33kV Substation Installation Costs

1. The document is a proposal and price quote for electrical and civil works for a new 2MVA 11/33kV substation and associated feeders. 2. It includes supply and installation of a power transformer, outdoor switchgear, indoor switchgear panels, protection equipment, battery bank, control cables, and civil works for the switchyard area. 3. The total proposed price is 120.6 million, excluding VAT. This covers the costs for all electromechanical equipment, installation, testing and commissioning works, and "As Built" drawings.

Uploaded by

ben
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
283 views2 pages

33kV Substation Installation Costs

1. The document is a proposal and price quote for electrical and civil works for a new 2MVA 11/33kV substation and associated feeders. 2. It includes supply and installation of a power transformer, outdoor switchgear, indoor switchgear panels, protection equipment, battery bank, control cables, and civil works for the switchyard area. 3. The total proposed price is 120.6 million, excluding VAT. This covers the costs for all electromechanical equipment, installation, testing and commissioning works, and "As Built" drawings.

Uploaded by

ben
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

1

CUMMINS POWER GENERATION


PROPOSED ABA MV S/S ASSOCIATED WORKS

2 MVA 11/33KV TRANSFORMER/FEEDERS MV WORKS


ELECTROMECHANICAL/CIVIL WORKS
ON-SHORE PRICES
Qty
S/N DESCRIPTION unit Unit Price Sub-Total Erection & Services GRAND TOTAL

(a) (b) c=(a*b) (d)

E1
POWER TRANSFORMER
Supply and Installation of 1x2MVA 33/11kV Transformer (European
1 No 1 11,000,000 1,200,000 12,200,000
Made) MAKE: SCHEIDER ELECTRIC/ABB 11,000,000

E2 OUTDOOR EQUIPMENT AND STRUCTURES

1 Supply and Installation of 33kV outdoor circuit breaker. No 6 3,200,000 19,200,000 3,000,000 22,200,000

2 Supply and installation of 33kV 3-phase isolator. Set 12 600,000 7,200,000 1,800,000 9,000,000

3 Supply and installation of 33kv 3-phase isolator/earthing Switch No 1 1,050,000 1,050,000 300,000 1,350,000
Supply of materials and Construction of 33kV gantry with all support
4 structures (galvanized steel lattice structures) and Lot 6 1,800,000 10,800,000 1,500,000 12,300,000
Clamps/Connections with 150mm2 ACSR. Conductor
5 Supply and Installation of 33KV Outdoor VT Set 1 1,600,000 1,600,000 150,000 1,750,000

6 Installation of 33KV 4x300/1/1/1A outdoor CT Set 6 1,600,000 9,600,000 900,000 10,500,000

7 Supply and Installation of 33KV Surge Arrester Set 2 200,000 400,000 150,000 550,000

8 Supply and Installation of Sky shield wire and lightning spike Lot 1 750,000 750,000 100,000 850,000

Substation earthing complete with earthing pit,earthing


9 Lot 1 1,850,000 1,850,000 200,000 2,050,000
mat,rods,clamps and copper conductor.

SUB TOTAL 72,750,000

E3 INDOOR AND PROTECTION EQUIPMENT

Supply and Installation of ABB 11KV, 4 Panel indoor switchgear panels


1 Set 1 15,000,000 15,000,000 1,050,000 16,050,000
made up of 1No. Incomer,1No Bus Section and 2No Outgoing Panels.
Supply and Installation of battery bank and charger unit complete
2 Set 1 2,000,000 2,000,000 200,000 2,200,000
with the rack.

3 Supply and Installation of Transformer control/relay panel No 1 2,000,000 2,000,000 300,000 2,300,000

4 Supply and Installation of Feeder control/relay panel No 5 2,000,000 10,000,000 1,500,000 11,500,000

5 Supply, laying, termination of Control Cables Mtr LOT 2,550,000 2,550,000 550,000 3,100,000

6 Installation of Protection Scheme lot 1 1,500,000 1,500,000

7 HV Insulating rubber mat(11KV side) Lot 1 80,000 80,000 80,000

Note: Cables quote not included (quantities not known)

SUB TOTAL 36,730,000

CIVIL WORKS - EXTERNAL WORKS / SWITCH YARD


PREPARATION
1
Privision for Reinforced concrete Power Transformer plinth lot 1 720,000 720,000.00 720,000.00

2 Level and compact Switchyard area to receive concrete lot 1 300,000 300,000.00 300,000.00
3 Provision for anti-weed over the whole surface Switch Yard area .
lot 1 1,850,000 1,850,000.00 1,850,000.00
Supply and spread along switch Yard /driveway, graded granite with
4
appropriate concrete kerbs 1 850,000 850,000.00 850,000.00
5
Provision for Gantry foundation civil work lot 1 1,200,000 1,200,000.00 1,200,000.00
6
Provision for Cable trench from proposd Switchroom to Trafo Plinth area lot 1 1,650,000 1,650,000.00 1,650,000.00
7
Provision for reinforced concrete retaining wall and Drainage lot 1 3,500,000 3,500,000.00 3,500,000.00

SUB TOTAL 10,070,000.00


2

ON-SHORE PRICES
Qty
S/N DESCRIPTION unit Unit Price Sub-Total Erection & Services GRAND TOTAL

(a) (b) c=(a*b) (d)

E4 TESTS, COMMISSIONING AND DRAWINGS

1 Testing and commissioning of the entire substation/Feeder works. Lot 1 850,000 850,000 850,000

"As Built" drawings of all relevant wirings, settings with all operation and
2 Lot 1 400,000 400,000 200,000
maintenance manuals both hard and electronic copies (6 sets)

SUB TOTAL 1,050,000

TOTAL (EXCLUDING VAT) 120,600,000