST. ) ( Sugiyanto ) ( Zulkarnaen )


Site Inspector Lab Teknisi Quality Control

[Link]
REPUBLIK INDONESIA
DEPARTEMANT PEKERJAAN UMUM
DIREKTORAT JENDERAL BINA MARGA
KEGIATAN PEMBANGUNAN JALAN DAN JEMBATAN KABUPATEN BUNGO
PAKET : JEMBATAN BUNGO II

SCALA DYNAMIC CONE PENETROMETER TEST

Link No. Date of testing : / /2019


Link Name :
Type of Work :

KM. 129+250 (kiri) KM. 129+300 (kanan) KM. 129+350 (kiri)


OVERLYING PAVEMENT OVERLYING PAVEMENT OVERLYING PAVEMENT OVERLYING PAVEMENT
axt axt axt axt
TYPE t (cm) a TYPE t (cm) a TYPE t (cm) a TYPE t (cm) a
2.54 2.54 2.54 2.54
37.00 43.00 41.00

STRUCTURAL NO. STRUCTURAL NO. STRUCTURAL NO. STRUCTURAL NO.


R D DD SPP R D DD SPP R D DD SPP R D DD SPP
0 0.00 0 0.00 0 0.00 0
5 12.00 5 14.00 5 13.00 5
10 28.00 10 31.00 10 30.00 10
15 46.00 15 49.00 15 50.00 15
20 57.00 20 62.00 20 58.00 20
25 62.00 25 71.00 25 67.00 25
30 30 30 30

CUMULATIVE NO OF BLOW CUMULATIVE NO OF BLOW CUMULATIVE NO OF BLOW


0 5 10 15 20 25 30 35 40 45 50 0 5 10 15 20 25 30 35 40 45 50 0 5 10 15 20 25 30 35 40 45 50
0 1 0 1 0 1

10 10 10

20 20 20

30 30 30

40 40 40

50 50 50

60 60 60

70 70 70

80 80 80

90 90 90
CUMULATIVE NO OF BLOW CUMULATIVE NO OF BLOW
0 5 10 15 20 25 30 35 40 45 50 0 5 10 15 20 25 30 35 40 45 50 CUMULATIVE NO OF BLOW
0 0

10 10

20 20

30 30

40 40

50 50

60 60

70 70

80 80

90 90

Disetujui oleh, Diperiksa oleh, Dikerjakan oleh,


PELAKSANA KEGIATAN KONSULTAN KONTRAKTOR

( Ade Kurnia, ST. ) ( Sugiyanto ) ( Zulkarnaen )


Site Inspector Lab Teknisi Quality Control
[Link]
[Link]
REPUBLIK INDONESIA
DEPARTEMANT PEKERJAAN UMUM
DIREKTORAT JENDERAL BINA MARGA
KEGIATAN PEMBANGUNAN JALAN DAN JEMBATAN KABUPATEN BUNGO
PAKET : JEMBATAN BUNGO II

SCALA DYNAMIC CONE PENETROMETER TEST

Link No. Date of testing : / /2019


Link Name :
Type of Work :

KM. 129+900 (kiri) KM. 129+950 (kanan) KM. 130+000 (kiri) KM. 130+050 (kanan)
OVERLYING PAVEMENT OVERLYING PAVEMENT OVERLYING PAVEMENT OVERLYING PAVEMENT
axt axt axt axt
TYPE t (cm) a TYPE t (cm) a TYPE t (cm) a TYPE t (cm) a
2.54 2.54 2.54 2.54
38.00 37.00 44.00 42.00

STRUCTURAL NO. STRUCTURAL NO. STRUCTURAL NO. STRUCTURAL NO.


R D DD SPP R D DD SPP R D DD SPP R D DD SPP
0 0.00 0 0.00 0 0.00 0 0.00
5 13.00 5 8.00 5 11.00 5 14.00
10 22.00 10 18.00 10 26.00 10 26.00
15 36.00 15 31.00 15 41.00 15 39.00
20 46.00 20 48.00 20 55.00 20 54.00
25 61.00 25 56.00 25 68.00 25 62.00
30 79.00 30 30 76.00 30

CUMULATIVE NO OF BLOW CUMULATIVE NO OF BLOW CUMULATIVE NO OF BLOW


0 5 10 15 20 25 30 35 40 45 50 0 5 10 15 20 25 30 35 40 45 50 0 5 10 15 20 25 30 35 40 45 50
0 1 0 1 0 1

10 10 10

20 20 20

30 30 30

40 40 40

50 50 50

60 60 60

70 70 70

80 80 80

90 90 90
CUMULATIVE NO OF BLOW CUMULATIVE NO OF BLOW
0 5 10 15 20 25 30 35 40 45 50 0 5 10 15 20 25 30 35 40 45 50 CUMULATIVE NO OF BLOW
0 1 0

10 10

20 20

30 30

40 40

50 50

60 60

70 70

80 80

90 90

Disetujui oleh, Diperiksa oleh, Dikerjakan oleh,


PELAKSANA KEGIATAN KONSULTAN KONTRAKTOR

( Ade Kurnia, ST. ) ( Sugiyanto ) ( Zulkarnaen )


Site Inspector Lab Teknisi Quality Control
[Link]
[Link]
REPUBLIK INDONESIA
DEPARTEMANT PEKERJAAN UMUM
DIREKTORAT JENDERAL BINA MARGA
KEGIATAN PEMBANGUNAN JALAN DAN JEMBATAN KABUPATEN BUNGO
PAKET : JEMBATAN BUNGO II

SCALA DYNAMIC CONE PENETROMETER TEST

Link No. Date of testing : / /2019


Link Name :
Type of Work :

KM. 130+100 (kiri) KM. 130+150 (kanan)


OVERLYING PAVEMENT OVERLYING PAVEMENT OVERLYING PAVEMENT OVERLYING PAVEMENT
axt axt axt axt
TYPE t (cm) a TYPE t (cm) a TYPE t (cm) a TYPE t (cm) a
2.54 2.54 2.54 2.54
36.00 41.00

STRUCTURAL NO. STRUCTURAL NO. STRUCTURAL NO. STRUCTURAL NO.


R D DD SPP R D DD SPP R D DD SPP R D DD SPP
0 0.00 0 0.00 0
5 11.00 5 13.00 5
10 23.00 10 26.00 10
15 34.00 15 40.00 15
20 46.00 20 55.00 20
25 60.00 25 70.00 25
30 76.00 30 30

CUMULATIVE NO OF BLOW CUMULATIVE NO OF BLOW CUMULATIVE NO OF BLOW


0 5 10 15 20 25 30 35 40 45 50 0 5 10 15 20 25 30 35 40 45 50 0 5 10 15 20 25 30 35 40 45 50
0 1 0 1 0

10 10 10

20 20 20

30 30 30

40 40 40

50 50 50

60 60 60

70 70 70

80 80 80

90 90 90
CUMULATIVE NO OF BLOW CUMULATIVE NO OF BLOW
0 5 10 15 20 25 30 35 40 45 50 0 5 10 15 20 25 30 35 40 45 50 CUMULATIVE NO OF BLOW
0 0

10 10

20 20

30 30

40 40

50 50

60 60

70 70

80 80

90 90

Disetujui oleh, Diperiksa oleh, Dikerjakan oleh,


PELAKSANA KEGIATAN KONSULTAN KONTRAKTOR

( Ade Kurnia, ST. ) ( Sugiyanto ) ( Zulkarnaen )


Site Inspector Lab Teknisi Quality Control
[Link]
[Link]
REPUBLIK INDONESIA
DEPARTEMANT PEKERJAAN UMUM
DIREKTORAT JENDERAL BINA MARGA
KEGIATAN PEMBANGUNAN JALAN DAN JEMBATAN KABUPATEN BUNGO
PAKET : JEMBATAN BUNGO II

SCALA DYNAMIC CONE PENETROMETER TEST

Link No. : Date of testing : / /2019


Link Name :
Type of Work :

KM. 132+050 (kiri) KM. 132+100 (kanan) KM. 132+150 (kiri) KM. 132+200 (kanan)
OVERLYING PAVEMENT OVERLYING PAVEMENT OVERLYING PAVEMENT OVERLYING PAVEMENT
axt axt axt axt
TYPE t (cm) a TYPE t (cm) a TYPE t (cm) a TYPE t (cm) a
2.54 2.54 2.54 2.54
36.00 39.00 41.00 40.00

STRUCTURAL NO. STRUCTURAL NO. STRUCTURAL NO. STRUCTURAL NO.


R D DD SPP R D DD SPP R D DD SPP R D DD SPP
0 0.00 0 0.00 0 0.00 0 0.00
5 13.00 5 15.00 5 14.00 5 11.00
10 27.00 10 34.00 10 28.00 10 24.00
15 41.00 15 48.00 15 42.00 15 39.00
20 57.00 20 60.00 20 56.00 20 54.00
25 74.00 25 72.00 25 70.00 25 66.00
30 30 30 30

CUMULATIVE NO OF BLOW CUMULATIVE NO OF BLOW CUMULATIVE NO OF BLOW


0 5 10 15 20 25 30 35 40 45 50 0 5 10 15 20 25 30 35 40 45 50 0 5 10 15 20 25 30 35 40 45 50
0 1 0 1 0 1

10 10 10

20 20 20

30 30 30

40 40 40

50 50 50

60 60 60

70 70 70

80 80 80

90 90 90
CUMULATIVE NO OF BLOW CUMULATIVE NO OF BLOW
0 5 10 15 20 25 30 35 40 45 50 0 5 10 15 20 25 30 35 40 45 50 CUMULATIVE NO OF BLOW
0 1 0

10 10

20 20

30 30

40 40

50 50

60 60

70 70

80 80

90 90

Disetujui oleh, Diperiksa oleh, Dikerjakan oleh,


PELAKSANA KEGIATAN KONSULTAN KONTRAKTOR

( Ade Kurnia, ST. ) ( Sugiyanto ) ( Zulkarnaen )


Site Inspector Lab Teknisi Quality Control
[Link]
[Link]
REPUBLIK INDONESIA
DEPARTEMANT PEKERJAAN UMUM
DIREKTORAT JENDERAL BINA MARGA
KEGIATAN PEMBANGUNAN JALAN DAN JEMBATAN KABUPATEN BUNGO
PAKET : JEMBATAN BUNGO II

SCALA DYNAMIC CONE PENETROMETER TEST

Link No. : Date of testing : 30-Apr-07


Link Name :
Type of Work :

KM. 133+500 (kiri) KM. 133+550 (kanan) KM. 133+600 (kiri) KM. 133+650 (kanan)
OVERLYING PAVEMENT OVERLYING PAVEMENT OVERLYING PAVEMENT OVERLYING PAVEMENT
axt axt axt axt
TYPE t (cm) a TYPE t (cm) a TYPE t (cm) a TYPE t (cm) a
2.54 2.54 2.54 2.54
39.00 38.00 37.00 42.00

STRUCTURAL NO. STRUCTURAL NO. STRUCTURAL NO. STRUCTURAL NO.


R D DD SPP R D DD SPP R D DD SPP R D DD SPP
0 0.00 0 0.00 0 0.00 0 0.00
5 10.00 5 10.00 5 12.00 5 8.00
10 22.00 10 23.00 10 26.00 10 21.00
15 35.00 15 34.00 15 42.00 15 33.00
20 48.00 20 52.00 20 56.00 20 49.00
25 63.00 25 74.00 25 70.00 25 65.00
30 30 30 30

CUMULATIVE NO OF BLOW CUMULATIVE NO OF BLOW CUMULATIVE NO OF BLOW


0 5 10 15 20 25 30 35 40 45 50 0 5 10 15 20 25 30 35 40 45 50 0 5 10 15 20 25 30 35 40 45 50
0 1 0 1 0 1

10 10 10

20 20 20

30 30 30

40 40 40

50 50 50

60 60 60

70 70 70

80 80 80

90 90 90
CUMULATIVE NO OF BLOW CUMULATIVE NO OF BLOW
0 5 10 15 20 25 30 35 40 45 50 0 5 10 15 20 25 30 35 40 45 50 CUMULATIVE NO OF BLOW
0 1 0

10 10

20 20

30 30

40 40

50 50

60 60

70 70

80 80

90 90

Disetujui oleh, Diperiksa oleh, Dikerjakan oleh,


PELAKSANA KEGIATAN KONSULTAN KONTRAKTOR

( Ade Kurnia, ST. ) ( Sugiyanto ) ( Zulkarnaen )